The Simple Works Contract (November 2006)
83 In November 2006, the Simple Works Contract was signed by Mr Stephen Power on behalf of Twentieth Green and Mr Price on behalf of CRP. The document utilised a standard form of contract prepared by the Master Builders Association Incorporated and the Royal Australian Institute of Architects. Mr Price purchased the document and inserted the required details by hand. The document is not dated but the evidence on both sides was that it was prepared and signed in November 2006. There were different contentions as to when during November 2006 it was most likely signed, but I do not think the evidence enables a conclusion to be drawn as to when during the month it was signed.
84 The document commenced with a section headed, "Introduction" which identified in item 1 (execution of the contract) the owner as Twentieth Green, the lending institution as BankWest, and the contractor as CRP. Although item 1 of the Introduction was the place provided for execution by the owner and the contractor, neither Twentieth Green nor CRP executed the contract in the places provided for execution in this part of the document. However, no point was taken in relation to this, given that the document was signed elsewhere.
85 Item 2 in the "Introduction" section dealt with the architect and was completed with details for Archestral Designs. However, as discussed below, Archestral Designs was not actually engaged; nor was any other architect engaged.
86 Item 3 of the "Introduction" was headed "Special conditions for houses and dwellings, the owner remaining in occupation, and other special conditions". This item contained three questions, with "Yes" or "No" alongside each question, and the instruction to strike out the alternative which was not applicable. The first question had "No" struck through, but the other two questions did not have "Yes" or "No" struck through. Immediately after the third question, there was provision for signatures of the owner and the contractor. It is here that the document was signed, by Mr Stephen Power on behalf of the owner and by Mr Price on behalf of CRP.
87 Item 4 in the "Introduction" dealt with the contract price. The following figures were written in by Mr Price in the places provided:
(a) for the cost of the building work: $1,939,350;
(b) for GST: $193,935;
(c) for the contract price: $2,133,285.
88 This item was signed by Mr Stephen Power on behalf of the owner in the space provided. Immediately after those figures, the document set out a "warning" that the contract price could be subject to adjustment and then listed a number of relevant provisions of the contract.
89 Item 5 in the "Introduction" dealt with the works. The form stated that "this contract is for the *works set out in the *contract documents, as briefly described below". (Words or expressions appearing in italics and preceded by an asterisk were defined in the definitions section, which was Section S.) The following description was written in by Mr Price:
REFURBISHMENT OF 15 no EXISTING APARTMENTS TOGETHER WITH THE CONSTRUCTION OF 8 no NEW APARTMENTS
90 The expressions "works" and "contract documents" were defined in Section S as follows. "Works" was defined as "the completed construction set out in the *contract documents (briefly described in item 5 of the Introduction)" and "contract documents" was defined as "any special conditions shown in schedule 2, the conditions in this contract, the specifications, the drawings and any other documents shown in schedule 3".
91 Section A of the Simple Works Contract was headed, "Overview" and dealt with matters such as the obligations of the contractor and the obligations of the owner. Clause A6 was headed, "Architect to administer the contract" and provided as follows:
1. The architect for the purposes of this contract is shown in item 2 of the Introduction.
2. The architect is appointed to administer this contract on behalf of the owner. The architect is the owner's agent for giving instructions to the contractor. However, in acting as assessor, valuer or certifier, the architect acts independently, not as the agent of the owner.
3. The owner must ensure that the architect, in acting as assessor, valuer or certifier, complies with this contract and acts fairly and impartially, having regard to the interests of both the owner and the contractor. The owner must not compromise the architect's independence in acting as assessor, valuer or certifier.
4. The owner warrants that the architect has authority to administer this contract.
5. If the architect resigns, or becomes incapable of acting as architect, or if the owner terminates the engagement of the architect, the owner must immediately nominate another architect and give written notice of the name and address of the architect to the contractor.
6. If the contractor has no reasonable objection to the nominated architect, that person will be appointed as the architect for the purposes of this contract.
