[2021] ACTSC 111
Supreme Court of the ACT
2021-06-03
Loukas-Karlsson J
Original judgment source is linked above.
Source: the ACT Courts (www.courts.act.gov.au). Converted to plain text by ZoeLaw. Not the official version.
SUPREME COURT OF THE AUSTRALIAN CAPITAL TERRITORY
Case Title: Cobanov v Josifovski (No 2)
Citation: [2021] ACTSC 111
Hearing Dates: 21 October 2019 – 24 October 2019, 16 June 2020
Submissions Last Received: 1 July 2020
Decision Date: 3 June 2021
Reasons Date: 4 June 2021
Before: Loukas-Karlsson J
Decision: See [853]
Catchwords: PARTNERSHIP – whether common intention of parties to form partnership – whether property ‘partnership property’ – whether express term illegal or unenforceable as against public policy – where express term is for avoidance of paying capital gains tax – whether owed fiduciary obligations – remedies for breach of fiduciary duties – account of profits – equitable compensation – restitution – resulting trust CONTRACT – standard form building contract – whether inclusions list incorporated – whether rectification damages warranted – where owner sold the property TORTS – NEGLIGENCE – standard of care
Legislation Cited: Building Act 2004 (ACT) ss 42, 48 Civil Law (Property) Act 2006 (ACT) ss 201, 204 Civil Law (Wrongs) Act 2002 (ACT) ss 42, 45 Court Procedure Rules 2006 (ACT) Pts 2.8, 2.9, r 1241 Evidence Act 2011 (ACT) s 135 Income Tax Assessment Act 1936 (Cth) Pt IVA, ss 177A, 177C, 177D, 177F Income Tax Assessment Act 1997 (Cth) ss 102.5, 102.20, 104.5, 104.10, 108.5, 118.110 Partnership Act 1963 (ACT) ss 5, 6, 24, 33, 39, 44 Statute of Frauds (1677) (29 Car 2)
Cases Cited: Bellgrove v Eldridge (1954) 90 CLR 613 Birtchnell v Equity Trustees Executors and Agency Co Ltd [1929] HCA 24; 42 CLR 384 Black Uhlans Inc v NSW Crime Commission [2002] NSWSC 1060 Bloch v Bloch (1981) 189 CLR 390 Blundell v Leighton [2013] ACTCA 1 Brenner v First Artists Management Pty Limited [1993] 2 VR 221 Brooks v Burns Philip Trustee Co Ltd [1969] HCA 4; 121 CLR 432 Bryant Bros v Thiele [1923] SASR 393 Calverley v Green (1984) 155 CLR 242 Central Coast Leagues Club Limited v Gosford City Council (Unreported, Supreme Court of New South Wales, Giles CJ, 9 June 1998) Cesare v Deluxe Motors Pty Ltd (1996) 13 BCL 136 Chan v Zacharia [1984] HCA 36; 154 CLR 178 Charles Marshall Pty Ltd v Grimsley (1956) 95 CLR 353 Cobanov & Anor v Josifovski [2019] ACTSC 269 Colburn v Simms (1843) 2 Hare 543 Comlin Holdings Pty Ltd v Metlej Developments Pty Ltd [2018] NSWSC 761 Commissioner of Taxation v Hart [2004] HCA 26; 217 CLR 216 Cordon Investments Pty Ltd v Ledesor Properties Pty Ltd [2012] NSWCA 184 Craig v Silverbrook [2013] NSWSC 1687 Dart Industries Inc v Decor Corporation Pty Ltd (1993) 179 CLR 101 David Securities Pty Ltd v Commonwealth Bank of Australia [1992] HCA 48; 175 CLR 353 Director of Public Prosecutions (NSW) v Elskaf [2012] NSWSC 21 Director of War Services Home v Harris (1986) QdR 275 Dr Martens Australia Pty Ltd v Bata Shoe Co of Australia Pty Ltd [1997] FCA 505; 75 FCR 230 Duke of Westminster’s Case [1936] AC 1 Federal Commissioner of Taxation v Spotless Services Ltd (1996) 141 ALR 92 Ferrie v Whitehead (1879) 5 VLR(L) 132 Fire and All Risks Insurance Co Limited v Powell [1966] VR 513 Ford v Comber (1890) 16 VLR 540 Fox v Percy [2003] HCA 22; 214 CLR 118 GM & AM Pearce & Co Pty Ltd v Australian Tallow Producers [2005] VSCA 113 Gollan v Nugent (1988) 166 CLR 18 Haines v Bendall (1991) 172 CLR 60 Hill v Rose [1990] VR 129 Hill v Stewart (1887) 13 VLR 76 Hollier v Rambler Motors (A.M.C) Ltd [1972] 2 QB 71 Holman v Johnson (1775) 98 ER 1120 Hospital Products Ltd v United States Surgical Corporation [1984] HCA 64; 156 CLR 41 Hyder Consulting (Australia) Pty Ltd v Wilhelmsen Agency Pty Ltd & Anor [2001] NSWCA 313 Jones v Dunkel (1959) 101 CLR 298 Kelenik v Apostolidis & Ors [2009] VSC 208 Maples Winterview Pty Ltd v Liu & Anor [2015] ACTSC 58 March v Stramare (E and M H) Pty Ltd (1991) 171 CLR 506 Maric v The Nominal Defendant [2012] NSWDC 69 McFarlane v Daniell (1938) S.R (NSW) 337 McKenzie v McDonald [1927] VLR 134 Melbourne Orthopaedic Group Pty Ltd v Stamford Aus-Trade & Press Pty Ltd [2015] VSCA 150 Minter v Minter [2000] NSWSC 100 Montefiore v Smith (1876) 14 SCR (NSW) 245 Noble v Maddison (1912) 12 SR (NSW) 45 Nocton v Lord Ashburton [1914] AC 932 Photo Production Limited v Secucor Transport Limited [1980] AC 827 Pooley v Driver (1876) 5 Ch D Port of Melbourne Authority v Anshun [1981] HCA 45; 147 CLR 589 Potter v Potter [2003] NZLR 145 Queensland Mines v Hudson (1978) 18 ALR 1 R v Meares (1997) 37 ATR 321 Re Ruddock (1879) 5 VLR (IP & M) 51 Reg. Glass Pty Ltd v Rivers Locking Systems Pty Ltd (1968) 120 CLR 516 Ross v Gordon [2021] ACTSC 41 at [171] Ruxley Electronics and Construction Ltd v Forsyth (1996) 1 AC 344 Ryan v Bunnings Group Limited [2020] ACTSC 353 Smith v Jenkins (1970) 119 CLR 397 Stone v Chappel [2017] SASCFC 72 Sze Tu v Lowe [2014] NSWCA 462; 89 NSWLR 317 Tabcorp Holdings Ltd v Bowen Investments Pty Ltd [2009] HCA 8; 236 CLR 272 Thomas Brown & Sons Limited v Fazal Deen [1962] HCA 59; 108 CLR 391 Toll (FGCT) Pty Limited v Alphapharm Pty Limited [2004] HCA 52; 219 CLR 165 Toyota Finance Australia Limited v AJI Enterprise Group Pty Ltd [2019] NSWSC 33 Tuggeranong Town Centre Pty Limited v Brenda Hungerford Pty Limited (No 2) [2017] ACTSC 88 UI International Pty Ltd v Interworks Architects Pty Ltd [2007] QCA 402 United Dominions Corporation Ltd v Brian Pty Ltd (1985) 157 CLR 1 V-Flow Pty Ltd v Holyoake Industries (Vic) Pty Ltd [2013] FCAFC 16; 296 ALR 148 Visnic v Sywak [2009] NSWCA 173; 257 ALR 517 Warman International Limited v Dwyer (1995) 182 CLR 544 Westdeutsche Landesbank Girozentrale v Islington London Borough Council [1996] AC 669 Wilkinson v Osborne [1915] HCA 92; 21 CLR 89 Parties: John Ivo Cobanov (First Plaintiff) A-Shell Homes Pty Ltd (Second Plaintiff) Kiki Josifovski (Defendant)
Representation: Counsel B Buckland (First and Second Plaintiffs) C Cassimatis (Defendant)
Solicitors O’Connor Harris & Co (First and Second Plaintiffs) Meyer Vandenberg (Defendant)
File Number: SC 241 of 2018 CONTENTS Introduction 5 Issues for Determination 6 Evidence 7 Credit and Reliability 7 Plaintiffs’ Claim 8 Does the evidence support the conclusion that the first plaintiff and the defendant 8 formed a partnership to develop and sell the property? What were the terms of the partnership agreement? 28 Is the alleged partnership agreement illegal (in part or in whole) or unenforceable for 29 public policy reasons? If any term of the alleged partnership is illegal, is that term severable? 35 If the whole of the partnership is illegal, are the plaintiffs entitled to restitution for 36 monies spent and payments not claimed? Are the plaintiffs entitled to equitable compensation or an account of profits? 36 Did the defendant pay the second plaintiff $76,850 in cash on 1 July 2013 as part of 39 payment towards the amount due under the HIA Contract? Did the first plaintiff pay the $25,000? What was the purpose and legal effect of that 57 payment? Does the evidence support a conclusion that the defendant sought, and/or directed 69 the alleged Additional Works? Did the plaintiffs pay for the alleged Additional Works? Were they performed? Were 69 they additional to requirements in the HIA Contract? Are the plaintiffs entitled to restitution for the alleged Additional Works? 89 If the alleged partnership was not formed, are the plaintiffs, or either of them, entitled 90 to restitution? If so, how much? Conclusion on the Plaintiffs’ Claim 90 Defendant’s Counterclaim 91 Which version of the HIA Contract did the second plaintiff and the defendant enter? 91 Did the parties intend to incorporate the inclusions list and building plans in the HIA 91 Contract? Did the first plaintiff fail to adequately supervise the works undertaken by the second 108 plaintiff? Did the second plaintiff fail to complete the works? 110 Did the second plaintiff breach the HIA Contract, and his duty of care (breaches) by 119 failing to build the house in a proper and skilful way, with proper material and with reasonable promptness? If the second plaintiff committed part or all of the breaches, did those breaches cause 121 the defendant to suffer the loss claimed? Was the second plaintiff entitled to be paid for each of the progress payments? Does 127 the defendant’s authorisation of payment of each of the progress payments affect the defendant’s right to claim those payments back? Is the defendant entitled to compensation for losses caused by the breaches, in 130 circumstances where he sold the property on or about 24 July 2019? Conclusion on the Defendant’s Counterclaim 138 Application for Interim Injunction 139 Orders 142 LOUKAS-KARLSSON J:
Introduction
This case concerned a dispute between three parties in respect of the construction of a residential property in the suburb of Casey (the property). John Ivo Cobanov (the first plaintiff) is the sole director, secretary, and shareholder of A-Shell Homes Pty Ltd (the second plaintiff). The plaintiffs claimed that the first plaintiff entered into a partnership with Kiki Josifovski (the defendant) to develop and sell the property. The plaintiffs also claimed that the second plaintiff performed works that were additional (the Additional Works) to the HIA ACT Residential Building Contract for New Dwellings (HIA Contract) that was entered into by the first plaintiff on behalf of the second plaintiff with the defendant.
The defendant denied any the existence of any partnership agreement and contended that the relationship between the parties was an ordinary arms-length builder/owner relationship. If there was a partnership between the first plaintiff and the defendant to develop and sell the property, the defendant contended the whole partnership was void for illegality or unenforceable due to public policy reasons as it involved an alleged scheme to avoid the payment of capital gains tax. The defendant further disputed any liability for the Additional Works claim.
The defendant also brought a counterclaim against the plaintiffs alleging that the second plaintiff breached the HIA Contract by failing to complete the contract requirements as to stages of the construction. The counterclaim also alleged that the second plaintiff failed to take reasonable care in undertaking the construction works which were the subject of the HIA Contract and that the negligence of the second plaintiff caused the defendant to suffer loss and damage.
Issues for Determination
On the Amended Statement of Claim
Does the evidence support the conclusion that the first plaintiff and the defendant formed a partnership to develop and sell the property?
If the first plaintiff and the defendant formed the alleged partnership:
a. What were the terms of the partnership agreement?
b. Is the alleged partnership agreement illegal (in part or in whole) or unenforceable for public policy reasons?
c. If any term of the alleged partnership is illegal, is that term severable?
d. If the whole of the partnership is illegal, are the plaintiffs entitled to restitution for monies spent and payments not claimed?
e. Are the plaintiffs entitled to equitable compensation or an account of profits? 3. Did the defendant pay the second plaintiff $76,850 in cash on 1 July 2013 as part of payment towards the amount due under the HIA Contract?
Did the first plaintiff pay the $25,000? What was the purpose and legal effect of that payment?
Does the evidence support a conclusion that the defendant sought, and/or directed the alleged Additional Works as defined at paragraph 32 of the amended statement of claim?
Did the plaintiffs pay for the alleged Additional Works? Were they performed? Were they additional to the requirements in the HIA Contracts?
Are the plaintiffs entitled to restitution for the alleged Additional Works?
If the alleged partnership was not formed, are the plaintiffs, or either of them, entitled to restitution? If so, how much?
On the Counterclaim
Which version of the HIA Contract did the second plaintiff and the defendant enter? Mr Cobanov’s version at page 394 of Exhibit 1 or Mr Josifovski’s version with the inclusion list at page 420 of Exhibit 1?
Did the parties intend to incorporate the inclusions list and building plans in the HIA Contract?
Did the first plaintiff fail to adequately supervise the works undertaken by the second plaintiff (noting he was the sole director, employee and shareholder thereof)?
Did the second plaintiff fail to complete the works?
Did the second plaintiff breach the HIA Contract, and his duty of care (owed to the defendant) (Breaches) by failing to build the house in a proper and skilful way, with proper material and with reasonable promptness?
If the second plaintiff committed part or all of the Breaches, did those Breaches cause the defendant to suffer the loss claimed (including the amounts the defendant paid to contractors as set out at paragraph 63 of Mr Josifovski’s statement dated 25 February 2019)?
Was the second plaintiff entitled to be paid for each of the progress payments? Does the defendant’s authorisation of payment of each of the progress payments affect the defendant’s right to claim those payments back?
Is the defendant entitled to compensation for losses caused by the Breaches, in circumstances where he sold the property on or about 24 July 2019? Evidence
Both the documentary evidence and oral evidence in this matter were extensive. It is important I note that all evidence that was received by the court has been taken into consideration, even where it is not explicitly referred to below.
Credit and Reliability
The plaintiffs contended that the court’s ultimate disposition of both the plaintiffs’ claim and the defendant’s counterclaim would involve an assessment of the versions of events given by the first plaintiff and the defendant. It was asserted that this was a credit case which would guide the courts determination as to which of the two versions 1 was true and correct on the balance of probabilities.
