[2025] WADC 23
General information, not legal advice.
District Court of WA
2025-04-10
Original judgment source is linked above.
(a) The terms of the gentlemen's agreement or side deal set out in the Defence differed from Mr De Coppi's oral evidence about its terms. Further, in his oral evidence the nature of that agreement or deal varied. In his oral evidence there were three variations of the agreement or deal. The discrepancies are significant. When cross-examined about the discrepancies Mr De Coppi suggested the terms of the gentlemen's agreement or side deal as pleaded in the Defence and the terms he gave evidence about were predominantly the same thing. I am unable to accept that contention. The existence of the discrepancies alone makes it impossible to accept Mr De Coppi's evidence that a gentlemen's agreement or side deal existed. Further, even if I had been satisfied of the existence of a gentlemen's agreement or side deal, I would have been unable to be satisfied as to its precise terms.
(b) Each of the five progress claims made by Emirge was for the total amount for that stage of construction and not for only the bank finance amount, which is inconsistent with Mr De Coppi's evidence that he was not required to pay the amounts specified in the 'Clients deposit held / released to builder' column of the Progress Claim Schedule. When questioned about this during the course of his closing submissions, Mr De Coppi accepted that Emirge issued the progress claims to him and he was responsible for liaising with Pepper to have them paid. I am satisfied from all the material before me that Mr De Coppi did not challenge any of the five progress claims made by Emirge on the basis they should have been only for the bank finance amount. I am also satisfied that Mr De Coppi submitted each of the five progress claims to Pepper for payment. His failure to challenge the amount of each progress claim is inconsistent with a gentlemen's agreement or side deal with terms that he was not required to pay Emirge the sum in respect of each progress claim specified in the column headed 'Clients deposit held / released to builder'.
(c) Despite the figures set out in the Progress Claim Schedule, an email from Pepper to Emirge[3] establishes that by 12 April 2023, Pepper was under the impression that Mr De Coppi had paid a total of $129,000 towards the first three stages and part of the fourth stage of construction. Therefore, Pepper was only willing to pay progress claims for part of stage 4 and the subsequent stages. That email from Pepper is largely consistent with the email Mr De Coppi sent to Mr Dye on 3 January 2023 in which he told Mr Dye the bank notified him that he needed to use his own money for the first three payments and after that they would pay the progress claims in full.[4] At the start of his email of 3 January 2023 Mr De Coppi informed Mr Dye he had been on the phone with Pepper that morning trying to find out when they would pay the first two progress payments. Had Mr De Coppi not been under any obligation to make those payments to Emirge, which was what his case boiled down to at trial, there would not have been a need for him to make inquiries with Pepper.
(d) Further, in that same email to Mr Dye, Mr De Coppi stated that Pepper's position 'Throws a spanner in the works as my money doesn't roll over with my dad until sometime next month'. That statement and the rest of the content of that email is consistent only with Mr De Coppi having a belief that he was required to pay the entire Written Contract amount. Had a gentlemen's agreement or side deal existed which did not require him to pay the full Written Contract amount, it makes no sense that Mr De Coppi did not remind Mr Dye of it and its terms.
(a) The content of the email is inconsistent with a belief by Mr De Coppi that he was not required to pay the full contract amount. The email was sent after Mr De Coppi had seen an email (not in evidence) from Emirge's lawyer. In the email Mr De Coppi acknowledged he was in a difficult position and was trying to sort out his situation with money. He referred to the fact that he would not be getting money, which he accepted in evidence was from his father, until closer to the end of the build and that his father wanted to pay as much as he could direct to trades. If Mr De Coppi was not required to pay the first three progress payments and part of the fourth one, he did not owe any money to Emirge. In those circumstances any financial difficulties Mr De Coppi was experiencing were irrelevant. Further, it would have been unnecessary for Mr De Coppi's father to pay trades because Pepper would pay the remaining progress claims when they were made.
(b) Nowhere in the email did Mr De Coppi say he did not owe any money to Emirge because of the gentlemen's agreement or side deal.