7. The newly appointed architect is bound by the written decisions of any previous architect.
92 Clause A10 provided that, where the contractor or the owner is entitled to compensation as determined under the contract, that compensation, when paid in full, was a sole and complete remedy for the contractor or the owner in those circumstances.
93 Section B was headed, "Documents". Clause B1 provided that if either the contract or the owner discovered any discrepancy or omission in, or between, any of the contract documents, that party must promptly give written notice to the architect; and the architect must promptly resolve the discrepancy or omission by giving a written instruction to the contractor and a copy to the owner. Clause B2 dealt with the order of precedence of documents.
94 Section C dealt with security. Section D dealt with liability. Section E dealt with insurance. At the end of this section, there was a handwritten annotation (in Mr Price's handwriting) to refer to the special conditions in schedule 2. Section F dealt with the site. Section G was headed, "Building the works". Clause G2 within this section set out the contractor's obligations.
95 Section H was headed "Claims to adjust the contract". Within this section, clause H1 dealt with the time for making a claim to adjust the contract, and provided that the contractor was entitled to make a claim to adjust the contract only if the contractor promptly notified the architect in writing of its intention to make a claim after receiving an instruction or, if no instruction was issued, promptly notified the architect after becoming aware of an event that would result in a claim; and submitted the detailed claim to adjust the contract to the architect within a time agreed in writing between the contractor and the architect (or if no time was agreed, within 20 working days). The clause provided that if the claim resulted from a delay in the progress of the works, the contractor was not required to give the first notification required under subclause H1.1 but the detailed claim was required to be submitted within 20 working days after the end of the delay. Clause H2 set out the details required for a claim, and clause H3 provided for the architect to assess the claim.
96 Section J was headed, "Variation to the works". Clauses J1 to J4 were crossed out and a handwritten note in the margin (in Mr Price's handwriting) referred to the special conditions in schedule 2. Section K was headed, "Adjustment of provisional and prime cost sums".
97 Section L was headed, "Adjustment of time" and, among other things, set out a process for adjustment of the practical completion date. Clause L1 provided that the contractor could make a claim for an adjustment to the date for practical completion in respect of a delay affecting working days in certain circumstances, as there set out. The requirements for making a claim to adjust the contract and the procedures to be followed were set out in section H.
98 Section M dealt with completion of the works.
(a) Clause M1 provided that the contractor was required to bring the works to practical completion by the date for practical completion shown in item 16 of schedule 1, as adjusted in accordance with the contract. It was provided that the works would be at practical completion when, in the reasonable opinion of the architect, certain matters had occurred (as there set out). The date for practical completion in item 16 of schedule 1 was 8 November 2007.
(b) Clause M2 provided for the contractor to notify the architect when the works were near practical completion. It provided for the contractor and architect to agree a program for inspection of the works.
(c) Clause M3 provided for the architect to decide whether the works had reached practical completion. Clause M4 provided that, if the architect considered that the works were not at practical completion, the architect was to give a written statement to this effect to the contractor and owner. Clause M5 provided that, if the architect gave a written statement to the contractor, the contractor was required to do whatever was necessary for practical completion to be reached. The contractor was then to notify the architect when it considered the works to have reached practical completion.
(d) Clause M6 provided that, if the architect failed to issue a notice under clauses M3 or M4 within a certain time, the contractor could request the architect to issue a notice.
(e) Clause M7 provided that if the owner took possession of the works before the architect issued the notice of practical completion, the works were to be treated as as having reached practical completion.
(f) Clause M8 dealt with liquidated damages. It provided that if the works had not reached practical completion by the date for practical completion as adjusted, the architect was to promptly notify the owner and the contractor in writing of the owner's entitlement to liquidated damages. It provided that the owner could then, at any time until the final certificate was issued under clause N11 or a certificate under clause Q9 or Q17 was issued, advise the architect in writing of the owner's entitlement to liquidated damages against the contractor. The clause provided that the contractor was liable to pay or allow the owner liquidated damages at the rate shown in item 18 of Schedule 1. This provided that the rate for liquidated damages was "Nil" dollars per calendar day. Clause M9 dealt with deduction of liquidated damages in the certificates prepared by the architect.