The defendant asserted that while the credit of the first plaintiff and the defendant would inform the court’s inquiry, the case would not rise and fall on credit. The defendant noted that the defendant could be ‘guilty’ of each of the points the plaintiffs’ wished to make as to his credit, but it would have no ultimate bearing on whether the parties 2 entered into the HIA Contract and whether the completed dwelling was defective.
It is abundantly clear from the authorities that the assessment of credit through demeanour has its limitations and that credibility may be more accurately tested by reference to objective facts, motive, and overall probabilities: see Fox v Percy [2003] HCA 22; 214 CLR 118 at [30]-[31], Ryan v Bunnings Group Limited [2020] ACTSC 353 at [21]-[30] (Ryan v Bunnings Group Limited), Craig v Silverbrook [2013] NSWSC 1687 at [140]-[142] (Craig v Silverbrook). This is the approach I have adopted in this case.
In Craig v Silverbrook, Sackar J made the following observations at [142]:
In the recent decision of McGraddie v McGraddie and Another [2013] UKSC 58; [2013] 1 WLR 2477, the UK Supreme Court emphasised that, especially in cases where a trial judge is faced with a stark choice between irreconcilable accounts, the credibility of the parties’ testimony, and the trial judge’s assessment of the character of witnesses and the manner in which the witnesses give evidence, is of primary importance. … Similar observations have been made in Australian authorities (Fox v Percy at [23]; Rosenburg v Percival [2001] HCA 18; 205 CLR 434 at [41] per McHugh J and see generally comments in Ritchie’s Uniform Civil Procedure NSW at SCA s 75A.20).
This case does not turn on demeanour. It turns on evidence.
In Director of Public Prosecutions (NSW) v Elskaf [2012] NSWSC 21, Garling J outlined at [60]-[61] the following considerations with respect to the assessment of a witness’ credibility and reliability:
It is necessary for a judicial officer to explain why he or she has found the evidence of a witness to be unacceptable. The possible bases for such a finding would include (but are not limited to):
(a) Contradictory evidence of the same events or incidents from another witness;
(b) Contradictory evidence from contemporaneous documents;
(c) Inconsistencies or contradictions within a witness’ own evidence;
1 T31.34-35. 2 T44.15-30. (d) The demeanour of a witness, including the manner of giving evidence; and
(e) Evidence of conduct or behaviour which is inconsistent with mandatory practices of police officers, or else those practices which are regularly followed by police officers.
A party who has called evidence from a witness, which is relevant and apparently probative, and whose evidence is not accepted is entitled to know the basis of that non-acceptance, in order, at least, to be able to assess the prospect of a successful appeal.
In my view, the reliability of the first plaintiff’s evidence is significantly undermined by his unsatisfactory evidence that while he did sign the 1 July 2013 invoice for $76,850 as paid, he did not receive those funds. Additionally, the reliability of the first plaintiff’s evidence is undermined by his evidence that he was going to pay capital gains tax on his portion of the profit realised from the sale of the property, notwithstanding the tax avoidance term. Further in my view, the reliability of the defendant’s evidence is undermined by the unsatisfactory evidence concerning the inclusions list.
The unsatisfactory aspects of the evidence of both the first plaintiff and the defendant outlined above has cast something of a shadow over the evidence of both parties, respectively. Therefore where there is available reliable, corroborative evidence, I have relied upon it: Ryan v Bunnings Group Limited at [74]; Maric v The Nominal Defendant [2012] NSWDC 69 at [118]; Tuggeranong Town Centre Pty Limited v Brenda Hungerford Pty Limited (No 2) [2017] ACTSC 88 at [964]; Kelenik v Apostolidis & Ors [2009] VSC 208 at [595]; and Toyota Finance Australia Limited v AJI Enterprise Group Pty Ltd [2019] NSWSC 33 at [83]. In particular, I have relied upon on the corroborative evidence of Elle Cobanov, Snezana Josifovski and Ratko Josifovski.
Plaintiffs’ Claim
Does the evidence support the conclusion that the first plaintiff and the defendant formed a partnership to develop and sell the property?
Relevant Legal Principles – Partnership – Statute
‘Partnership’ is defined within s 6(1) of the Partnership Act 1963 (ACT) (Partnership Act) as the ‘relation between people carrying on a business in common with a view of profit’.
s 24 of the Partnership Act states the following:
…. All property, and rights and interests in property, originally brought into the stock of a firm or acquired, whether by purchase or otherwise, on account of a firm or for the purposes, and in the course of the business, of a firm are called in this Act partnership property.
Subject to subsection (3), the partnership property of a firm shall be held and applied by the partners in the firm exclusively for the purposes of the firm and in accordance with the partnership agreement.
A legal estate or interest in land, being an estate or interest that belongs to a firm, shall devolve according to the nature and tenure of, and the general rules of law applicable to, the estate or interest, but in trust so far as is necessary for the persons beneficially interested in the estate or interest under this section.
…
A partner in a firm other than an incorporated limited partnership must give true accounts and full information about everything affecting the firm to another partner or another partner’s legal personal representatives.
A partnership is dissolved by the happening of an event which makes it unlawful for the business of the firm to be carried on or for the members of the firm to carry on the business of the firm in partnership.
After the dissolution of a partnership, the authority of each partner to bind the firm and the other rights and obligations of the partners continue, despite the dissolution, so far as necessary to wind up the affairs of the firm or to complete transactions started but unfinished at the time the partnership is dissolved, but not otherwise.
Relevant Legal Principles – Partnership at Common Law
A partnership may be created through an express agreement or it may be an inference to be drawn from the dealings between the parties: Ferrie v Whitehead (1879) 5 VLR(L) 132. The partnership relationship is itself a contractual arrangement: Pooley v Driver (1876) 5 Ch D at 472.
The conduct and actions of the parties throughout their dealings will form the basis of any inference to be drawn as to whether there was a partnership agreement. Whether a partnership exists does not depend on the private intention of a party, instead their intentions will be ascertained from their actions: Montefiore v Smith (1876) 14 SCR (NSW) 245. Determination of the intention of the parties is a question of fact: Bryant Bros v Thiele [1923] SASR 393 at 401 and all facts and relevant circumstances of the interactions between the parties must be considered: Re Ruddock (1879) 5 VLR (IP & M) 51.
A single purpose joint venture is still capable of being a partnership if it is able to satisfy the indicia for a partnership, in that the enterprise has the object of gain or profit: Minter v Minter [2000] NSWSC 100 at [81]; United Dominions Corporation Ltd v Brian Pty Ltd (1985) 157 CLR 1 at 15. The key factor is not ongoing continuity of carrying on a business but instead whether it is a commercial venture with a view to profit.
Although the ACT modern successor of the Statute of Frauds (1677) (29 Car 2), s 201(1) of the Civil Law (Property) Act 2006 (ACT) (Civil Law (Property) Act) establishes that an interest in land cannot be created except by writing, this requirement does not apply to a partnership that is formed for the purpose of acquiring land as opposed an acquisition of land itself: Comlin Holdings Pty Ltd v Metlej Developments Pty Ltd [2018] NSWSC 761 at [199] (Comlin Holdings).
In addressing whether such a partnership must be evidenced in writing, in Ford v Comber (1890) 16 VLR 540 at 552, Holroyd J stated: When a partnership, or an agreement for partnership, for the purpose of buying and selling land exists, and afterwards in pursuance of the partnership agreement one of the members purchases land in his own name, the land becomes part of the stock-in-trade of the firm, although the agreement was never reduced to writing. The Statute of Frauds (I use the old term for convenience) is not violated, inasmuch as a resulting trust is created by operation of law…But the partnership agreement must exist first, and its existence must be proved as an independent fact.
In Sze Tu v Lowe [2014] NSWCA 462; 89 NSWLR 317 at [115]-[127], the Court of Appeal held that property acquired after the partnership is formed should not be referred to as property the subject of a resulting trust but instead to be understood as partnership property within the meaning given by the relevant Partnership Act. This view was approved in Comlin Holdings at [192].
In relation to the issue of whether a partnership was for an illegal purpose, illegality should be explicitly raised in the pleadings: Hill v Stewart (1887) 13 VLR 76 at 79. However, if the court discovers during the course of the proceedings that the purpose of the partnership is illegal, the court must refuse to grant the relief sought and dismiss the claim: Noble v Maddison (1912) 12 SR (NSW) 45.
Evidence
John Cobanov
The first plaintiff completed a witness statement dated 20 December 2018 (the first 3 witness statement of the first plaintiff) that formed part of Exhibit 1. At the hearing, counsel for the defendant objected to various parts of the first witness statement of the first plaintiff. I determined that the evidence was admissible, subject to weight. The question of weight being a matter for submissions from the parties prior to my 4 determination of the case.
The first witness statement of the first plaintiff sets out a context for the dispute by asserting that the first plaintiff met the defendant’s brother, Goran Josifovski, in the mid- 2000s. At some point Goran Josifovski introduced the first plaintiff to the defendant. On 1 December 2009, the first plaintiff entered into a contract for the building of an upstairs residential and downstairs commercial building located at 60 Phyllis Ashton Circuit Gungahlin (the Phyllis Ashton project). The property was owned jointly by Goran Josifovski and the defendant.
The first witness statement of the first plaintiff detailed an arrangement between the second plaintiff and CRD (No 1) Pty Ltd (CRD) where the second plaintiff had entered 5 into a put and call option deed with CRD for 5 blocks of land in Casey. The first plaintiff had not found a buyer for the land by 11 April 2011 for one of the blocks, being the 6 subject property, and CRD exercised its put option.
The first witness statement of the first plaintiff set out an exchange with Goran Josifovski after the prospective buyer did not proceed with the purchase of two of the Casey blocks. The first plaintiff asserted that Goran Josifovski stated that the defendant may be interested and the defendant subsequently called the first plaintiff and a meeting was arranged to take place in January 2013.
3 The first witness statement of the first plaintiff Tab 6 Exhibit 1. 4 T42.39-46. 5 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [3]. 6 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [4].
The first plaintiff said to the defendant words to the effect of “I have this block that I was due to settle on in November 2012. I need to find a buyer and Goran said you might be interested but he doesn’t think you can afford it”. The defendant replied with words to the effect of “that’s right”.
The first plaintiff broached the idea of jointly developing the block by building a display home. The first plaintiff then said words to the effect of “I’m old and used to building houses from the 80s. I need to do something to appeal to newer, younger buyers”. The defendant then said that he was undertaking a course in order to become qualified as a builder in the ACT. The first plaintiff and the defendant proceeded to discuss how the project would be ideal for the defendant to provide new and fresh design ideas, as well as offering the defendant the opportunity to develop experience under the first plaintiff’s builder’s licence.
The first plaintiff alleges that he and the defendant orally agreed that the first plaintiff would contribute the availability of the block, his licence and insurances, his resources, equipment, time, skill and experience as a builder all at cost. The defendant would contribute design ideas, time and sufficient finance to cover as much of the costs of the build that could not be covered by the first plaintiff at first instance. The first plaintiff asserted that he said to the defendant “the amount that I can cover I estimate will be about 20% of the total build cost, excluding the cost of the land”.
The first plaintiff stated that once built, the property would be sold. The first plaintiff and the defendant would be reimbursed for the expenses they had contributed and the profit would be shared.
The first plaintiff claimed that he and the defendant established that the next step was to engage an architect for the design and for the defendant to obtain finance approval. The parties orally agreed for the defendant to approach Robert Jukic from R Inventive Building Design, who was the tenant at the defendant and Goran Josifovski’s property located at Phyllis Ashton Circuit. The first plaintiff also asserted that the parties established that the defendant would approach Patrick Bouquiaux, a mortgage broker with Tiffen & Co. The first plaintiff asserted that both he and the defendant both knew 7 Patrick Bouquiaux and had both used his services previously.
The first plaintiff completed a second witness statement on 18 April 2019 (the second 8 witness statement of the first plaintiff) that also formed part of Exhibit 1. At the hearing, counsel for the defendant again objected to various parts of the second witness statement of the first plaintiff. Again, I adopted the approach of receiving the evidence subject to weight as discussed above.
Under the heading ‘Kiki’s active involvement in the build’, the second witness statement of the first plaintiff annexed a series of email correspondence between the first plaintiff 9 and the defendant. An exchange that commenced on 5 September 2013 to 11 September 2013 was as follows:
First Plaintiff: kiki jarod bricklayer [mobile number] you will have to ring pgh bricks need 4000 facebricks 3000 commons on js Cobanov account.
7 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [11]-[19]. 8 Tab 14 Exhibit 1. 9 Tab 76 Exhibit 1. Defendant: bricks ordered ok.
Defendant: Just spoke to Jared. He’s good for Wednesday this week. He will give me quantities for sand lime cement today. What’s the account name with lopilato so I can order? I’m ordering the bricks so they arrive by Wednesday. Can I call you over there if I need to ask you something?
Defendant: John why do we need facebricks when its all going to be rendered? Shouldn’t I just get 7000 super scratch commons? The only part not rendered is the stonewall feature at the front similar like your place in forest.
First Plaintiff: OK so 7000 scratch commons ordered. Will be here tommorow (sic). Jared to start Wednesday. Just need your account name for lopilato for the sand cement lime etc? Thanks john.
Defendant: Sand ordered with Lopilato. Where do you usually get your cement from John? Bricks coming today, brickies to start this week just need to finalise cement order. I will await your advice boss…
First Plaintiff: Herzog steel.
Defendant: Thanks. The brickies are setting up today, they will be pumping it through this week and weekend. Hopefully the rain holds off. When are you back?
Defendant: John,
Contact details needed
Please provide contact details for the following: Marco phone number, Dazza phone number, Bricklayers name and phone number. Plumbers name and phone number (give me rasic and the younger boy). Tiler name and number. Guy for downpipes. Someone for glassbalustrading? (sic)
Account details
Please provide account details for the following: FAW. Magnet Mart. Flight stairs. Someone for glass balustrading? Timber guy gavin. Rivoland plus other any other tile place? Barnetts transport so I can follow up appliances deliveries. Concrete?. Lopilato bros
Invoices
How do we go about paying invoices? How do I access building funds while you are away? Aside from the items in the list, I will need to pay renderers, painters, supplies etc. Ok, have a safe trip, enjoy a few aged whiskeys on the beach. I assume you will have your phone with you and email so please stay in touch. I will call you soon to go over the details.
Thanks
Defendant: Hi John,
Enjoying the holiday?
Marco
Marco has asked me to get you to organise materials for the wardrobes. Just standard plain white adjustable board is fine Can you please let me know where we need to get supplies from? He is calling me on a daily basis asking what he can do.
