Corbett Court Pty Limited v Quasar Constructions
[2008] NSWSC 1163
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2008-10-31
Before
Hammerschlag J, Mr P
Source
Original judgment source is linked above.
Judgment (70 paragraphs)
BACKGROUND 1 HIS HONOUR: In about September 2003 the plaintiff (or "CorCourt" or "the owner" as the case may be) employed the defendant (or "Quasar" or "the contractor" as the case may be) to construct a shopping mall at Picton in the shire of Wollondilly for $11,275,000. 2 It did so under a contract in the form of the ABIC MW-1 2003 major works contract, with modifications ("the Contract"). 3 The Contract includes general conditions (in alphabetically sequenced sections) and numbered special conditions. It provides that the latter take precedence. 4 The form used contains provisions for the appointment of an architect to perform administration and certification functions. The parties amended the form to define "architect" also to mean "superintendent". They designated the superintendent to be Corbett Constructions Pty Ltd and the superintendent's representative to be Mr John Corbett, a director of the plaintiff. The plaintiff and the superintendent were accordingly closely related and were both represented in their dealings with the defendant by Mr Corbett. This was a source of difficulty for the parties' relationship. 5 The development consisted of a Coles Supermarket and external and internal shops together with an underground car park servicing all components. The floor of the car park was to be, and now is, a concrete basement slab. 6 An Interim Occupation Certificate was issued by Wollondilly Shire Council ("the council") on 16 July 2004 for "Coles supermarket & carpark". 7 Coles commenced trading on 17 July 2004. The internal shops commenced trading on 4 August 2004 and the external tenancies on 24 October 2004. 8 A final Occupation Certificate for the building was issued only on 19 July 2005. 9 During the course of the Contract the defendant made sixteen progress claims on the plaintiff under the Building and Construction Industry Security of Payment Act 1999 (NSW) ("the SOP Act"). Eleven claims were paid without adjudication. Five went to adjudication under that Act and were then paid. One of the adjudicated claims resulted in a judgment in favour of the defendant against the plaintiff in the District Court. 10 As at 23 May 2008 the plaintiff had paid the defendant $11,496,070. 11 Proceedings in this Court were commenced by the plaintiff in 2006 when it sought to reclaim a significant part of the monies earlier paid to the defendant and made a claim against the defendant for liquidated damages for delay. It challenged numerous variations for which the defendant had claimed and been paid. The defendant cross-claimed for additional amounts which it said were owed to it under the Contract. 12 On 13 April 2007 the whole of the proceedings were referred under Pt 20 r 20.14 of the Uniform Civil Procedure Rules 2005 (NSW) ("UCPR") to Mr G R Easton ("the referee") for inquiry and report. 13 The hearing before the referee was anticipated to take two weeks but took 36 hearing days. Over 2,700 pages of oral testimony were transcribed. 14 The referee conducted more than seven conclaves with experts retained by the parties, and directed the preparation of joint expert reports. 15 On 23 May 2008 the referee gave his report ("the report"). It runs to 210 paragraphs spanning 140 pages. 16 In par 8 of the report the referee made the following observation: "An unusual aspect of these proceedings is that while the matters in dispute are almost entirely routine building issues (which sensibly should have been resolved between the parties), it seems that every minor issue is still being litigated in the Reference proceedings. This situation has arisen apparently because of CorCourt's dissatisfaction with the outcomes of the five earlier adjudications under the SOP Act. Since Quasar is in the position of already having been paid (on an interim basis) for its claims, CorCourt is, in effect, the claimant seeking restitution by reversing all of Quasar's claims and mounting its own claims. Inevitably, resolution has become a difficult and costly process for which litigation is not well-suited. This is exemplified by the parties retaining no less than twelve experts to address the matters in dispute, at a cost which is likely to approach the total amount in issue." 17 The report can justifiably be described as thorough, analytical and (where appropriate) scientific. It concluded that $736,263.77 is owed by the defendant to the plaintiff. THESE PROCEEDINGS 18 Now before the Court is a contest between the parties under UCPR Pt 20 r 20.24 in relation to the adoption of the report ("the adoption hearing"). 19 Each party accepts that the report should be adopted but each contends for particular variations. 20 The parties have agreed that the amount determined by the referee is to be adjusted in favour of the defendant by $163,599 to take account of moneys which the referee took as having been paid to the defendant but which were in fact not paid. 21 In addition, the plaintiff did not contest that there should be an adjustment in favour of the defendant of $1,260 which the referee allowed for GST on liquidated damages found to be due to the plaintiff, incorrectly because GST is not payable. 