(g) Clause M10 provided that the contractor was required to correct any defects (a defined expression) or finalise any incomplete work, whether before or after the date for practical completion, within the agreed time as stated in an instruction or, if no time limit was stated, within 10 working days after receiving a written instruction from the architect to do so.
(h) Clause M11 provided that if the contractor failed to correct a defect or finalise any incomplete work within the time nominated under clause M10 or failed to show reasonable cause for the failure together with a timetable for correcting the problem that was acceptable to the architect, the owner could use another person to correct the problem at the cost of the contractors; that if the owner was required to use another person to rectify a problem, the owner was entitled to make a claim to adjust the contract; and that if the owner made a claim to adjust the contract, the architect was required promptly to assess the claim and could issue a certificate under clause N4.
(i) Clause M12 provided that the defects liability period was as shown in item 19 of Schedule 1. This item specified 12 months. The clause provided that this commenced on the date of practical completion of the works.
(j) Clause M13 provided for the contractor's obligations during and after the defects liability period. The clause provided that if there was any remaining defect or incomplete work, or the contractor became aware by instruction from the architect or from its own observation of any defect or incomplete work during the defects liability period, it was required to promptly return to the site and correct the defect or finalise the incomplete work.
99 Section N dealt with payment for the works. Clause N1 provided that the contract price shown in item 4 in the "Introduction" was a lump sum and the contractor represented that the contract price allowed for everything reasonably required to complete the works and various other matters (as there set out). Clauses N3 and N4 (which related to progress payments) were crossed out and there was a note in the margin referring to the special conditions in schedule 2. Section P dealt with dispute resolution. Clause P3, which related to alternative dispute resolution, was crossed out. Section Q dealt with termination of the engagement and section R was headed, "Miscellaneous". Clause R4 was an 'entire agreement' clause and provided:
This contract contains everything the owner or the architect has agreed with the contractor in relation to the matters it deals with. Neither party may rely on an earlier contract, or on anything else said or done by the other party (or by an officer, agent or employee of the other party) before this contract was entered into.
100 Clause R7 dealt with waiver and provided as follows:
The fact that a party or the architect fails to do, or delays in doing, something it is entitled to do under this contract, does not amount to a waiver of that party's or the architect's right to do it. Any waiver by a party or the architect must be in writing. A written waiver is only effective in relation to the particular obligation or breach in respect of which it is given. It is not to be taken as an implied waiver of any other obligation or breach, or as an implied waiver of that obligation or breach in relation to any other occasion.
101 Schedule 1 was headed, "Contract information" and most of the items in this schedule were completed by hand (by Mr Price). Each page of the schedules was initialled by Mr Stephen Power and Mr Price in the spaces provided at the foot of each page for the owner's initials and the contractor's initials. Item 11 within Schedule 1 set out the percentage for the contractor's overheads and profit for the purposes of clause H2 (which concerned claims to adjust the contract) and 10% was inserted. Item 20 concerned the date for submitting progress claims; the words, "15th of the month" were inserted.
102 Schedule 2 to the contract set out special conditions, including particular conditions relevant to houses in Victoria. This included clauses N3 and N4 dealing with progress payments. Within clause N3, option 1 (which provided for monthly progress payments) was selected and initialled by Mr Stephen Power and Mr Price in the space provided. Schedule 10 (which appeared next, evidently being an inserted page) was headed, "Checklist required under section 31(1)(r) of the Domestic Building Contracts Act 1995" and set out a list of questions with the instruction, "Check this list and make sure you can tick the 'yes' column for every answer before signing your building contract". The list included the questions:
Is the work shown and clearly described in the contract, plans or specifications and any other relevant documents such as engineering computations or soil report?
Have you included all special requirements and finishes in your plans or specifications?