Treads
Also, I need Darren to get two treads or the stairs to the cellar. We could not find anything at your farm, can you please organise this or let me know where I can tell Daz to attain. Some with any other supplies he needs for the cellar.
Timber floors
I have a good floating floor substitute for a good price. European Oak in Charcoal. Its floating but it still looks the part. Works out to be 80-90sq fully finished. Just need Marco to install. I will get a quote/invoice to you in coming days. I asked Gavin too but he came in a nearly double that price for it. Need to have flooring completed in the next week or so.
Tiles
I went to see Ronnie but he hasn’t attained anything suitable yet. If you hear from him please let me know. I will go look for some alternative suppliers this weekend.
Door handles, etc
Where should I be getting these from, marco will need to do this at the same time he does the wardrobes etc
Please email me soon. Call me anytime on [number] or on viber.
Thanks
Kiki First Plaintiff: Faw for timber and door handles ,steps come from binks in Mitchell but I don’t have account there about 50 dollars each ,tiles I was speaking to Dennis riivoland (sic) tiles queanbeyan for tiles he found something ask him ,timber floors go ahead I’m now on line Croatia bit hard to get things organized but all good see you 22 nd
Defendant: Ok thanks. What is the account called at FAW? For the timber floors, is my estimate correct, 195sqm?
Also can you please organise the plumber/ rasic (or give me their details) to make the downpipes square ones not round as discussed.
I think that’s all for now. Ill (sic) wait for your email.
Speak soon.
First Plaintiff: Faw [account name] timber floor was 70 metres sq
Further emails between the defendant and various subcontractors with the first and second plaintiffs at times carbon copied into the correspondence were also annexed to 10 the second witness statement of the first plaintiff. Many of the subcontractors themselves provided witness statements and will be referred to below.
At the hearing on 21 October 2019 the first plaintiff also gave oral evidence. In relation to the meeting that took place between the first plaintiff and the defendant in January 2013, the first plaintiff stated in examination in chief that his recollection of that conversation involved him telling the defendant he had the piece of land, that the 11 defendant could have a look at it and together they could undertake a joint venture.
The first plaintiff gave evidence that at the meeting in January 2013, he and the defendant discussed the potential arrangement because they had to formulate a plan on how to execute it. The first plaintiff stated he said to the defendant they could do the 12 project together and he could help the defendant get the project across the line.
A collection of printed emails was tendered through the first plaintiff and became Exhibit 3. The email exchange above at paragraphs [37]-[39] that formed part of Exhibit 1 was also part of Exhibit 3 however further emails were included in Exhibit 3. An email in Exhibit 3 from the defendant to an email address of the second plaintiff on 3 March 2014 stated the following:
Defendant: John
Two options for the bath: Harvey norman commercial: DECINA HNF1525 Fabrino Rect. Bath – 1525 x 765 x 400 mm WH WHT Ea $193.60 inc gst
Ostar: bath tub VB150N 1500mm $154 incl gst
10 Tab 77 Exhibit 1. 11 T66.36-43. 12 T67.1-6. Let me know which one you pick.
Thanks Kiki
Defendant: John,
Please order this at the same time as the bath from ostar. This will save us a grand in the powder room.
WD480 Vanity $190+ gst
….
We will also need plugs and floor wastes – where can you get these from?
Thanks Kiki
Counsel for the Defendant: You had no intention of getting an ABN, an Australian Business Number, did you?
First Plaintiff: No, but my business is separate to Kiki’s business. Whatever business Kiki has is his 15 business, whatever I have is my business.
The first plaintiff confirmed that he had bought and sold various properties previously and was familiar with the process of what costs are incurred when a property is 16 purchased. The first plaintiff acknowledged that he did not pay stamp duty, 17 conveyancing costs, council rates or water rates for the property.
The first plaintiff was referred to a cheque butt for the $25,000 which said ‘land sale’, the cheque butt became part of Exhibit 2 in the proceedings. When queried why he had made a written record of that note but not of the alleged partnership agreement, the first plaintiff stated that he had undertaken a previous project with the defendant (the 18 Phyllis Ashton project) and that he thought the defendant was of good character.
In re-examination the first plaintiff was again asked why he did not undertake steps to formally set up an Australian business number or complete a business activity statement. The first plaintiff answered that he did not feel it was necessary and that at
13 T106.1-13. 14 T123.16-20 & 42-45. 15 T123.19-21. 16 T106.31-37. 17 T107.1-7 & T106.39-47. 18 T135.5-7. the time he had indicated to the defendant that it was an opportunity for the defendant 19 to project manage the job. 20
I, John Cobanov of ASHELL HOMES PTY LTD, agree to the work plan as prescribed in the agreement and adhere to complete all works by ____
I understand that if I do not complete the full scope of work prescribed in the document to the client’s satisfaction then I may be financially penalised as per the client’s discretion.
Agreement to complete works within timeframe
Signed: _________________
Print Name: _________________
Date: _________________
Witness
Signed: _________________
Print Name: _________________
Date: _________________
As we discussed. All money to be returned to each partner. Your way or my way. Size now is 310m² + inclusions. – allowance can be made on tiles, bathroom kitchens, in $1200 no landscaping
The document was unsigned and undated. The first plaintiff gave evidence that it was his handwriting at the bottom of the page and that he would have written this on the 21 document before his meeting with the defendant on 14 July 2014.
Counsel for the plaintiffs sought to tender the undated document and counsel for the defendant objected to its tender pursuant to s 135 of the Evidence Act 2011 (ACT) 22 (Evidence Act). Counsel for the defendant submitted the document was of no probative value and had the tendency to be misleading and confusing. It was also submitted that the document was inconsistent with the partnership as pleaded by the 23 plaintiffs’ that claimed it was an oral agreement.
19 T178.43-45. 20 T184.30-32. 21 T185.21-27 & T186.16. 22 T186.32-36. 23 T186.30-45.
When considering whether to grant leave to reopen the examination in chief, I observed 24 that at best, the document appeared to be an undated note to self. As to the objection to the tender of the document, I noted there was force in the submissions of counsel for the defendant but allowed the document to be tendered subject to weight. The undated document which purportedly set out a written partnership became Exhibit 8 in the proceedings.
In cross examination as to Exhibit 8, the first plaintiff gave evidence that he intended to rely on both the oral agreement that was said to have originated before June 2014 and 25 the written agreement in July 2014.
Elle Cobanov
Elle Cobanov is the daughter of the first plaintiff. Elle Cobanov provided a witness 26 statement dated 18 April 2019 that formed part of Exhibit 1. In her witness statement, Elle Cobanov asserted that in early 2013 the first plaintiff had told her about an arrangement he had made with the defendant to jointly develop a property on one of the CRD blocks that the second plaintiff had bought on speculation of subsequently 27 finding an owner to buy and build on it.
The witness statement of Elle Cobanov also stated that the first plaintiff had told her that the arrangement was a partnership whereby the first plaintiff would provide his accounts with suppliers, trade discounts, builder’s licence and expertise, as well as some finance. The defendant would also contribute finance. Upon completion, the property would be sold, the proceeds would be used to pay the first plaintiff and the 28 defendant’s respective contributions and then the profits would be split.
Elle Cobanov gave oral evidence at the hearing on 22 October 2019. The portions of her witness statement extracted in the preceding two paragraphs were initially objected to by counsel for the defendant. However, counsel for the defendant subsequently was not heard against the portions of the material being admitted into evidence subject to 29 weight. The oral evidence of Elle Cobanov did not add further to the issue of whether there was a partnership.
Juha Lehtonen
Juha Lehtonen provided a witness statement dated 14 December 2018 that formed part of Exhibit 1. Juha Lehtonen is a carpenter and is self-employed. Juha Lehtonen met the first plaintiff in 2009 and subcontracted to him on multiple building jobs for residential dwellings thereafter. Juha Lehtonen had also previously met the defendant 30 and Goran Josifovski.
Juha Lehtonen stated that he had first learnt about the ‘Casey job’ when the first plaintiff asked him to cut frames for the property. In his witness statement, Juha Lehtonen stated that from the ‘get go’ he was told that the property was ‘a speci home’, that is a 31 show home being built on speculation of finding a buyer. Juha Lehtonen had initially
24 T184.14-15. 25 T188.1-11. 26 Elle Cobanov statement Tab 13 Exhibit 1. 27 Elle Cobanov statement Tab 13 Exhibit 1 [12]. 28 Elle Cobanov statement Tab 13 Exhibit 1 [13]. 29 T142.37. 30 Juha Lehtonen statement Tab 3 Exhibit 1 [3]-[5], [11]. 31 Juha Lehtonen statement Tab 3 Exhibit 1 [9]. presumed that the first plaintiff, the defendant and Goran Josifovski were building the property in a partnership. However, the first plaintiff told him that “this one is just me 32 and Kiki. Kiki is arranging the finances and I am doing the building. Happy days”.
Early in the build, Juha Lehtonen queried with the first plaintiff why single glaze windows were being used for the property when his understanding was that double glaze was to be used, unless the owner wanted to maximise profit. The first plaintiff responded that “this isn’t anyone’s house. We’re building this together and then selling 33 it off”.
In his witness statement, Juha Lehtonen noted that the defendant became increasingly concerned with specifications of the house. Juha Lehtonen stated that he began to think that the property was going to be the defendant’s home, rather than being sold 34 off.
Juha Lehtonen did not give any oral evidence at the hearing nor was he cross-examined on his statement. Counsel for the defendant objected to the tender of the 35 entire statement on the basis of relevance. I allowed the tender of the statement 36 subject again to weight.
John Rasic
Vlatko ‘John’ Rasic completed a witness statement on 21 December 2018 that formed 37 part of Exhibit 1. John Rasic is in the business of earthworks, plumbing and drainage services. He met the first plaintiff over twenty years ago as a builder and would undertake plumbing and drainage of approximately five to ten houses a year for the first plaintiff. John Rasic also knew the defendant’s father, Ratko Josifovski as well as the defendant’s brother, Goran Josifovski from having previously undertaken works for 38 them.
John Rasic stated that he received plans from the first plaintiff for the development of the property and he then provided the first plaintiff with a quote for his services. John Rasic claimed that the first plaintiff called him and the following conversation took place:
First Plaintiff: I am doing this project as a joint venture with Kiki.
John Rasic: Are you going to make money on this land or are you just feeling the market out?
First Plaintiff: It should be right as long as we don’t blow out on the 39 finishes.
32 Juha Lehtonen statement Tab 3 Exhibit 1 [12]. 33 Juha Lehtonen statement Tab 3 Exhibit 1 [10]. 34 Juha Lehtonen statement Tab 3 Exhibit 1 [15]. 35 T158.3-4. 36 T161.8-10. 37 John Rasic statement Tab 7 Exhibit 1. 38 John Rasic statement Tab 7 Exhibit 1 [4]-[5], [7]-8]. 39 John Rasic statement Tab 7 Exhibit 1 [10]-[11]. that usual practice was that owners would not direct trades but that this was a different 40 arrangement.
In his witness statement, John Rasic stated that due to customisation, the schedule of finishes increased and the defendant would become increasingly irritated. John Rasic 41 opined that it became obvious the property was not going to market.
John Rasic gave evidence at the hearing on 23 October 2019, to the extent that he partook in examination in chief to adopt his statement and for his witness statement to be formally tendered as part of Exhibit 1. Counsel for the defendant objected to the entirety of the statement being admitted on the basis that it possessed no probative 42 43 value. The statement was admitted again subject to weight.
Scott Dickason
Scott Dickason completed a witness statement dated 18 December 2018 that formed 44 part of Exhibit 1. At the time his witness statement was deposed, Scott Dickason had been a licenced electrician for twenty-one years and a sole trader for nine years. His work was predominantly the supply and provision of electrical materials and services 45 by subcontract to builders on residential houses or units.
Scott Dickason had employed Andrew Desmond as a qualified electrician since 2010. The first plaintiff and Scott Dickason met in the mid-2000s through family friends and the first plaintiff became one of the first builders Scott Dickason contracted to. Thereafter Scott Dickason performed fairly consistent work for the first plaintiff as a 46 subcontractor on projects building residential houses or units. Scott Dickason was previously aware of the second plaintiff, being one of the companies that the first 47 plaintiff represented and as an entity that was the contractor for different projects.
Scott Dickason stated that at some point in 2013, the first plaintiff sent him plans for a residential build in Casey, being the property. The first plaintiff asked for a quote for electrical work and wiring, which Scott Dickason delegated to Andrew Desmond who 48 then provide the first plaintiff with the quote.
The first plaintiff then called Scott Dickason approximately six months later to ask whether the electrical works could be commenced. The following conversation took place:
First Plaintiff: Do you remember Kiki Josifovski and his brother Goran when we did their place in Gungahlin?
Scott Dickason: [words to the effect of ‘yes’]
40 John Rasic statement Tab 7 Exhibit 1 [12]. 41 John Rasic statement Tab 7 Exhibit 1 [13]. 42 T190.40. 43 T191.1-2. 44 Scott Dickason statement Tab 4 Exhibit 1. 45 Scott Dickason statement Tab 4 Exhibit 1 [2]. 46 Scott Dickason statement Tab 4 Exhibit 1 [5]. 47 Scott Dickason statement Tab 4 Exhibit 1 [6]-[7]. 48 Scott Dickason statement Tab 4 Exhibit 1 [12]. First Plaintiff: Kiki and I are partners on this job. Kiki has fresh ideas and designs to make it more suitable to people like Kiki. 49 We’re doing this together like I did with G.
In his witness statement, Scott Dickason states that he knows the person referred to as ‘G’ to be his accountant Gerardo D’Ambrosio. Scott Dickason stated that prior the property being developed, Gerardo D’Ambrosio had said to him words to the effect of “I am investing in a place with John. John has a block of land in Casey that he needs to sell or build on. He is going to provide the material and labour and I am going to finance it. When it’s built, we’ll see it and split the profits after paying back our respective expenses”. Scott Dickason understood that when the first plaintiff said “like I did with G” to be the same arrangement that Gerardo D’Ambrosio had told him of but with the 50 defendant.
During the development of the property, Scott Dickason stated he and Andrew Desmond had commenced the wiring when the defendant began to come to the site and ask for variation to the works. Upon checking with the first plaintiff, Scott Dickason stated that the first plaintiff said “go ahead and do it” and eventually words to the effect 51 of “do whatever Kiki wants”. Scott Dickason noted that in his experience, it was very 52 unusual to accept modifications directly from a client without liaising with the builder.
Scott Dickason gave evidence at the hearing on 23 October 2019, again only to the extent that his examination in chief involved him confirming the accuracy of his 53 statement and for his statement to be tendered as part of Exhibit 1. Scott Dickason was not cross-examined. Counsel for the defendant again maintained an objection to 54 the entirety of the statement being admitted. I allowed the statement to be tendered, 55 again subject to weight.