(c) The email contains a table. In the table Mr De Coppi set out the two progress payments that had been paid to Emirge by Pepper, the anticipated future payments to Emirge from Pepper, the already incurred building costs paid by Emirge ($190,000), as well as remaining estimated building costs for work yet to be done ($156,588). Mr De Coppi submitted that the figure of $156,588 in the table is the 'tally estimate' of future works that never took place and that the figure of $190,000 was an estimate only of future works not completed and past works. While I accept that the figure of future works might be an estimate only, as opposed to having been based on actual quotes to carry out the work, I do not accept the latter figure includes the former. In the table itself next to the figure of $190,000 are the words 'paid out'. Those words are consistent with the figure of $190,000 being the amount Emirge had paid at the date of the email for goods and trades for the construction of the house. My view about that is fortified by the fact that in the table, those two figures are added to arrive at a total of $346,588 from which the total progress payments Pepper would pay pursuant to the Written Contract ($75,750 already paid and $245,250 to be paid) to arrive at a shortfall of $25,588. If the $190,000 included the future works, it would make no sense to add to it $156,588. The shortfall is an estimate of the amount that Emirge would be out of pocket if the construction of Mr De Coppi's house had been completed.
(d) Below the table Mr De Coppi said, 'I know this is not an ideal situation, but I need to resolve this for you and I and it seems the best way moving forward'. That sentence was followed by a dot point and the words '3% margin to be paid'. Regardless of whether the table is referring to estimates of the cost of future work, or quotes for future work, it shows the existence of a shortfall or potential shortfall of money owed to Emirge upon completion of construction of the house. It is clear from the content of the table that Mr De Coppi believed that after Pepper paid the rest of the progress claims, which would be issued after further work took place, there would be a shortfall owing to Emirge. The existence of a shortfall is inconsistent with any gentlemen's agreement or side deal Mr De Coppi claimed existed with terms, of whatever nature, that did not require him to pay the $129,000 of the Written Contract amount.
(e) The email can best be characterised as an attempt by Mr De Coppi to renegotiate the Written Contract in a way that required him to pay less than the $450,000 contract amount.
(f) In his evidence, Mr De Coppi seemed to suggest that the reference to 3% in that email was a reference to a percentage above the cost of construction of the house, which formed part of the gentlemen's agreement or side deal. However, that contention does not sit well with the rest of the contents of the email. Further, it is inconsistent with his written submissions on Exhibit 11. In those written submissions, Mr De Coppi suggested the 3% was an extra margin he and Mr Dye discussed to mitigate any potential interest Emirge accrued. An offer of an extra 3% margin is consistent with evidence given by Mr Dye. Mr Dye's evidence about the email was to the effect that the 3% margin referred to by Mr De Coppi was an additional margin being offered to Emirge for its indulgence in relation to the outstanding progress claims. It is not readily discernible from the email itself that the reference in the email to a 3% margin is meant to be an extra margin. However, it is apparent from the email chain that there must have been other discussions, either orally or by email, about the situation between Emirge and Mr De Coppi. Therefore, it may well have been the case that an extra 3% margin had been discussed by them at some point before the email was sent by Mr De Coppi. However, it does not necessarily follow that is what he meant in the email.
(g) I need not make any finding about what the reference to a '3% margin to be paid' actually meant because what is significant is that the reference to any 3% margin is inconsistent with Mr De Coppi not owing any money to Emirge because of the gentlemen's agreement or side deal.
(h) The table shows a shortfall owing to Emirge of $25,588. In his written submissions on Exhibit 11 Mr De Coppi suggested the potential shortfall consisted of the extra 3% margin. That position is inconsistent with the figures in the table. It is clear the shortfall is the difference between total construction costs and the total amount Emirge would be paid by Pepper if the house was completed. The shortfall amount bears no relationship to a margin of 3% on the total anticipated or estimated construction cost of $346,588 that is set out in the table.
I certify that the preceding paragraph(s) comprise the reasons for decision of the District Court of Western Australia.
[1] Order made by Principal Registrar McGivern on 29 July 2024.
[2] Coyne v GSC Contracting Pty Ltd [2022] WADC 115 [172] - [179].
[5] Spiers Earthworks Pty Ltd v Landtec Projects Corporations Pty Ltd [No 2] [2012] WASCA 53 [23], [86].
[6] Ringrow Pty Ltd v BP Australian Pty Ltd [2005] HCA 71; (2005) 224 CLR 656 [32].
Coyne
GSC Contracting Pty Ltd
Coyne v GSC Contracting Pty Ltd [2022] WADC 115
Ringrow Pty Ltd v BP Australian Pty Ltd [2005] HCA 71; (2005) 224 CLR 656
Spiers Earthworks Pty Ltd v Landtec Projects Corporations Pty Ltd [No 2] [2012] WASCA 53
(2005) 224 CLR 656