103 As with the other pages of the schedules, this page was initialled by Mr Stephen Power and Mr Price in the space provided at the foot of the page.
104 Next, Schedule 3 was headed, "Order of precedence of contract documents". Following the statement, "The order of *contract documents is", the following was inserted by hand (by Mr Price):
SCOPE OF WORKS
WORKING DRAWINGS
105 Schedule 4 was headed, "Site information". Following the statement, "The *site information is", the following was inserted by hand (by Mr Price):
PLANNING PERMITS
BUILDING SURVEYORS REPORT
SCOPE OF WORKS
WORKING DRAWINGS
106 Schedule 5 dealt with the form of any unconditional guarantee; schedule 6 (relating to provisional sums) was crossed out; schedule 7 (relating to prime cost sums) was crossed out; and schedule 8 (headed, "Items to be supplied by owner for incorporation in the works") was crossed out.
107 No documents, such as a scope of works, were attached to the Simple Works Contract as signed. This was accepted by Mr Stephen Power during cross-examination.
108 At the time the Simple Works Contract was signed, the town planning drawings were in existence, but engineering drawings and working drawings were not yet in existence.
109 In his third affidavit, Mr Price stated that he prepared the Simple Works Contract in November 2006, two months after CRP had been appointed the builder of the Project "for the purpose of Twentieth Green Pty Ltd obtaining its finance for the Project from BankWest". He said that he was asked to provide a breakdown of the amount to be funded by the bank, and prepared the two page, handwritten document, with the total $1,939,345 (Ex R10, tab 4). He stated in his affidavit that with GST of 10% added to it, the amount is $2,133,279, which correlated with the build costs to be funded by BankWest specified in the Simple Works Contract. Mr Price said during cross-examination (and I accept) that this document was prepared before the Simple Works Contract was entered into. I note that it does not contain any item for margin or overheads.
110 In his third affidavit, Mr Price also said:
16. I have never agreed to undertake a substantial development or renovation on a fixed price. For such work I have always operated on a cost plus basis where I have charged for all materials consumed and labour or trades engaged to perform the work and added a contractor's margin of 10% or 15%. I believe it is too risky to agree to a fixed price due to the many unknowns and potential unforseen (sic) issues that can arise. I certainly would never agree to a fixed price in the following circumstances:
(a) If I did not have detailed working drawings and final structural and engineering drawings as the costs of the building will be massively affected by the details of slab design, structural steel requirements, wall and roof design and window types and fire rating issues and all specifications, measurements and details concerning these matters. This was a significant issue in relation to the development, as the final design as designed by the structural engineer required a suspended slab over the car park, which added enormous cost to the Project.
(b) If I did not have final soil reports as the construction costs can be massively affected by the ground conditions and any particular issues on the site which may affect slab design, pylons and footings, remediation and clean up costs and any fill or soil removal and contouring requirements. This was a significant issue in relation to the development because due to the soil conditions and contours at the Site, there was substantial amount of excavation, stabilising and removal of existing soil. This added significantly to excavation costs and soil removal costs and importation of a suitable medium to stabilise the ground.
(c) If I did not have final approved building plans as the Council may impose costly variations or requirements as conditions of the building approval.
(d) If I did not have a final sewage plan which has [been] approved by Council. There can be massive costs variations if sewage works are required or not required. This is what happened at the Project. When I started the Project I did not believe there would be any sewage works required but the Council subsequently required that there be an upgrade to the sewage works on the property to accommodate the increased number of units. This work cost $70,000.