Andrew Desmond
Andrew ‘Drew’ Desmond completed a witness statement dated 19 December 2018 56 which formed part of Exhibit 1. As referenced above, Andrew Desmond had worked for Scott Dickason since 2010 as a qualified electrician. Andrew Desmond knew the first plaintiff as a builder who had utilised Scott Dickason’s services frequently over the 57 years.
Andrew Desmond confirmed that Scott Dickason had provided him with the set of plans for the property and completed the quote for the first plaintiff. Approximately six months later, Andrew Desmond and Scott Dickason attended the property to commence wiring. In his statement, Andrew Desmond stated that he was introduced to the defendant by Scott Dickason and at the time of introduction Scott Dickason said “Kiki is doing this 58 with John”.
49 Scott Dickason statement Tab 4 Exhibit 1 [13]. 50 Scott Dickason statement Tab 4 Exhibit 1 [14], [16]-[17]. 51 Scott Dickason statement Tab 4 Exhibit 1 [18]. 52 Scott Dickason statement Tab 4 Exhibit 1 [21]. 53 T195.1-27. 54 T195.42-44. 55 T195.46-47 & T196.1-2. 56 Tab 5 Exhibit 1. 57 Andrew Desmond statement Tab 5 Exhibit 1 [1], [3]. 58 Andrew Desmond statement Tab 5 Exhibit 1 [4]-[5].
In his witness statement, Andrew Desmond states that it became clear to him that the defendant was not an ‘ordinary owner’ as the defendant was requesting additional variations beyond the scope of the initial quote. Andrew Desmond understood from early in the project that he was permitted to take instructions from the defendant in 59 relation to variations. The first plaintiff also said to Andrew Desmond on a couple of 60 occasions that the defendant was his partner.
Andrew Desmond stated that as the job progressed, the defendant was increasingly present at the site and by the fixing stage, was there at least half of the time. In relation to variations to the original quote, the defendant would liaise directly with Andrew 61 Desmond often verbally or at times via email.
Andrew Desmond gave oral evidence at the hearing on 23 October 2019. His examination in chief was brief in that it consisted only of adopting his statement so that it could be tendered as part of Exhibit 1 and to confirm his email address on a set of correspondence that had been tendered through the first plaintiff in relation to the 62 defendant’s active involvement in the build. Andrew Desmond was not cross examined although counsel for the defendant maintained an objection to the tender of Andrew Desmond’s statement on the basis of relevance. Counsel for the defendant noted that the objection was not laboured to the extent that I would allow the tender of 63 evidence subject to weight. I determined that the statement would again be admitted 64 subject to weight.
Kiki Josifovski
The defendant completed his first witness statement (the first witness statement of the defendant) on 25 February 2018. The first witness statement of the defendant also 65 became part of Exhibit 1. The defendant denied the allegation that he had entered into a partnership with the first plaintiff to develop the property and further stated he 66 had no desire to enter a partnership with the first plaintiff.
The defendant claimed that he had commenced looking for a block of land to build a family home on where he and his fiancé would live. In the defendant’s first witness statement, the defendant claimed his brother Goran Josifovski had suggested that the 67 defendant ought to consider a parcel of land for sale in Casey.
The defendant further denied that he had agreed with the first plaintiff to use the services of Patrick Bouquiaux to obtain finance to develop the property. Instead, the defendant claimed that he sought the services of Patrick Bouquiaux as he had 68 previously acted as the mortgage broker for the defendant.
In the defendant’s first witness statement, the defendant agreed that the first plaintiff had recently finished building a property that the defendant and Goran Josifovski owned in Gungahlin, being the Phyllis Ashton project. The defendant stated that he
59 Andrew Desmond statement Tab 5 Exhibit 1 [7]. 60 Andrew Desmond statement Tab 5 Exhibit 1 [5]-[6]. 61 Andrew Desmond statement Tab 5 Exhibit 1 [9]-[11]. 62 T193.24-25. 63 T194.16-17. 64 T194.19-21. 65 Tab 8 Exhibit 1. 66 The first witness statement of the defendant Tab 8 Exhibit 1 [6]. 67 The first witness statement of the defendant Tab 8 Exhibit 1 [7]-[8]. 68 The first witness statement of the defendant Tab 8 Exhibit 1 [12]. spoken to the first plaintiff before purchasing the property to seek advice on construction costs.
Prior to purchasing the property, the defendant also claimed he spoke to the architect 69 Robert Jukic to obtain advice about what dwelling could be built on the property. The defendant denied that he and the first plaintiff had agreed to utilise the services of Robert Jukic. Instead, the defendant stated that he chose Robert Jukic as he was a family friend of the defendant and he had previously engaged the services of Robert 70 Jukic.
After receiving sketches of what a dwelling on the property could look like, the defendant sought a costing estimate to build the house in the sketch from the first plaintiff. The defendant recalled that the first plaintiff said words to the effect of “I could 71 probably get it up for about $350,000”.
In either late April or early May 2013, the defendant and his fiancé had decided to purchase the property and engaged Aussie Conveyancing to act as solicitors on the 72 purchase. Approximately at the same time, the defendant engaged Robert Jukic to prepare proper plans. The plans dated 4 June 2013 were provided to the defendant in 73 early June 2013.
Shortly after receiving the plans, the defendant provided them to the first plaintiff for an 74 update on costing, an inclusions list and a timeframe for the build.
Around 12 June 2013, the defendant met with Patrick Bouquiaux and the first plaintiff at Tiffen & Co’s office in Kingston to execute the HIA Contract. The defendant claimed that one copy of the HIA Contract was executed and Patrick Bouquiaux made two copies, one for the defendant and one for the first plaintiff. The original was to be 75 provided to Westpac Bank to obtain finance.
Patrick Bouquiaux had verbally advised the defendant that he had unconditional loan approval and then confirmed this in a letter dated 1 July 2013. The letter stated that the defendant had approval for an interest-only (for 15 years) loan with a term of 30 years, 76 for the sum of $555,870.
On 2 July 2013, the defendant exchanged a contract to purchase the property from CRD for a sum of $277,500. The purchase was funded by the defendant entirely from 77 his own monies and monies he had personally borrowed from Westpac Bank.
On 17 July 2013, the defendant’s solicitors advised him that $7,267.50 was payable to the ACT Revenue Office for stamp duty on the property. The defendant provided a 78 bank cheque from Commonwealth Bank for that amount.
On 22 July 2013, the defendant’s conveyancer received an email from CRD that stated that the first plaintiff or the defendant needed to pay interest of $4,158.22 in addition to
69 The first witness statement of the defendant Tab 8 Exhibit 1 [3]. 70 The first witness statement of the defendant Tab 8 Exhibit 1 [16]. 71 The first witness statement of the defendant Tab 8 Exhibit 1 [17]. 72 The first witness statement of the defendant Tab 8 Exhibit 1 [18]. 73 The first witness statement of the defendant Tab 8 Exhibit 1 [19]. 74 The first witness statement of the defendant Tab 8 Exhibit 1 [21]. 75 The first witness statement of the defendant Tab 8 Exhibit 1 [26]. 76 The first witness statement of the defendant Tab 8 Exhibit 1 [30], [39]. 77 The first witness statement of the defendant Tab 8 Exhibit 1 [40]. 78 The first witness statement of the defendant Tab 8 Exhibit 1 [56]. the remainder of the purchase price or CRD would not settle on the property. The defendant asserted he had not been aware of any pre-existing relationship or deal between CRD and the first plaintiff.
On 26 July 2013, settlement of the purchase of the property occurred. The defendant 79 was not required to pay interest.
In the defendant’s first written statement, the defendant denied that he had ever entered into a partnership in relation to the property with the first plaintiff nor any of the entities controlled by the first plaintiff. The defendant claimed he was first put on notice of an alleged partnership when he received a letter from the first plaintiff’s solicitor on 14 80 November 2017.
The defendant denied that the first plaintiff or the second plaintiff ever made any 81 financial contribution to the construction of the dwelling on the property.
The defendant also denied that he was actively involved in the build. The defendant claimed he only received emails in respect of site plans due to the first plaintiff being 82 overseas and wanting to avoid any delays resulting from that travel.
In relation to elective variations to the plans, the defendant denied that he had instructed Robert Jukic to amend the plans to accommodate these variations. The defendant stated that variations were required as ‘work arounds’ due to errors in the 83 construction. The defendant insisted that the plans required amending because the 84 second plaintiff failed to construct the dwelling in accordance with the approved plans.
As to why the defendant began to pay trades directly, the defendant stated that this was due to the first plaintiff being overseas, frequently away or uncontactable. To 85 continue the progress of the build, the defendant paid the subcontractors directly.
The defendant admitted that he was regularly onsite to check the progress of the development throughout October and November 2014. The defendant stated that while onsite, various subcontractors would make complaints to him that the second plaintiff had not paid them. The defendant claimed that he paid many of the subcontractors 86 directly out of desperation and in an effort to complete the development.
The defendant admitted that he had sourced material directly from suppliers using the first plaintiff’s trade accounts, engaged directly with tradesmen regarding the sourcing and specification of materials, provided direction to tradesmen and researched options for different fittings and fixtures and placed orders using the first plaintiff’s trade accounts or credentials. The defendant claimed this was undertaken in the normal course of an owner specifying inclusions for his home. In relation to the use of the first plaintiff’s trade accounts, the defendant stated he only used said accounts when the 87 first plaintiff asked him to.
79 The first witness statement of the defendant Tab 8 Exhibit 1 [59]. 80 The first witness statement of the defendant Tab 8 Exhibit 1 [60]-[61]. 81 The first witness statement of the defendant Tab 8 Exhibit 1 [62]. 82 The first witness statement of the defendant Tab 8 Exhibit 1 [70]. 83 The first witness statement of the defendant Tab 8 Exhibit 1 [74]. 84 The first witness statement of the defendant Tab 8 Exhibit 1 [81]. 85 The first witness statement of the defendant Tab 8 Exhibit 1 [92], [94]. 86 The first witness statement of the defendant Tab 8 Exhibit 1 [99]. 87 The first witness statement of the defendant Tab 8 Exhibit 1 [110].
The defendant addressed the statement of Juha Lehtonen in the defendant’s first witness statement. The defendant denied knowing Juha Lehtonen as well as denying the conversations that were claimed to have taken place involving the defendant in 88 Juha Lehtonen’s witness statement.
The defendant addressed the allegations contained within the statement of John Rasic. 89 The defendant denied that he was providing instructions for variations.
In relation to the statement of Scott Dickason, the defendant also denied that he 90 directed Scott Dickason to undertake variations.
The defendant again denied the allegations as set out in the statement of Andrew Desmond, specifically that he ever directed any variations.
The defendant also completed a second witness statement (the second witness 91 statement of the defendant) dated 5 June 2019 that formed part of Exhibit 1. In the second witness statement of the defendant, the defendant denied the partnership with 92 the first plaintiff as set out in the witness statement of Elle Cobanov.
The defendant gave evidence at the hearing on 23 October 2019 and 24 October 2019. Both of the defendant’s witness statements were tendered as part of Exhibit 1. Counsel for the plaintiffs raised objections in relation to the admissibility of portions of the defendant’s first and second witness statements. I allowed the statements to be 93 tendered subject to weight.
The defendant was cross examined by counsel for the plaintiffs on his intention to look 94 for a parcel on land to build a family home on in 2013. The defendant stated that he saw block 1 of 104 in Casey was for sale and that the whole estate had been advertised. The defendant claimed there had been a sales office and agents working in the sales office. When it was put to him that the block was not available for sale because it was still under contract with the first plaintiff and CRD, the defendant stated he did not know 95 whether that was the case.
The defendant gave evidence that his intention was to live with his family at the property 96 after it was built and that had been his intention when purchasing the property. It was put to the defendant that his intention was instead to build an investment property, as recorded by Patrick Bouquiaux. The defendant denied that he was going to build an 97 investment property.
The defendant was referred to his Loan Application documentation for the Westpac Bank loan that became Exhibit 13 in the proceedings. There were references in the Loan Application to whether the property was going to be rented out. Under the question “will you rent out this property?” a box was ticked next to the word “yes” and in the box asking for the rental amount per month to be specified, $3,983 was written.
88 The first witness statement of the defendant Tab 8 Exhibit 1 [172]. 89 The first witness statement of the defendant Tab 8 Exhibit 1 [173]. 90 The first witness statement of the defendant Tab 8 Exhibit 1 [171]. 91 Tab 15 Exhibit 1. 92 The second witness statement of the defendant Tab 15 Exhibit 1 [16]. 93 T205.42-43. 94 T258.5-6. 95 T258.18-38. 96 T258.43-47. 97 T260.1-3 & 16-20. It was put to the defendant that he clearly intended to rent out the property, given that he obtained a rental appraisal for the property. The defendant denied this and said the rental appraisal amount was included because Patrick Bouquiaux would have thought 98 it would assist in helping to obtain interest only finance.
It was put to the defendant that the Westpac Loan Application contained various references that the property was to be an investment property because that was indeed 99 the loan purpose. The defendant denied this was the purpose of the loan. The defendant was queried on why he was content to tell Westpac the loan was for an 100 investment property compared to a live-in home. The defendant responded that he 101 had faith in his mortgage broker to obtain an interest only loan.
The defendant was referred to a previous project involving himself, the first plaintiff and Alfonso Campa for a property in Crace (the Campa project). The defendant gave evidence that Alfonso Campa asked the defendant if he knew a builder and the 102 defendant confirmed he did, being the first plaintiff. The defendant was referred to an email that had originated from an email address belonging to the defendant on 25 April 2013. The email was addressed to an email address of the second plaintiff and stated the following:
John,
As discussed here are the final plans for crace. Call me when you review these so we can figure out how to go about it. I have done the numbers and it looks good.
Also when you can, get me the quote for the demountable. Remember to change the specs slightly.
Talk soon
Consideration
98 T262.5-7. 99 T264.36-37. 100 T265.27-45. 101 T266.3. 102 T280.11-13. 103 T281.14-37. 104 Plaintiffs’ submissions in chief 4 December 2019 [15].
The plaintiffs submitted that from this conversation, it was the common intention of the parties to develop the property for their mutual profit. The first plaintiff would contribute, or cause to be contributed through the second plaintiff: the subject property; building licence and insurances; trade and supplier contacts and accounts; equipment, time and skill and experience as a builder, while the defendant would provide finance, as well as design ideas and time in running the build. The first plaintiff would also contribute 20 per cent of the build cost and 10 per cent of the land cost, the former in kind and the latter in cash. The goal of the partnership was mutual profit. The plaintiffs alleged that 105 the evasion of tax was not the purpose of the transaction. Again, I am not persuaded that it was the common intention of the parties to develop the property for their mutual profit.
