[2020] QCAT 307
General information, not legal advice.
Queensland Civil and Administrative Tribunal
2020-08-12
Original judgment source is linked above.
ADMINISTRATIVE LAW - ADMINISTRATIVE TRIBUNALS - QUEENSLAND CIVIL AND ADMINISTRATIVE TRIBUNAL - where direction to rectify issued - where decision made that building work undertaken at the direction of the Commission is not of a satisfactory standard - whether the time to comply with the direction was extended - where no physical work done to rectify the defective work - whether 'reviewable decision' - consideration of Tribunal's review jurisdiction generally - meaning of 'building work' - whether building work undertaken at the direction of the Commission is of a satisfactory standard
Queensland Building and Construction Commission Act 1991 (Qld), s 72, s 72B, s 86, , Schedule 2, (Qld), , , ,
Briginshaw v Briginshaw [1938] HCA 34; (1938) 60 CLR 336
CTP Plumbing and Maintenance Pty Ltd t/as Charlie the Plumber v Queensland Building and Construction Commission [2019] QCAT 409
JM Kelly (Project Builders) Pty Ltd v Queensland Building Services Authority [2013] QCAT 502
Kehl v Board of Professional Engineers of Queensland [2010] QCATA 58
Project Blue Sky Inc v Australian Broadcasting Authority (1998) 194 CLR 355
C Low, Legal Officer, Queensland Building and Construction Commission
The installation of the new hot water unit into the existing services cupboard is non-compliant with AS3500.4 (Plumbing Code of Australia) and the Queensland Plumbing & Wastewater Code in that water from the HW unit and AC to the dwelling is being discharged directly into the safe tray resulting in pooling of water within the safe tray which is wetting timber packers and causing rusting to occur - pertains to item 1 on QBCC complaint form.[13]
s 72AA(2) of the QBCC Act and argued that a person must not obstruct another person from rectifying the building work. Further to that Mr Scerri argued that the building work was obstructed by the homeowner and CTP should not be penalised by the homeowner who did not grant them access to the property. Mr Scerri argued that the building work was of a satisfactory standard and stated that although CTP did not make the HWU compliant to start with he tried to do everything right and CTP should not be held responsible.
Preliminary issue - is there a reviewable decision?
...QBCC has taken into consideration all your circumstances and in best interests of achieving a desirable outcome for everyone involved QBCC has approved an EOT for CTP to comply with the DTR to the 30th August 2018.
After which time if the matter has not been resolved by way of agreement or rectification works QBCC will issue a FTR and infringement notice. This is on the basis that all attempts by CTP have been made to gain access to the premises and the owner grants reasonable access within the timeframe.[26]
An act done in breach of a condition regulating the exercise of a statutory power is not necessarily invalid and of no effect. Whether it is depends upon whether there can be discerned a legislative purpose to invalidate any act that fails to comply with the condition. The existence of the purpose is ascertained by reference to the language of the statute, its subject matter and objects, and the consequences for the parties of holding void every act done in breach of the condition. ...[29]
s 86(1)(f) of the QBCC Act.[32]
s 24 of the QCAT Act, are to confirm or amend the decision; set aside the decision and substitute its own decision; or set aside the decision and return the matter for reconsideration to the decision-maker for the decision, with the directions the Tribunal considers appropriate.[34]
Was any building work undertaken by CTP during the rectification period?
(b) Providing professional advice to the homeowner regarding the options available to rectify the alleged defect;
(c) Seeking instructions from the homeowner on his preferred decision;
(d) Making offers to carry out the work discussed and seeking access albeit unsuccessfully, to the homeowner's property; and
(e) Attending the homeowner's property to inspect the HWU, take measurements and to work out solutions suitable for rectification.[35]
Was any building work undertaken at the direction of the Commission of a satisfactory standard?
[3] Hearing Brief ('Exhibit 1'), Response to miscellaneous matters filed by the applicant dated 2 June 2020, Part 11. At the oral hearing, CTP abandoned its application for further orders that the demerit points incurred as a result of the direction to rectify be reversed and the fine paid be refunded.
[4] Tribunal Directions dated 21 May 2020.
[7] Kehl v Board of Professional Engineers of Queensland [2010] QCATA 58, [9].
[9] See Briginshaw v Briginshaw [1938] HCA 34; (1938) 60 CLR 336, 361-362.
[10] The decision-maker must file a written statement of the reasons and any material relevant to the review pursuant to s 21(2) of the QCAT Act.
[12] Exhibit 1, Written submissions of the respondent, Tab 12, p 2.
[20] CTP v Plumbing and Maintenance Pty Ltd t/as Charlie the Plumber v Queensland Building and Construction Commission [2019] QCAT 409; see Exhibit 1.
[35] See Exhibit 2. Mr Scerri gave oral evidence at the hearing about his attendance on 13 August 2018 at the homeowner's property to inspect the HWU.
[38] QBCC Act, Schedule 2 (definition of 'building work' paras (f) and (fa)).
[40] See JM Kelly (Project Builders) Pty Ltd v Queensland Building Services Authority [2013] QCAT 502.
CTP Plumbing and Maintenance Pty Ltd t/as Charlie the Plumber
Queensland Building and Construction Commission [2020] QCAT 307
(1938) 60 CLR 336
(1998) 194 CLR 355