(e) If I did not have a detailed specification of all finishes, fit out and painting. The costs can vary quite significantly depending on the level of finishes and fit out required. A granite bench is far more expensive than laminate, stainless steel balustrading is far more expensive than timber, a Miele appliance is far more expensive than Dishlex, Porter's paints are far more expensive than Dulux. The quality of fittings in bathrooms and kitchens can vary enormously. As has been demonstrated in the respondents' evidence they believe CRP should have smoothed or painted surfaces when I do not and they believe some finishes in the car park in particular should have been completed to a standard of finish that I do not. A detailed specification is necessary to ensure these matters are known and can be priced to an agreed quality and standard. Working under a costs plus basis makes this unnecessary as the owner can be consulted on such matters and they can be agreed upon as they arise. … There was no specification prepared in relation to the Project. …
17. I did not have any of the documents or necessary information referred to in paragraph 16 above and consequently never would have agreed to build the Project to a fixed cost in the circumstances. I was not asked to put in a fixed price quote for the Project and if asked in the circumstances I would have declined the opportunity to do so.
111 During cross-examination, the following exchange took place between senior counsel for the first to seventh respondents and Mr Price in relation to the reason for signing the Simple Works Contract:
Mr Price, it seems that you want his Honour to accept that the only reason this signed written contract was for bank finance; is that your case?---That was its intent at the beginning, as I understood it.
Does at the beginning - does it mean that things changed after the beginning? Are you suggesting that once you got the development check estimate in February 2007 from BMT confirming that the price was fair and competitive that it was actually the contract between your parties; is that your position?---My position is that I am of the understanding that to get that - to get finance for our first project, Bankwest finance, we had to have a building contract as a part of the letter of offer for a certain amount. And that's what - what the basis it was prepared on.
112 Mr Price did not give evidence, either in his affidavits or orally, of any specific conversation with members of the syndicate to the effect that the document which became the Simple Works Contract would not govern the relationship between the parties and would only be used to obtain finance.
113 Mr Price accepted during cross-examination that at no stage in the period between December 2006 and November 2008 did he render an invoice to Twentieth Green which was on the basis of the cost of labour and materials plus a 15% margin.
114 In his second affidavit, Mr Stephen Price rejected the proposition (set out in the Fast Track Statement) that the syndicate members said to Mr Price that the written contract would only be used to obtain finance for the Project and would not record the terms under which CRP was to be engaged. He said: "In my view, showing a bank a signed contract with a builder in order to gain finance when the contract was not in fact the true arrangement with the builder would be dishonest. I would not do such a thing."
115 Mr Stephen Power accepted during cross-examination that he told Mr Price that he needed to sign a building contract to provide to the bank to facilitate the loan. He accepted that he could well have asked Mr Price to produce a Master Builders Association simple works contract. Mr Stephen Power said during cross-examination that he had no recollection of asking Mr Price to complete the contract with the building costs to be approximately the sum to be provided by the bank. Mr Stephen Power strongly disputed that he said to Mr Price that the building contract would only be used to obtain finance and did not record the actual terms of the engagement.
116 Mr Stephen Power said during cross-examination (and I accept) that he did not show the Simple Works Contract to the other syndicate members and that he was "charged with getting it sorted for the bank's purposes". Mr Reynolds said during cross-examination (and I accept) that he did not see the Simple Works contract and that there were other people handling it.
117 As noted above, schedules 3 and 4 of the Simple Works Contract referred to a scope of works.
118 In his third affidavit, Mr Price stated that there was no specification prepared in relation to the Project and that "the only document that was prepared for the purposes of the BankWest loan, was a scope of works document … which was prepared on or about 17 November 2006, but it contains very little detail". The document Mr Price identified in that evidence is a three-page document on CRP letterhead headed, "Development of existing apartment complex at 33 Albion Road, Box Hill for Twentieth Green Pty Ltd" (the Three Page Scope of Works) (Ex R10, tab 10). The document has a fax header dated 17 November 2006 indicating it was in existence by that date. The fax header also indicates that it was sent from a fax machine at Holiday Concepts and comprised pages 8, 9 and 10 of a fax. The document contained a sub-heading, "Refurbished apartments - Scope of Works" and then provided details for items such as "Windows", "Planning", "Joinery". At the end of the document was a second sub-heading, "2 New Works" followed by the following sentence: "To construct eight (8) no. new apartments as per drawings provided and in accordance with schedule of finishes as prepared." During cross-examination, Mr Price said that the "schedule of finishes" referred to in this sentence was the finishes set out in the first part of the document, dealing with the apartments to be refurbished.