The plaintiffs emphasised that the first plaintiff arranged for the second plaintiff’s contract with CRD for the subject property to be rescinded and for a fresh contact with CRD to be issued with the defendant as the purchaser. The plaintiffs submitted that the defendant did not offer a reasonable explanation of how this arrangement took place yet maintained the assertion that the dealings between the parties were always an 106 arm’s length transaction. This aspect of the evidence does not, in my view, detract from my finding that on the balance of probabilities I am not persuaded there was a partnership. Nor am I persuaded entirely of the defendant’s version of the events. Nevertheless, the plaintiffs bear the onus on the balance of probabilities of establishing the partnership and in my view, the plaintiffs have not done so to the requisite standard.
The plaintiffs also relied on the Campa project to inform the inquiry as to whether there was a partnership. The Campa project was also another proposal on foot between the parties and Alfonso Campa and it provided context to the intention of the parties to develop the subject property as a partnership rather than a standard arm’s length owner/ builder relationship. The plaintiffs drew upon Exhibit 16 which was an email from the defendant to the first plaintiff in relation to the Campa project in which the defendant 107 writes “I have done the numbers and it looks good”. In my view, Exhibit 16 does not necessarily support the first plaintiff’s partnership contention.
The references to renting out the property in the loan application documents and the anticipated rental return were also relied upon by the plaintiffs to counteract the evidence of the defendant that the property was only ever going to be his marital home and that was the purpose of it being built. The plaintiffs submitted that the court would more readily accept what is recorded in the contemporaneous material about the 108 purpose of the loan and would reject the version proffered by the defendant. Again, in my view this is not determinative, nor does it necessarily lend support to the first plaintiff’s version of events.
The plaintiffs relied on the defendant not calling Patrick Bouquiaux as grounds for the court drawing a Jones v Dunkel (1959) 101 CLR 298 (Jones v Dunkel) inference. That is, that the unexplained failure of the defendant to call Patrick Bouquiaux may lead to an inference that the evidence of that witness would not have assisted the defendant’s 109 case: see Jones v Dunkel at [5].
105 Plaintiffs’ submissions in chief 4 December 2019 [16]. 106 Plaintiffs’ submissions in chief 4 December 2019 [18]. 107 Plaintiffs’ submissions in chief 4 December 2019 [19]-[20]. 108 Plaintiffs’ submissions in chief 4 December 2019 [27]-[29]. 109 Plaintiffs’ submissions in chief 4 December 2019 [28].
The plaintiffs’ highlighted that the evidence of Patrick Bouquiaux could have provided evidence as to why he had written that the purpose of the loan was for an investment property, why a rental appraisal was obtained and why the weekly rental amount was written into the loan documentation. The defendant’s position was that these actions undertaken by Patrick Bouquiaux were apparently contrary to the defendant’s intention, that is that he was building a family home to live in with his fiancé. The plaintiffs submitted that where the defendant denies aspects of the claim by asserting a positive state of affairs, it is not for the plaintiffs to make good the defence case. The plaintiffs commended the alternative inference that the defendant did not call Patrick Bouquiaux as his evidence would have undermined the versions of events propounded by the 110 defendant. I take this into account. Nevertheless, the drawing or otherwise of the inference does not assist to any significant degree on the partnership issue.
At the further hearing for submissions on 16 June 2020, counsel for the plaintiffs again referred to the loan documentation completed by Patrick Bouquiaux and noted that it 111 was not a ‘just a tick-a-box investment property’.
The plaintiffs also drew upon the defendant’s active role in the management of the build to demonstrate the alleged partnership. The plaintiffs referred to the chains of email correspondence, where the defendant engaged directly with suppliers and subcontractors, to demonstrate that the degree and type of involvement in the building of the property of the defendant could only be explicable if the defendant was acting as 112 a partner and not as an ordinary homeowner. At the further hearing, counsel for the plaintiffs submitted that the correspondence during the course of the build showed a level of participation and care which is only consistent with the actions of a 113 partnership.
The evidence of Juha Lehtonen, John Rasic, Scott Dickason and Andrew Desmond was relied upon to demonstrate that the defendant was involved in the construction of the property more than a regular owner would be. The plaintiffs’ explanation for the defendant’s involvement was that the defendant was authorised to give instructions to the subcontractors because the parties were jointly engaged in developing the subject 114 property for mutual profit.
The plaintiffs’ submissions also addressed four additional factors that they claimed undermined the defendant’s version of events as to the existence of a partnership:
The progress payment invoices, in relation to the evidence of Elle Cobanov that she did not recognise them as invoices of the second plaintiff and that the first plaintiff was not technologically proficient to author them, to assert that the progress payment invoices were authored by the defendant.
The final progress payment was not released to the second plaintiff in error.
The defendant did not call Patrick Bouquiaux to give evidence. 115 4. The Construction Contract Settlement Agreement.
110 Plaintiffs’ submissions in chief 4 December 2019 [66]-[68]. 111 T384.5. 112 Plaintiffs’ submissions in chief 4 December 2019 [15]. 113 T389.31-33. 114 Plaintiffs’ submissions in chief 4 December 2019 [57]. 115 Plaintiffs’ submissions in chief 4 December 2019 [59]-[73].
In my view, the objective evidence does not support the finding on the balance of probabilities that the parties entered into a partnership agreement. The first plaintiff had taken no steps to formally set up the alleged partnership. The first plaintiff did not contribute to payment of stamp duty, conveyancing costs nor council and water rates.
The evidence of the third-party subcontractors, namely Juha Lehtonen, John Rasic, Scott Dickason and Andrew Desmond, relied on by the plaintiffs was not in my view particularly probative. It was not of telling significance in this case.
It was submitted by counsel for the defendant and I accept that the Phyllis Ashton project involving the first plaintiff, the defendant and Goran Josifovski as well as the original arrangement with Goran Josifovski to sell the block to a group including a man named Ziad Deeb were the pre-purchase arrangements of the parties. These facts do not assist the court to determine whether or not there was a partnership in this case.
It was also submitted on behalf of the defendant that the use of the HIA Contract, 116 117 regardless of whether it was the first plaintiff’s or the defendant’s version of the HIA Contract, was another factor that highlighted that the parties were not in a 118 partnership. Counsel for the defendant submitted that the HIA Contract was entered into in the ordinary commercial sense of a builder/ client arrangement rather than a 119 partnership agreement. I accept this submission.
I do not accept the plaintiffs’ submission that the degree and nature of the defendant’s involvement in the development was inconsistent with an ordinary fixed-price construction project completed through an arms-length builder/ owner agreement.
Counsel for the plaintiffs stated that the overarching inference that the plaintiffs urged upon the court was that a partnership between the first plaintiff and the defendant was the only explanation for the entirety of the circumstances. As discerned above, I am not persuaded on the balance of probabilities of such a partnership.
What were the terms of the partnership agreement?
Plaintiff Submissions
In the plaintiffs’ amended statement of claim, the plaintiffs alleged that the express terms of the partnership between the first plaintiff and the defendant were as follows:
The first plaintiff and the defendant would develop Block 1, Section 104 Casey, also known as 48 Wighton Terrace and 31 Chilton Street (the property);
116 Tab 79 Exhibit 1. 117 Tab 80 Exhibit 1. 118 T406.44-45. 119 T406.26-37. 2. The defendant would obtain finance to purchase the land and contribute to funding the build;
The first plaintiff would assign his right to purchase the property from CRD to the defendant;
The second plaintiff would build the residential home on the property at a cost of $1,180 per square metre; and
Upon completion of the building, the defendant would live in the property for one year to avoid capital gains tax, following which the property would be sold and the profits from the sale would be divided equally between the first 120 plaintiff and the defendant.
Defendant Submissions
Consideration
Is the alleged partnership agreement illegal (in part or in whole) or unenforceable for public policy reasons?
Relevant Legal Principles
The legislative regime addressing capital gains tax is set out in the Income Tax Assessment Act 1997 (Cth) (Income Tax Assessment Act 1997) and the Income Tax Assessment Act 1936 (Cth) (Income Tax Assessment Act 1936).
s 108.5 of the Income Tax Assessment Act 1997 defines land as a capital gains tax asset. Pursuant to s 104.10 of the Income Tax Assessment Act 1997, where a capital gains tax asset is disposed, it becomes a capital gains tax event. s 104.10 of the Income Tax Assessment Act 1997 sets out that a capital gains tax asset is disposed of upon a change of ownership. The quantum of the capital gain is the capital proceeds from disposal of the asset less the asset’s cost base: see s 104.5 Income Tax Assessment Act 1997. s 102.20 of the Income Tax Assessment Act 1997 sets out that a capital gain is made upon the happening of the capital gains tax event and it occurs at the time of the event. s 102.5(1) of the Income Tax Assessment Act 1997 establishes that a taxpayer’s assessable income includes their net capital gain for the income year that the capital gain occurs.
s 118.110(1) of the Income Tax Assessment Act 1997 establishes that the capital gain upon the capital gains tax event happening in relation to a dwelling is disregarded if
(a) the person is an individual;
120 Plaintiffs’ amended statement of claim 22 October 2019 [8]. (b) the dwelling was the individual’s main residence throughout the ownership period; and
(c) the interest did not pass to the individual as a beneficiary in, or as the trustee of, the estate of a deceased person.
Schemes with a dominant purpose of being entered into or carried out for the purpose of avoiding paying tax, including capital gains tax avoidance, attract scrutiny under the Part IVA avoidance provisions under the Income Tax Assessment Act 1936.
s 177A(1) of the Income Tax Assessment Act 1936 defines a ‘scheme’ as
(a) any agreement, arrangement, understanding, promise or undertaking, whether express or implied and whether or not enforceable, or intended to be enforceable by legal proceedings; and
(b) any scheme, plan, proposal, action, course of action or course of conduct.
(5) A reference in this Part (other than sections 177DA and 177J) to a scheme or a part of a scheme being entered into or carried out by a person for a particular purpose shall be read as including a reference to the scheme or part of the scheme being entered into or carried out by the person for 2 or more purposes of which that particular purpose is the dominant purpose.
(1) an amount not being included in the assessable income of the taxpayer of a year of income where that amount would have been included, or might reasonably be expected to have been included, in the assessable income of the taxpayer of that year of income if the scheme had not been entered into or carried out;
...
s 177D(1) of the Income Tax Assessment Act 1936 sets out schemes to which Part IVA applies as the following:
This Part applies to a scheme if it would be concluded (having regard to the matters in subsection 2) that the person, or one of the persons, who entered into or carried out the scheme or any part of the scheme did so for the purpose of:
(a) Enabling a taxpayer (a relevant taxpayer) to obtain a tax benefit in connection with the scheme; or
(b) Enabling the relevant taxpayer and another taxpayer (or taxpayers) each to obtain a tax benefit in connection with the scheme;
Whether or not that person who entered into or carried out the scheme or any part of the scheme is the relevant taxpayer or is the other taxpayer or one of the other taxpayers.
Having regard to certain matters
(a) The manner in which the scheme was entered into or carried out;
(b) The form and substance of the scheme (c) The time at which the scheme was entered into and the length of the period during which the scheme was carried out;
(d) The result in relation to the operation of this Act that, but for this Part, would be achieved by the scheme;
(e) Any change in the financial position of the relevant taxpayer that has resulted, will result, or may reasonably be expected to result, from the scheme;
(f) Any change in the financial person who has, or has had, any connection (whether a business, family or other nature) with the relevant taxpayer, being a change that has resulted, will result or may reasonably be expected to result, from the scheme;
(g) Any other consequence for the relevant taxpayer, or for any person referred to in paragraph (f), of the scheme having been entered into or carried out;
(h) The nature of any connection (whether of a business, family or other nature) between the relevant taxpayer and any person referred to in paragraph (f).
…
Tax benefit
When schemes entered into etc.
(a) The scheme has been or is entered into 27 May 1981; or
(b) The scheme has been or is carried out or commenced to be carried out after that day (and is not a scheme that was entered into or before that day).
(a) in the case of a tax benefit that is referable to an amount not being included in the assessable income of the taxpayer of a year of income [the Commissioner may] – determine that the whole or a part of that amount shall be included in the assessable income of the taxpayer of that year of income;
…
and, where the Commissioner makes such a determination, he or she shall take such action as he or she considers necessary to give effect to that determination.
Evidence
John Cobanov
At the hearing on 22 October 2019, the first plaintiff was cross-examined about the final alleged express term of the partnership, being the capital gains tax avoidance term. It was put to the first plaintiff that pursuant to the partnership he had an intention to make 121 a capital gain and pay no tax on it. The first plaintiff denied that he was not going to pay tax and alleged that the avoidance would only be on the defendant’s portion of the profit. The first plaintiff stated that whatever he was to receive out of the funds would have gone back into the second plaintiff and the first plaintiff would have then paid the 122 tax.
Counsel for the defendant took the first plaintiff through his previous evidence that he had not obtained a tax file number nor an Australian business number for the partnership so to frame the question of when the first plaintiff was going to pay tax on the profit. The following exchange took place:
Counsel for the Defendant: When were you going to pay tax on the profit that you say you were entitled to in the statement of claim?
First Plaintiff: Once I received moneys back, they would have gone into my A-Shell [the second plaintiff] and any expensive would have been – gone against that and any profits would have been paid for. It would have been taxed. Simple as that. I’ve been in business for 37 years and I’ve been paying tax 123 for 37 years.
Plaintiff Submissions
The plaintiffs submitted that the final term of the alleged partnership was not unlawful, but was instead a legal means of ordering the affairs of the partnership to merely minimise the parties’ tax liability as opposed to tax avoidance: Duke of Westminster’s 124 Case [1936] AC 1 at [19].
The plaintiffs submitted that absent a declaration by the Tax Commissioner it was unclear whether the partnership or a term of the partnership could contravene the relevant sections of the income tax statutory instruments as particularised by the defendant. It was asserted by the plaintiffs that the purpose of the income tax provisions on capital gains tax is to enable the Tax Commissioner to recover tax, as opposed to voiding contracts in circumstances where the Tax Commissioner may possibly make a 125 declaration.
Conclusion
121 T122.42. 122 T122.43-35. 123 T124.5-10. 124 Plaintiffs’ submissions in chief 4 December 2019 [77]. 125 Plaintiffs’ submissions in chief 4 December 2019 [78].
In reference to the first plaintiff’s evidence at the hearing that he always intended to pay tax on his portion of the profit, the defendant claimed that assertion was inherently inconsistent with the tax avoidance term. Further, the first plaintiff’s assertion was also entirely inconsistent with the intention of the partnership. The defendant submitted that the court ought to reject the evidence of the first plaintiff that he was always going to pay tax on his portion of the profit and that such evidence would lead the court to 126 question the reliability and honesty of the first plaintiff as a witness.