22 During the adoption hearing the parties maintained the bellicose stance towards each other which the referee observed. The adoption hearing took three days with each party represented by senior and junior counsel. Neither party made any meaningful concession. 23 The material relied upon by the parties and placed before the Court in the adoption hearing was limited to the Contract, some brief extracts of the affidavit material and experts' reports relied on in the reference, extracts from the submissions made to the referee, a limited number of extracts from the transcript of oral evidence and a few miscellaneous documents. THE VARIATIONS FOR WHICH THE PARTIES CONTEND 24 The plaintiff contends that the report should not be adopted in the following respects: The slab damages claim a the plaintiff brought, and the referee rejected, a claim for damages of $1,185,187 alleged to have been suffered as a result of the breach by the defendant of an alleged oral undertaking (collateral to the Contract) to provide independent certification in respect of an agreed modification to the specifications for the basement slab ("the slab damages claim"); b the plaintiff put that the slab damages claim should have succeeded and moves for a variation of the report so as to uphold it, but restricted to the amount of $243,103. The liquidated damages claim a the plaintiff claimed liquidated damages of $418,900 (alternatively $311,900) for alleged failure by the defendant to have the works reach practical completion by the contractual deadline of 9 June 2004 ("the liquidated damages claim"); b the plaintiff contended that whilst the Coles Supermarket and basement reached practical completion on 17 July 2004 the internal tenancies only reached practical completion on 4 August 2004 and the external tenancies only on 24 October 2004; c the defendant contended that it was entitled to extensions of time to the dates for practical completion of each of the three components as a result of variations to the works required by the plaintiff; d the referee determined that the whole of the works reached practical completion on 17 July 2004; e the referee determined that the adjusted date for practical completion for the Coles Supermarket was 9 July 2004 and awarded damages at the contractual rate of $1,800 per day for seven days totalling $12,600; f the referee found that the defendant was entitled to extensions of time beyond 17 July 2004 in respect of the internal tenancies and external tenancies and accordingly reported that no liquidated damages were payable in respect of those components; g the plaintiff challenges the referee's findings on practical completion with respect to the internal tenancies and the external tenancies and puts that the referee should have found the dates for which it contends, and that the report should be varied to award it liquidated damages accordingly. The delay claim a the defendant brought a claim for "adjustment of time costs" to which it alleged it was entitled under the Contract ("the delay claim"); b the claim depended on a finding that the works had been delayed by variations required by the plaintiff; c the plaintiff contended that the delay claim was barred because the defendant had failed to comply with formalities required by the Contract. It also challenged particular claims for extensions of time; d the referee found that the plaintiff had waived compliance with the contractual formalities and upheld the delay claim. He determined that the defendant is entitled to such costs for 52.5 days at $6,200 per day (which rate was agreed between the parties). He found that the plaintiff is liable to pay to the defendant $325,500; e the plaintiff challenges the referee's findings of waiver of the contractual formalities and his findings with respect to the delays occasioned by the plaintiff's variations. It puts that the delay claim should be dismissed. 25 Apart from the two adjustments already mentioned (one of which is agreed and the other not contested), the defendant contends that the report should be adopted save with respect to part of an amount awarded by the referee to the plaintiff representing preliminaries in respect of damages for defects. It asserts an amount (which transpires to be $13,466 - as appears below - out of $36,542) was wrongly awarded because there was no evidence that the actual cost of preliminaries would exceed $19,230 ("the defendant's challenge"). 26 During the adoption hearing the defendant sought leave to file a motion seeking an order that there be an allowance for interest in its favour for the period during which payment claims for variations and delay costs were unpaid, in the amount of $106,554.10. The plaintiff opposed leave and I refused it because by agreement between the parties interest was a question not dealt with by the referee on the basis that he would deal with it in a later report if the need arose. I will refer any question of interest which the parties have by agreement left over, to the referee for report should the need arise. I will, as I made clear to the parties, consider on delivery of this judgment, the entry of judgment for an amount on an interim basis.