119 During cross-examination, Mr Price accepted that he took responsibility for preparing the scope of works in relation to the Project.
120 During cross-examination, senior counsel for the first to seventh respondents handed Mr Price a document which was produced by BMT in response to a subpoena issued by the applicants. The document is ten pages in length, on the letterhead of CRP, bears the date, September 2006, and headed, "Development of existing apartment complex at 33 Albion Road, Box Hill for Twentieth Green Pty Ltd" (the Ten Page Scope of Works) (Ex R5). Parts of this document are the same as, or very similar to, the Three Page Scope of Works. But the document contained a significant amount of additional material. Immediately after the heading on the first page, the following was stated:
Following your instructions, please find enclosed our inclusive pricing for the abovementioned project.
The pricing is tendered in accordance with providing fifteen (15) No. refurbished apartments together with eight (8) No. new apartments as per architectural drawings TP2-TP10.
This price is also in accordance with the schedule of finishes as prepared.
We have divided this submission into the following sections:
1. Refurbished apartments
2. New works
121 Following those statements, there was a section headed, "Refurbished apartments - Scope of Works", which was similar to the Three Page Scope of Works, but also had prices at the end. The sub-total for this work was $737,300. Then there was a section headed, "2 New Works" followed by the same sentence as in the Three Page Scope of Works quoted in paragraph [118] above. However, unlike the Three Page Scope of Works, a price was provided ($1,106,550). It is noteworthy that the total price (taking into account landscaping and fire hydrant) was $1,939,350 (without GST) or $2,133,285 (including GST), which are the same amounts as in the Simple Works Contract.
122 The fourth to tenth pages of the Ten Page Scope of Works comprised a schedule of finishes for the works. It included details about such matters as the brands of appliances in the kitchen and the brands of fittings in the bathrooms.
123 Mr Price accepted during cross-examination that "with exhibit R5 we have 10 pages which fully describe, with precision, the price and the finishes". It was put to him that he prepared it and he answered, "It seems as though it was". He said that he did not know for whom the document was prepared. In re-examination, Mr Price said that he could not say who prepared the Ten Page Scope of Works, and that he did not prepare it; and that the Project was not far advanced as at September 2006. He was asked a series of questions which compared the level of detail in the Ten Page Scope of Works, the one page "Schedule of Finishes" forming part of the BMT Preliminary Cost Plan dated 5 October 2006, and the "Trade Breakup" forming part of BMT's Development Check Estimate dated 12 February 2007 (discussed below). Based on that comparison, Mr Price said that the BMT Preliminary Cost Plan "would have come first" and that he could not tell which came first as between the other two documents as they specified the same finishes. Mr Price also said during re-examination that he did not show the Ten Page Scope of Works document to another syndicate member.
124 During re-examination, Mr Price was taken to a contract of sale for one of the units (unit 18) which included a schedule of finishes with a fax header on it (Ex A5). The fax header on those pages is similar to the fax header on the Three Page Scope of Works. Both documents were sent from the same fax machine (that is, the Holiday Concepts fax) on the same date and at almost the same time. The schedule of finishes forming part of the sales contract is marked pages 2 to 7 in the fax header, while the Three Page Scope of Works is marked pages 8 to 10. It is to be inferred that the two documents were faxed together on 17 November 2006. The schedule of finishes forming part of the sales contract is similar to, or the same as, the schedule of finishes comprising pages 5 to 10 of the Ten Page Scope of Works, indicating that a document with this level of detail had been prepared by 17 November 2006. CRP and Mr Price did not have any employees at this time and Mr Price had access to and used the Holiday Concepts fax machine.
125 During cross-examination, Mr Stephen Power was taken to the Ten Page Scope of Works. He accepted that he never sat down and discussed the document with Mr Price. He also accepted that the document was not put forward by Mr Price as a formal tender document, nor did Twentieth Green accept it as such.