The defendant referred to the legislative scheme under the Income Tax Assessment Act 1997 and the Income Tax Assessment Act 1936 to establish the illegality of the tax 127 avoidance term.
The defendant submitted that if the partnership agreement was to be upheld, it must follow from the definition of partnership in s 6 of the Partnership Act that the parties intention to carry on a business in common with a view to profit was intended to be a 128 profit that would be free of the obligation to pay capital gains tax.
The defendant submitted it was clear that the partnership agreement would meet the definition of a scheme contained within Part IVA of the Income Tax Assessment Act 1936 as the agreement was for the sole or in the alternative dominant purpose of avoiding the liability of capital gains tax in the relevant year of assessable income. The defendant urged a finding that the objective inquiry pursuant to Part IVA would reveal 129 that the tax avoidance term was solely intended as a scheme to avoid tax.
The defendant asserted that the partnership agreement ought to be voided for illegality as it could not be performed without a violation of the law and was therefore ex facie 130 illegal.
The defendant also relied upon the basic maxim in common law of ex turpi causa non oritur (ex turpi causa) espoused by Lord Mansfield in the case of Holman v Johnson 131 (1775) 98 ER 1120 at 1121:
No court will lend its aid to a man who founds his cause of action upon an immoral or an illegal act. If, from the plaintiff’s own stating or otherwise, the cause of action appears to arise ex turpi causa, or the transgression of a positive law of this country, there the Court says he has no right to be assisted. It is upon that ground the Court goes; not for the sake of the defendant, but because they will not lend their aid to such a plaintiff.
The Australian decisions of Smith v Jenkins (1970) 119 CLR 397; Gollan v Nugent (1988) 166 CLR 18 underline that the ex turpi causa maxim has been limited in this country to causes of action which to be upheld would require enforcing an illegal contract: see also Fire and All Risks Insurance Co Limited v Powell [1966] VR 513 at 528.
In addition to the question of illegality, the “partnership” agreement is unenforceable as it is against public policy. The defendant referred to the case of Wilkinson v Osborne
126 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [21]-[22]. 127 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [24]-[48]. 128 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [20]. 129 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [41]. 130 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [42]. 131 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [43]. [1915] HCA 92; 21 CLR 89 at 97 where Isaacs J stated that the public policy test must relate to
…some definite and governing principle which the community as a whole has already adopted either formally by law or tacitly by its general course of corporate life and which the Courts of the country can therefore recognise and enforce.
The “partnership” agreement by virtue of the tax avoidance term is contrary to the legislative regimes set out in the Income Tax Assessment Act 1936 and Income Tax Assessment Act 1997. The “partnership” agreement is unenforceable as it is against public policy.
The plaintiff’s claimed that tax avoidance was not the purpose or the object of the partnership. Instead, the tax avoidance term was an aspect of the partnership that 133 involved lawful tax minimisation. The plaintiffs referred to the following statement of Gleeson CJ in R v Meares (1997) 37 ATR 321 at 323:
Although on occasion, it suits people, for argumentative purposes, to blur the difference, or pretend that there is no difference, between tax avoidance and tax evasion, the difference between the two is simple and clear. Tax avoidance involves using, or attempting to use, lawful means to reduce tax obligations. Tax evasion involves using unlawful means to escape payment of tax. Tax avoidance is lawful and tax evasion is unlawful.
Although some people may feel entitled to disregard that difference, no lawyer can treat it as unimportant or irrelevant. It is sometimes said that the difference may be difficult to recognise in practice. I would suggest that in most cases there is a simple practical test that can be applied. If the parties to a scheme believe that its possibility of success is entirely dependent upon the revenue authorities never finding out the true facts, it is likely to be a scheme of tax evasion, not tax avoidance.
In relying on Federal Commissioner of Taxation v Spotless Services Ltd (1996) 141 ALR 92 at [14]-[15], the plaintiffs submitted that the fundamental question for the court was determining whether the partnership was entered into for the dominant purpose of obtaining a tax benefit. In Spotless Services Ltd, it was held that dominant means the ruling, prevailing or most influential purpose. On the plaintiffs’ case, the dominant purpose of the partnership was the development of the land for mutual profit. It was submitted that the reason for the defendant residing in the property for a period of time was merely ancillary to the dominant purpose. The plaintiffs ultimately submitted that 134 the partnership was not illegal nor unenforceable for public policy reasons.
At the further hearing on 16 June 2020, counsel for the plaintiffs submitted that in the event that the attempt to limit the taxation liability was ineffective for the purposes of the statutory regime for income tax assessment, the effect would not be that the entire partnership would be void or unenforceable but rather the profit realised would have 135 been lower as a result of having to pay capital gains tax.
132 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [49]-[51]. 133 Plaintiffs’ submissions in reply 16 March 2020 [13]. 134 Plaintiffs’ submissions in reply 16 March 2020 [16]. 135 T398.40-47.
If the tax avoidance term of the alleged partnership is illegal, is that term severable?
Plaintiff Submissions
The plaintiffs submitted that in the event the tax avoidance term was held by the court to be illegal, it was severable from the partnership agreement. It was submitted that the entire partnership agreement would only be voided for illegality if the dominant purpose of the whole agreement was illegal. The plaintiffs again relied upon the line of argument that the dominant purpose was the development and sale of the property for mutual profit.
The plaintiffs claimed that having to pay capital gains tax would not defeat the object of the partnership, it would merely make the venture between the parties less profitable. The plaintiffs urged a conclusion that if the tax avoidance term was illegal, it could be 136 severed from the partnership agreement.
At the further hearing on 16 June 2020, counsel for the plaintiffs asserted that the tax avoidance term could be severed and the balance of the agreement could be performed in a completely lawful manner. Counsel for the plaintiffs submitted that the appropriate means of dealing with any illegality of the tax avoidance term would be severance as opposed to voiding the entire partnership or rendering it unenforceable as against 137 public policy.
Conclusion
If the elimination of the invalid promises changes the extent only but not the kind of the contract, the valid promises are severable: Putsman v Taylor [1927] 1 KB 637 at 640- 641. If the substantial promises were all illegal or void, merely ancillary promises would be inseverable.
Also relevant is Brooks v Burns Philip Trustee Co Ltd [1969] HCA 4; 121 CLR 432 where at 442 Taylor J stated that determining whether a term can be severed is a question of intention to be derived from the agreement at hand itself.
In light of the authorities, severing the tax avoidance term from the partnership pleaded by the plaintiffs would alter the nature of the partnership agreement and would be inconsistent with the expressly alleged intention. That is, the express inclusion of the tax avoidance term itself to make a tax-free capital gain. The tax avoidance term formed the basis for the plaintiffs claim for damages or restitution.
136 Plaintiffs’ submissions in chief 4 December 2019 [70]. 137 T399.14-20. If the whole of the partnership is illegal, are the plaintiffs entitled to restitution for monies spent and payments not claimed?
Plaintiff Submissions
(a) A company of which he was a director, Slavica Pty Ltd, to pay $25,000 to the defendant as a contribution towards the costs of purchasing the property;
(b) The second plaintiff to forego sums of money owing to it under the building contract, namely the $76,850; and
(c) The second plaintiff to carry out works, including the Additional Works, above and beyond the work for which it was paid under the building 138 contract.
Are the plaintiffs entitled to equitable compensation or an account of profits?
Relevant Legal Principles – Fiduciary Duties
The relationship between partners within the meaning of s 6 of the Partnership Act is recognised as an established category of a fiduciary relationship: Hospital Products Ltd v United States Surgical Corporation [1984] HCA 64; 156 CLR 41 at 96 (Hospital Products) (Mason J). In their capacity as partners in the partnership, partners owe fiduciary duties to each other in respect of any dealings with the property of the partnership and the business of the partnership: Chan v Zacharia [1984] HCA 36; 154 CLR 178 at 196 (Chan v Zacharia) (Deane J).
In Birtchnell v Equity Trustees Executors and Agency Co Ltd [1929] HCA 24; 42 CLR 384 at 407-498, Dixon J as his Honour then was, made the following observations about the fiduciary duties owed by partners:
The relation between partners is, of course, fiduciary. Indeed, it has been said that a stronger case of fiduciary relationship cannot be conceived than that which exists between partners. “Their mutual confidence is the life-blood of the concern. It is because they trust one another that they are partners in the first instance: it is because they continue to trust one another that the business goes on” (per Bacon V.C. in Helmore v Smith (1886) 35 Ch D 436 at 444). The relation is based, in some degree, upon a mutual confidence that the partners will engage in some particular kind of activity or transaction for the joint advantage only. In some degree it arises from the very fact that they are associated for such a common end and are agents for one another in its accomplishment.
138 Plaintiffs’ submissions in chief 4 December 2019 [18].
In Chan v Zacharia at 199, Deane J held that a person who is under a fiduciary obligation to a partner in a partnership must account to the other partner to whom the obligation is owed for any benefit or gain which has been obtained or received through the use of the fiduciary position or of an opportunity or knowledge deriving from it.
In Hospital Products at 107, Mason J, as his Honour then was, held that a fiduciary will be liable to account for a profit or benefit obtained by reason of the fiduciary position or by the fiduciary taking advantage of opportunity or knowledge which was derived as a result of their position as a fiduciary.
If the court is satisfied that one partner has breached their fiduciary duties owed to the other partner, the general principle is that the breaching party cannot be permitted to retain the benefit or profit which was obtained by reason of the breach of fiduciary duty: Hospital Products at 107 (Mason J).
Relevant Legal Principles – Equitable Compensation
Upon a breach of the equitable obligation of fiduciary duties, a court in the jurisdiction of equity may utilise its discretion to order equitable compensation to compensate an aggrieved plaintiff by pecuniarily putting them in the position as they would have been before the breach of the fiduciary duty: Nocton v Lord Ashburton [1914] AC 932 at 952 (Viscount Haldane); McKenzie v McDonald [1927] VLR 134 at 146.
In Hill v Rose [1990] VR 129 at 143 (Hill v Rose), Tadgell J made the following observations about equitable compensation:
The remedy, like any equitable remedy, is necessarily to be fashioned to meet the needs of the case. The method of calculation of monetary compensation will vary according to the nature of the fiduciary obligation whose breach is to be addressed. It might be appropriate to compensate the plaintiff’s loss by reference to the defendant’s gain, as in McKenzie v McDonald. Compensation may be awarded, however, whether or not the defendant has made any pecuniary gain.
Relevant Legal Principles – Account of Profits
In Dart Industries Inc v Decor Corporation Pty Ltd (1993) 179 CLR 101 at 114 (Dart Industries Inc), Mason CJ, Deane, Dawson and Toohey JJ held that an account of profits is not a remedy that acts to punish the defendant but instead prevents the defendant’s unjust enrichment. Their Honours in Dart Industries Inc at 115 further held that the remedy of an account of profits is not awarded to compensate the plaintiff.
An account of profits only targets the profits made by the errant fiduciary that were made improperly as it would be unconscionable for them to retain the profits made dishonestly: V-Flow Pty Ltd v Holyoake Industries (Vic) Pty Ltd [2013] FCAFC 16; 296 ALR 148 at [57].
In determining the quantum to be awarded for an account of profits, undertakes the ‘nearest approximation which it can make to justice’ Colburn v Simms (1843) 2 Hare 543 at 560 (Wigram VC); Dart Industries Inc at 119.
Akin to other remedies in equity, whether an account of profits is ordered remains at the discretion of the court: Warman International Limited v Dwyer (1995) 182 CLR 544 at 560-561 (Warman International Limited).
Relevant Legal Principles – Election Between Equitable Remedies and Discretionary Nature of Equitable Relief
A plaintiff must elect between equitable compensation and an account of profits as they are inconsistent remedies and a plaintiff is unable to receive double recovery: Dr Martens Australia Pty Ltd v Bata Shoe Co of Australia Pty Ltd [1997] FCA 505; 75 FCR 230 at 507:232 (Dr Martens Australia). The election made binds the plaintiff: Warman International Limited at 559.
In GM & AM Pearce & Co Pty Ltd v Australian Tallow Producers [2005] VSCA 113 at [61] Warren CJ made the following observations about when a plaintiff ought to make the election between equitable compensation and an account of profits:
A plaintiff, where faced with a choice between an account of profits or equitable compensation, must make a decision as to which one it will pursue….Normally, where both remedies are available, a plaintiff must elect between them. Ordinarily, the election need not be made before the trial starts and may be delayed until determination of the cause of action. There is therefore no difficulty where the plaintiff claims both equitable compensation and an account of profits in the prayer for relief, however, election must be made when (but not before) judgment is given. Where the plaintiff does not know which remedy is more favourable at the time of judgment on liability, the court may order discovery or other orders designed to give the plaintiff the information it requires to make the election.
Plaintiff Submissions
In the amended statement of claim, the plaintiffs alleged that by virtue of the partnership agreement, the defendant owed the first plaintiff fiduciary duties. The plaintiffs pleaded that the fiduciary obligations included a duty to provide an account of all of the partnership assts, to avoid profiting personally from partnership activities and to account for benefits obtained from partnership business or assets without the informed 139 consent of the other partner, namely the first plaintiff.
The plaintiffs submitted that the defendant owed fiduciary duties as a result of the partnership agreement and breached said duties by treating the property as his own, including when the property was sold and when the defendant disbursed the proceeds 140 to discharge his personal debts.
Conclusion
139 Plaintiffs’ amended statement of claim 22 October 2019 [8A]. 140 Plaintiffs’ submissions in chief 4 December 2019 [76]; Plaintiffs’ submissions in reply 16 March 2020 [20]. fiduciary obligation owed by the defendant would directly flow from the tax avoidance term which was illegal or unenforceable as against public policy and would destroy the 141 plaintiffs’ ability to seek either of the equitable remedies pleaded.
The decision of Brenner v First Artists Management Pty Limited [1993] 2 VR 221 at 262 distinguishes between equitable compensation from an account of profits: in that an account of profits is ordered to force a party to account for the profit made to the party claiming so to prevent unjust enrichment. An account of profits is not ordered by a court 142 to punish a party: see Brenner at 263.
It is noteworthy that a plaintiff who seeks to claim both equitable compensation and an account of profits must elect between the two remedies, so to avoid doubling up of an award: see Warman International Limited at 561; Dr Martens Australia.
The plaintiffs have failed to make an election. The court has not received a breakdown of costs and expenses. The plaintiffs have not demonstrated the basis for an account of profits.
In response to the failure to make an election for an equitable remedy, the plaintiffs correctly submitted that the court had discretion to order either form of relief to be assessed at a later date. The plaintiffs urged this course of action as the defendant had not disclosed the whole of his dealings with the property which inhibited the plaintiffs to accurately assess the profit gained or the detriment caused by the defendant’s 143 breaches.