126 In my view, it is likely that the Ten Page Scope of Works was created by Mr Price in October or November 2006. It is likely that it was prepared by Mr Price given that he was the person charged with preparing the scope of works, it is on CRP letterhead, and he did not employ anyone. Although it bears the date September 2006, it is likely to have been prepared later; most likely during October or November 2006. If it had been in existence in September, it would probably have been provided to BMT and formed part of the Preliminary Cost Plan of 5 October 2006; but that document does not reflect the level of detail of finishes contained in the Ten Page Scope of Works. It is likely that the Ten Page Scope of Works was in existence by 17 November 2006, given that the two documents faxed on that date (the Three Page Scope of Works, and the schedule of finishes attached to the contract of sale for unit 18) contain nearly all of the material in the Ten Page Scope of Works other than the prices. The price in the Ten Page Scope of Works correlates with the price in the Simple Works Contract and in the two-page handwritten document prepared by Mr Price referred to in paragraph [109] above. I think it is likely that, as with that two-page handwritten document, the Ten Page Scope of Works was prepared by Mr Price before the Simple Works Contract, in order to support or explain the price in that contract. Accordingly, I find that the Ten Page Scope of Works was prepared during October or November 2006 and that it was prepared before the Simple Works Contract was signed.
127 Some of the cross-examination of the first to seventh respondents' witnesses concerned whether the Simple Works Contract lacked certainty. On a number of occasions, amounts were charged by CRP and paid by Twentieth Green outside the normal progress payment regime established by the Simple Works Contract. This evidence is dealt with later in these reasons. However, it is convenient to note at this point the following exchange between counsel for the applicants and Mr Stephen Power during cross-examination:
So what I want to suggest to you, sir, is that having regard to the state of this contract at the time - that is, the lack of working drawings, the lack of a detailed specification, no discussion about finishes, no discussion about prime cost items - the truth is you didn't really know what was going to be delivered for the price that was in the contract, did you?---I trusted Colin, so I was happy - if Colin prepared it I was happy enough to accept it.
You may have trusted him, but the truth is you, on behalf of the syndicate, did not know what was going to be delivered. That has got to be right, doesn't it, on the state of this contract? ---On the state of this contract, yes.
Yes, thank you. And I want to suggest to you that, in the end, you didn't really care about that, because as long as the bank accepted the document and allowed the project to go forward with the borrowing, that was fine. That was the situation, wasn't it? ---The - we needed a contract for the first time.
Yes? ---I would be lying if I said I - I was sure of my ground here, but I did have faith in Colin's ability to prepare it and to be fair and reasonable about it.
Be fair and reasonable? So you relied - when you say "be fair and reasonable" do you mean about what was delivered? ---No, you know, the price that he agreed to build it for, and there was a schedule of finishes. It may not be as comprehensive as it should have been but there was - you know, the bare bones were there.
So do you know where - you wouldn't know whether you were going to get Miele appliances or Whirlpool or whether the finishes were going to be stainless steel or they were going to be cheap chrome. You wouldn't know any of that, would you? ---No, but Colin had done a lot of refurbishments for us in the past, so we knew what to expect in terms of finish, not necessarily the type of appliances, but, you know, the quality of the finish.
And to the extent that - I don't know - that he produced a particular standard of work that you were unhappy with, if you went back to the contract, the contract wouldn't tell you whether he had met the requirement or not; correct? ---Possibly.
Yes. Sir, I just want to - I will restate the question in light of what we've just discussed, that the truth is it didn't really matter as long as the bank ticked it off and you could get on with the project. That's correct, isn't it? ---It mattered inasmuch as we wanted to know what it was going to cost us to build.
Yes? ---We needed to put a contract in place for the very first time.
Yes? ---We needed timeframes, so there were elements there that were important that … the contract did contain. Now, there are certain - obviously some deficiencies as well.
128 In re-examination, Mr Stephen Power said (and I accept) that he did not recall any conversation with Mr Price where he said that he did not know what work he had to do under the contract.