As the evidence does not establish on the balance of probabilities that the defendant owed the first plaintiff fiduciary obligations pursuant to a partnership, the court need not consider the question of equitable compensation nor an account of profits. Further, the court is not, on the evidence, in a position to determine an account of profits in any event.
Did the defendant pay the second plaintiff $76,850 in cash on 1 July 2013 as part payment towards the amount due under the HIA Contract?
Evidence
John Cobanov
In the first witness statement of the first plaintiff, the first plaintiff claimed that that defendant gave him a ‘tax invoice’ for $76,850 that the defendant had prepared at around the time the defendant was arranging finance to purchase the property. The defendant said to the first plaintiff words to the effect of “this is required by the bank, 144 can you sign this as paid?”.
The first plaintiff asserted he had previously determined in early June 2013 that the amount he could carry was the first two progress payments and approximately one half of the third progress payment. It was the first plaintiff’s understanding that the invoice
141 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [80]; T412.41-46. 142 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [79]. 143 Plaintiffs’ submissions in reply 16 March 2020 [21]. 144 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [30]. was the means of indicating his contribution of waiving the first 20 per cent of the 145 contract price.
In the second witness statement of the first plaintiff, the first plaintiff claimed that he had never received $76,850 in cash from the defendant. The first plaintiff stated that he did not author the ‘tax invoice’ for $76,850 nor did he arrange for anyone else to 146 create it.
The first plaintiff claimed that the ‘tax invoice’ was handed to him by the defendant at the meeting on 1 July 2013. The first plaintiff confirmed he signed it and then handed 147 it back to the defendant. The first plaintiff referred to invoices relating to the Phyllis 148 Ashton project and annexed them to his second witness statement.
At the hearing on 21 October 209, the first plaintiff gave evidence that he was not computer literate. The first plaintiff stated that the extent of his ability to use a computer only involved being able to log on, read emails and respond to emails. The first plaintiff gave evidence that he did not know how to use Microsoft Word, any other word processing program, Microsoft Excel, any other spreadsheet program, the accounting 149 program MYOB nor any other business management software.
The first plaintiff gave evidence that he employed his daughter, Elle Cobanov, and a 150 bookkeeper to assist with business management of the second plaintiff. The first plaintiff stated that Elle Cobanov’s role involved preparing minimal paperwork for the 151 accounts.
In cross examination, it was put to the first plaintiff that he had received the $76,850 in cash from the defendant. The first plaintiff denied that he ever had received the amount 152 in cash.
The first plaintiff was referred to the invoice dated 1 July 2013 that bore the second plaintiff’s details at the top of the document, although the invoice referred to the second 153 plaintiff as Ashellhomes Pty Ltd. That invoice formed part of Exhibit 1. The first plaintiff agreed that the invoice displayed the second plaintiff’s company ABN, the 154 address of the second plaintiff and the first plaintiff’s mobile and fax number.
The first plaintiff also agreed that the invoice had his signature in the middle of the page 155 but denied this meant he had received the money in cash. When queried about why the invoice was signed and stamped as paid when the first plaintiff denied receiving the funds, the following exchange took place:
Counsel for the Defendant: Well, sir, it says there ‘Paid’ in the middle of the page doesn’t it?
145 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [27], [30]. 146 The second witness statement of the first plaintiff Tab 14 Exhibit 1 [3]-[4]. 147 The second witness statement of the first plaintiff Tab 14 Exhibit 1 [5]. 148 Tab 74 Exhibit 1. 149 T67.20-39. 150 T67.41. 151 T67.44-45. 152 T125.8 & T125.47. 153 Tab 24 Exhibit 1. 154 T125.22-29. 155 T125.33. First Plaintiff: It doesn’t matter. This document was tendered for – to get the finance. We required this to get the finance with this. Without this document, he could not get the finance. It was impossible, he had no money.
Counsel for the Defendant: So it says ‘Paid’ on that page, does it not? 156 First Plaintiff: It doesn’t matter. It’s – I did not get paid.
Elle Cobanov
In her witness statement, Elle Cobanov stated that she had worked on and off for her 159 father, the first plaintiff, for his building and construction business since 2013. Elle Cobanov stated that her duties included: sending and receiving emails, preparing 160 invoices, compiling and paying invoices and attending to all office based work.
Elle Cobanov claimed that during the periods 2013, 2014 and up until February 2015, invoices for the second plaintiff were produced by entering the data into the accounting program MYOB, which would then record the transaction and generate an invoice from 161 a template.
Elle Cobanov’s evidence was that the template used throughout that period consisted of a simple outline of a house logo which she had created in a photoshop program 162 when she commenced working for the first plaintiff. An example of that template was 163 annexed to her statement and formed part of Exhibit 1. Under the outline of the house, was the name of the second plaintiff written out as ‘ASHELL HOMES PTY LTD’ in capital letters. When unable to access MYOB, invoices were produced using Microsoft Word. Elle Cobanov claimed that while it differed slightly from the MYOB template, it contained the same logo of the outline of the house and was similar. The invoice numbers on both the MYOB invoices and the Microsoft Word invoices were 164 asserted to have no meaning.
When giving evidence at the hearing on 22 October 2019, Elle Cobanov reiterated that the MYOB template that formed part of Exhibit 1 was the format of invoices used by 165 the second plaintiff at the relevant period. Elle Cobanov also reaffirmed that there
156 T125.35-41. 157 T126.2-9. 158 T126.14-15. 159 Elle Cobanov statement Tab 13 Exhibit 1 [3]. 160 Elle Cobanov statement Tab 13 Exhibit 1 [4]. 161 Elle Cobanov statement Tab 13 Exhibit 1 [6]. 162 Elle Cobanov statement Tab 13 Exhibit 1 [7]. 163 Tab 73 Exhibit 1. 164 Elle Cobanov statement Tab 13 Exhibit 1 [8]. 165 T144.36. was another template used at the time for invoices, but that it was a Microsoft Word 166 document with the same logo of the outline of a house.
In her witness statement, Elle Cobanov stated that in the office she had never seen or used a stamp that produced a red square with the words “Paid”, “Date” and “CHQ 167 No”. There were no other employees in the office during the relevant periods or undertaking administration work for the business of the second plaintiff. There was a 168 bookkeeper named Jackie who prepared the Business Activity Statement.
Elle Cobanov’s evidence was that she never produced or issued invoices for progress 169 payments or any other payments in relation to the project.
When shown the invoice dated 1 July 2013, which had the “Paid” “Date” “CHQ No” stamp on it and no outline of the house as a logo, Elle Cobanov stated she did not recognise the invoice and that she could not recall if invoices in that format had been 170 used at any stage throughout her time working for the second plaintiff.
Kiki Josifovski
First Plaintiff: If you can give me a significant upfront payment this will give me the momentum to build it quickly. It will mean you secure my services for your job only, and I will just focus on your place. Otherwise I have to take on other jobs as well and I won’t be able to build your place as quickly. By you paying the money up front I can order all the materials and secure the trades, and it will mean I can get to lock up quickly. I need up to and including half of the third progress payment.
Defendant: How far will that take me?
First Plaintiff: It will probably get the roof trusses up by the end of the year. 172 Defendant: Okay I will see what I can do.
The defendant noted that at that stage, he already had the unconditional loan approval after Patrick Bouquiaux had verbally conveyed it to him on the phone. The defendant referred to the letter dated 1 July 2013 from Patrick Bouquiaux confirming the status of 173 the loan.
The defendant stated that the payment of $76,850 represented the first progress payment (deposit), the second progress payment (full payment of the floor slab) and
166 T144.41. 167 Elle Cobanov statement Tab 13 Exhibit 1 [9]. 168 Elle Cobanov statement Tab 13 Exhibit 1 [11]. 169 Elle Cobanov statement Tab 13 Exhibit 1 [17]. 170 T145.3, 20-21. 171 The first witness statement of the defendant Tab 8 Exhibit 1 [29]. 172 The first witness statement of the defendant Tab 8 Exhibit 1 [29]. 173 The first witness statement of the defendant Tab 8 Exhibit 1 [30]. part of the third progress payment (part payment of the roof frame) under the HIA 174 Contract.
The defendant stated that the $76,850 was paid to the first plaintiff in cash, from funds that were gifted to the defendant by his parents, Snezana Josifovski and Ratko Josifovski. The cash payment was solely derived from the cash provided by the defendant’s parents, meaning that the defendant did not need to draw funds from the 175 Westpac Bank loan.
After handing the $76,850 to the first plaintiff, the defendant asserted that the first 176 plaintiff gave him an invoice stamped “paid”. The invoice dated 1 July 2013 was signed by the first plaintiff and was annexed to the first statement of the defendant, 177 becoming part of Exhibit 1.
The defendant claimed that he proceeded to give the signed and stamped invoice to Patrick Bouquiaux. The defendant’s understanding was that Patrick Bouquiaux submitted the invoice to Westpac Bank. The invoice was submitted along with a letter under the hand of Patrick Bouquiaux confirming the nature of the invoice and including a letter under the hand of Snezana Josifovski confirming that she had gifted her son $76,850.
In the defendant’s second witness statement, the defendant denied that he did not pay the first plaintiff $76,850 and also denied preparing the 1 July 2013 tax invoice. The defendant claimed that the tax invoice was prepared, stamped and signed by the first 178 plaintiff.
The defendant could not recall whether or not the invoices in relation to the Phyllis Ashton project included in the second witness statement of the first plaintiff had been 179 issued to him directly.
The defendant also claimed that he did not know whether Elle Cobanov prepared the invoices for the property but confirmed he had received invoices from the second plaintiff, annexing them to his first witness statement. The defendant denied ever having received an invoice from the second plaintiff bearing the logo of the outline of a 180 house.
In cross examination, the defendant was taken to various invoices from the second plaintiff to the defendant in relation to the Phyllis Ashton project which were also part 181 of Exhibit 1. It was put to the defendant that the Phyllis Ashton invoices were similar to the 1 July 2013 invoice, that in amongst other things, the spelling of the second 182 plaintiff was ‘Ashellhomes Pty Ltd’.
The defendant confirmed in cross examination that the 1 July 2013 was the first invoice allegedly received from the second plaintiff in relation to the development of the
174 The first witness statement of the defendant Tab 8 Exhibit 1 [31]. 175 The first witness statement of the defendant Tab 8 Exhibit 1 [32]. 176 The first witness statement of the defendant Tab 8 Exhibit 1 [32]. 177 Tab 24 Exhibit 1. 178 The second witness statement of the defendant Tab 15 Exhibit 1 [5]-[6]. 179 The second witness statement of the defendant Tab 15 Exhibit 1 [7]. 180 The second witness statement of the defendant Tab 15 Exhibit 1 [17]. 181 Tab 74 Exhibit 1. 182 T237.26-27. property. The defendant was then taken to the second invoice dated 2 December 184 2013 received for the development and the defendant agreed that the second invoice 185 was in a completely different format to the 1 July 2013 invoice.
It was put to the defendant that the remaining invoices received from the second plaintiff for the development of the property were all in the format of the 2 December 2013 186 invoice as opposed to the 1 July 2013 invoice. The defendant conceded this point.
The defendant was also taken to an email he had sent from his ACT government email 187 address back in 2011 in relation to the Phyllis Ashton project. The email had been sent to two email addresses in the name of the second plaintiff and attached an invoice in the form of a Microsoft Excel spreadsheet named ‘Yerrabi Invoice 17 June 2011’. When referred to the 2 December 2013 invoice and the invoices in the same format thereafter, the defendant conceded that those invoices were in a similar template as 188 invoice attached to the email in relation to the Phyllis Ashton project.
It was put to the defendant that he had drafted all of the invoices that were in the similar template to the 2 December 2013 and that they had originated from a template the defendant had from 2011 in relation to the Phyllis Ashton project. The defendant denied 189 these claims.
In relation to this point, the defendant was taken to the Loan Application documentation for the Westpac loan that became Exhibit 13 in the proceedings. On the first page of the document was a heading ‘customer contribution’, underneath it read ‘where is the customer’s contribution coming from?’. On the document, the boxes savings/bank account and other were ticked. The word gift was written alongside other. When asked who had written the word ‘gift’ the defendant responded that he was not sure but that 190 it may have been the broker, Patrick Bouquiaux.
The defendant agreed that there was no other reference in the Loan Application documentation to the gift. The defendant however noted that attached to the back of the documentation was a letter under the hand of his mother Snezana Josifovski dated 7 June 2013 which stated she had provided the defendant with a gift of $76,850 to 191 assist with the deposit.
The defendant gave evidence that he had received the gift of $76,850 from his mother at the time he had signed the Loan Application on 7 June 2013, which is also the date 192 of his birthday.
In cross examination the defendant could not recall the exact date that his mother had given him the $76,850 but stated that it was in the days leading up to his birthday on 7 193 June 2013.
183 T237.29-30. 184 Tab 43 Exhibit 1. 185 T237.40. 186 T238.6-9. 187 Tab 78 Exhibit 1. 188 T240.44. 189 T241.29-35. 190 T266.30. 191 T266.32. 192 T267.18 & T268.45. 193 T323.43-44.
When queried about what denominations the $76,850 was given to the defendant in, the defendant gave evidence that the money was a mix of $50 and $100 notes, arranged in $10,000 stacks with the remaining stack of $6,850. The defendant agreed 194 that it was broken up into approximately six or seven stacks of cash.
It was the defendant’s evidence that his mother had given him the $76,850 at his parents’ family home located in Harrison. The defendant stated that the exchange took place in the living room of the family home, which was open plan and included a dining room setting. The defendant gave evidence that after they had eaten dinner his parents had said “we’re here to help you like we helped your brother” and then his mother 195 proceeded to hand him the money.
The money was in an envelope and the defendant stated that he did not open the 196 envelope when he first received it from his mother. The defendant stated that it was 197 a white envelope and could not recall whether there was any writing on the envelope. When asked when he first discovered the amount of stacks, the defendant claimed that he later took the envelope to his bedroom in the family home in Harrison and opened the envelope. He proceeded to count the money and then put it away in his wardrobe for safekeeping. The defendant stated that he had taken the money out of his wardrobe 198 and placed it onto his bed on at one least occasion to recount the amount.
The defendant gave evidence that he had taken the $76,850 with him when he met with the first plaintiff on 1 July 2013. The defendant stated that the money was no longer in the same white envelope but had instead been transferred to a grey Country Road 199 tote bag.
When queried why he knew he needed to take the money to the meeting with the first plaintiff, the defendant again affirmed they had previously discussed the first plaintiff 200 requiring the funds. The defendant gave evidence that the meeting occurred at the 201 first plaintiff’s workplace address.
The defendant stated that he took the cash from the Country Road tote bag and handed it to the first plaintiff. The first plaintiff then allegedly counted the funds in the 202 defendant’s presence before putting the cash to one side on the table. The defendant stated that the stacks of cash remained on the side of the table when he left and 203 confirmed that he believed 1 July 2013 was the last time he had seen the $76,850.
It was put to the defendant that the contract to purchase the land was not going to exchange until 2 July 2013 and that there was no certainty exchange would proceed. The defendant claimed that he was quite certain exchange would proceed given he had his finances secured at the time and exchange had been booked to take place on 204 2 July 2013.
194 T324.25-34 & 36. 195 T324.40-43, 45-47 & T325.1-5. 196 T325.9. 197 T325.16-18. 198 T325.11-24, 25, 29-34. 199 T325.41-22, 44-46 & T326.1-11. 200 T326.13-19. 201 T328.18. 202 T327.30-46. 203 T328.1-13. 204 T328.14-20.
The defendant conceded that there was perhaps a risk that there would be a delay in 205 settlement and that the defendant may not actually have the land at all. The defendant also acknowledged that the first plaintiff would not actually be able to 206 commence work until the defendant had possession of the land. It was agreed by the defendant that he gave the first plaintiff $76,850 on an allegedly urgent basis when 207 there was no land for the second plaintiff to commence work on.
It was the defendant’s evidence that the first plaintiff gave him the 1 July 2013 invoice but that he was not sure whether it had been produced by the first plaintiff, Elle Cobanov 208 or the first plaintiff’s bookkeeper. The defendant denied stamping it as paid with the stamp that read “Paid” “Date” “CHQ No” and that he did not think he wrote the date into 209 the stamped area of the invoice but he could not recall.
It was put to the defendant that he had drafted the 1 July 2013 invoice for the first plaintiff to sign and then had stamped it as paid and entered the date after the first plaintiff signed it, before the defendant submitted it to Westpac Bank. The defendant 210 denied this.
The defendant was unsure whether he took the original tax invoice or whether he took 211 a copy, but thought it was most likely to be the original. The defendant stated he believed the first plaintiff made a copy of the invoice but conceded that he could not 212 remember if he saw the first plaintiff make a copy.
When asked why he did not simply retain the $76,850 until after settlement, the defendant claimed that the first plaintiff had assured him the trades and materials could be prearranged which would ensure the property would be built in the indicated 213 timeframe.
The defendant was further asked why he was content to give the first plaintiff $76,850 at a time when there was no security that the project would proceed, when the first 214 plaintiff allegedly owed the defendant’s father $31,000. The defendant confirmed he was content to pay the first plaintiff the $76,850 notwithstanding the first plaintiff 215 allegedly had not paid his own father back the $31,000.
The defendant was queried as to whether he had drafted the letter under the hand of Snezana Josifovski dated 7 June 2013. The defendant denied that he had drafted the letter and indicated that he did not know whether his mother had drafted the letter herself. The defendant admitted that his mother had not given him the letter at the same 216 time she had given him the $76,850 in cash.
The defendant was also referred to a document that was a loan enquiry with Tiffen & Co and had the name of Patrick Bouquiaux as the loan writer. This document was
205 T329.19-26. 206 T329.46-47. 207 T330.2-3. 208 T330.39-41. 209 T330.43, 45-47 & T331.1-4. 210 T331.30-35. 211 T331.6-13. 212 T331.15-17. 213 T330.8-12. 214 T330.14-29. 215 T330.22-24. 216 T323.27, 29, 31. 33-34. Exhibit 14 in the proceedings. That document recorded that the defendant and a contribution of gift/ other of $69,000 and in the details relating to contribution box the words “has been given a gift of $69,000 from his mum to help him” were written in.
It was put to the defendant that he had told Patrick Bouquiaux he had a gift of $69,000 as opposed to $76,850 on the basis that he never in fact received $76,850 from his 217 mother on his birthday. The defendant maintained he had received $76,850 from his mother, notwithstanding that Patrick Bouquiaux had recorded the amount $69,000 twice on the loan enquiry. The defendant however accepted that he had given Patrick Bouquiaux answers to every question he was asked but maintained he had told Patrick Bouquiaux he had a gift of $76,850. The defendant continued to state that Patrick Bouquiaux was mistaken on two occasions when recording the gift amount as 218 $69,000.
The defendant was also queried why Patrick Bouquiaux would have written down $69,000 in circumstances where the defendant had allegedly counted the amount as $76,850 at least twice in his bedroom. The defendant maintained he was unsure why 219 the mistake of $69,000 had been recorded multiple times.
The defendant was taken to a Westpac Bank Loan Offer that became Exhibit 15 in the proceedings. The loan offer was signed by the defendant on 4 July 2013. The defendant accepted that there was no amount of $76,850 received as a gift listed as 220 an asset in the document.
The defendant agreed that there were no other documents apart from the 1 July 2013 invoice and the letters under the hand of his mother to evidence the existence of the 221 $76,850.
The defendant denied the allegation he never gave the first plaintiff the $76,850 and further rejected that the 1 July 2013 invoice served the evidence the arrangement that the first plaintiff was going to forego $76,850 as part of his contribution to the 222 partnership.
Snezana Josifovski
Snezana (Susie) Josifovski prepared a witness statement dated 25 February 2019 that 223 formed part of Exhibit 1. In her witness statement, Snezana Josifovski confirms she is the defendant’s mother and that she knew the first plaintiff as he had built the family home in Harrison, as well as her husband Ratko Josifovski previously been retained by 224 the first plaintiff to undertake painting.
Snezana Josifovski’s witness statement details an exchange she recalls took place in or around the middle of 2013 with the defendant and the defendant’s father Ratko Josifovski:
217 T270.42-47. 218 T270.24-42, T271.3-4 & T273.18-19. 219 T326.21-27. 220 T227.6. 221 T331.19-25. 222 T331.27-28 & 37-39. 223 Tab 11 Exhibit 1. 224 Snezana Josifovski statement Tab 11 Exhibit 1 [1]-[2]. Defendant: John is asking for around $70,000 cash to start building my home.
Snezana Josifovski: We are here to help you. 225 Ratko Josifovski: We will help you like we helped your brother.
In her witness statement, Snezana Josifovski recalls that she handed the defendant $76,850 in cash at the family home in Harrison just prior to his birthday on 7 June 2013. 226 At the time, Ratko Josifovski was also present.
Snezana Josifovski also details a series of letters she signed in June and July 2013: one being dated 7 June 2013 and two others being dated 22 July 2013. The letters were signed at the request of Patrick Bouquiaux, who Snezana Josifovski knew as the mortgage broker of the defendant. The series of letters were annexed to Snezana 227 Josifovski’s witness statement.
The 7 June 2013 letter is addressed to Patrick Bouquiaux and states that Snezana Josifovski had provided her son, the defendant, with a gift of $76,850 to assist with the deposit to build the home. The letter confirmed there was no requirement for the defendant to repay the amount. This letter also formed the final page of Exhibit 13, being the Westpac Bank Introducer Application Pack.
The first 22 July 2013 letter is also addressed to Patrick Bouquiaux and clarified that the money gifted by Snezana Josifovski to the defendant was contributed to the construction of the home itself. The letter refers to a receipt of the contribution being attached.
The second 22 July 2013 letter is also addressed to Patrick Bouquiaux and further clarified that the money gifted to the defendant was contributed to the construction of the home itself pursuant to cultural practice. The letter details that the contribution is to the amount of $76,850 worth of building works at 1/104 Casey, ACT. This letter also refers to a receipt of the contribution being attached.
In relation to the references to a receipt of the contribution being attached to the 22 July 2013 letters, Snezana Josifovski claimed that the receipt was the 1 July 2013 invoice stamped as $76,850 being paid to the second plaintiff. Snezana Josifovski 228 recalled seeing the invoice in or around July 2013.
Snezana Josifovski stated that she could not recall whether she drafted the letters, whether Patrick Bouquiaux drafted them solely or whether it was a combined effort. The letters were to confirm with Westpac Bank that the gifted money was to go towards 229 the actual construction of the property.
Snezana Josifovski gave evidence at the hearing on 24 October 2019. It was noted by 230 counsel for the defendant that English was Snezana Josifovski’s second language.
225 Snezana Josifovski statement Tab 11 Exhibit 1 [4]. 226 Snezana Josifovski statement Tab 11 Exhibit 1 [6]. 227 Tabs 17, 18 and 19 of Exhibit 1. 228 Snezana Josifovski statement Tab 11 Exhibit 1 [8]. 229 Snezana Josifovski statement Tab 11 Exhibit 1 [7]. 230 T353.35. Snezana Josifovski’s evidence in chief merely consisted of the witness adopting the 231 truth of her statement and the statement being formally tendered as part of Exhibit 1.
In cross examination, Snezana Josifovski stated that she gave the defendant $76,850 in cash a few days before his birthday. Snezana Josifovski gave evidence that she gave the defendant the money during dinner in the living area of the family home in 232 Harrison.
Snezana Josifovski gave evidence that she had arranged the cash into bundles of $10,000 but that she could not recall how many bundles there were. The $10,000 bundles were made up of $50 and $100 denominations. Snezana Josifovski stated she had given the defendant the bundles of money in a white envelope. After giving the envelope to the defendant, Snezana Josifovski said that she believed the defendant 233 took it to his bedroom in the family home.
When asked whether that amount of money had come from, Snezana Josifovski gave evidence she had not withdrawn it from the bank but there was cash stored in the home 234 from saving. Snezana Josifovski stated that there had been more than $76,850 stored in the home but that she could not recall whether it was more or less than 235 $100,000 in total.
When referred to the 7 June 2013 letter, Snezana Josifovski gave evidence that she 236 did not type the letter but it did bear her signature. Snezana Josifovski stated that she believed she had first handwritten out the letter then provided it to Patrick Bouquiaux, she was unsure whether it may have been Patrick Bouquiaux who typed 237 the letter.
Shortly thereafter, Snezana Josifovski stated she could not recall if she had handwritten 238 the letter or whether she typed it or Patrick Bouquiaux typed it. Snezana Josifovski gave evidence that she did not have a printer at home and that she did not think she had a computer at home at the time. She rejected that she could not have typed it if she did not have a computer at home, instead stating she may have used a work 239 computer but she could not recall.
Snezana Josifovski gave evidence that the letter was the result of Patrick Bouquiaux calling her saying he required something in writing to confirm to Westpac that she had given the defendant the money. Snezana Josifovski was then provided with a copy of 240 the letter to sign by Patrick Bouquiaux.
In relation to the first 22 July 2013 letter, Snezana Josifovski gave evidence that she could not recall handwriting or typing the letter but confirmed it bore her signature. She
231 T355.6. 232 T356.4-5 & 7-12. 233 T356.16-22, 25-26, 28-29 & 33-34. 234 T356.40-43. 235 T357.1-9. 236 T357.20, 25-26. 237 T357.22-23, 28. 238 T357.10. 239 T358.14-17, 20. 240 T358.33-35, 37-40. could not recall where she signed it or if it was signed in the presence of any other 241 person.
Snezana Josifovski’s recollection of the first 22 July 2013 letter was that she recalled signing it and speaking with Patrick Bouquiaux. She gave evidence that Patrick Bouquiaux had said he needed documentation to prove that the money was given to the defendant as cash as he needed to prove to Westpac Bank that the money was 242 going towards the construction of the home.
When referred to the second 22 July 2013 letter, Snezana Josifovski confirmed that the 243 letter bore her signature. Snezana Josifovski was unable to recall where she was when she signed the letter, nor who had prepared the letter. She stated that it may have been Patrick Bouquiaux who typed the letter as she was aware he needed something for Westpac to prove the gift was given to the defendant after seeing the 1 244 July 2013 invoice.
Snezana Josifovski was cross examined as to whether anyone else was involved in preparing the second 22 July 2013 letter, including the defendant. Snezana Josifovski said the defendant may have said to her words to the effect of “we need something for 245 the bank. Patrick will call you” but she could not recall.
Ratko Josifovski
Ratko Josifovski prepared his first witness statement dated 7 June 2019 that formed 246 part of Exhibit 1. Ratko Josifovski is the father of the defendant and the husband of 247 Snezana Josifovski.
In his first witness statement, Ratko Josifovski confirms he was aware that the defendant had engaged the first plaintiff through the second plaintiff to construct the dwelling in Casey after the land was purchased in 2013. Ratko Josifovski knew the first plaintiff as the first plaintiff had built his family home in Harrison and because the first plaintiff had previously retained him to undertake painting work from time to time. The 248 trading name of Ratko Josifovski’s painting business was Roko Painting.
Although been unable to recall the date, Ratko Josifovski remembered a conversation with the defendant and his wife Snezana Josifovski where the following exchange took place:
Defendant: John is asking for around $70,000 in cash to start building my home.
Snezana Josifovski: We are here to help you. 249 Ratko Josifovski: We will help you like we helped your brother.
241 T358.25, 27-29, 31, 40-42. 242 T358.33-36. 243 T358.47. 244 T359.2-6 & 8-17. 245 T359.26-28. 246 Tab 10 Exhibit 1. 247 Ratko Josifovski first statement Tab 10 Exhibit 1 [1]. 248 Ratko Josifovski first statement Tab 10 Exhibit 1 [2]-[3]. 249 Ratko Josifovski first statement Tab 10 Exhibit 1 [4].
Ratko Josifovski could recall discussing the defendant’s request with Snezana 250 Josifovski where he told his wife to give the money to the defendant.
Ratko Josifovski stated that he recalled that he and his wife gave the defendant $76,850 just before the defendant’s birthday, although he could not recall the exact 251 date of the exchange.
Ratko Josifovski gave evidence at the hearing on 24 October 2019. As was the case for Snezana Josifovski, counsel for the defendant also indicated to the court that 252 English was Ratko Josifovski’s second language.
The evidence in chief of Ratko Josifovski consisted of confirmation that the witness was telling the truth about the information contained in his first and second witness statements, which were then formally tendered as part of Exhibit 1.
In cross examination, Ratko Josifovski confirmed he was present in the room when his wife gave the defendant the $76,850 in cash. He gave evidence that Snezana 253 Josifovski had handed the defendant a white envelope which contained the money.
When queried where the large sum of cash had come from, Ratko Josifovski stated 254 that the money was kept in the house as a result of saving from his hard work. Upon being asked whether that amount was all of the cash within the home, Ratko Josifovski gave evidence that there was perhaps a little bit more money in the house, but he was 255 unsure of the quantum.
Ratko Josifovski also gave evidence that he had previously given his other son, Goran Josifovski money. Although, Ratko Josifovski was unable to recall how much money 256 he had given to Goran Josifovski or when this had taken place.
Ratko Josifovski was referred to Exhibit 19 in cross examination. Exhibit 19 had been tendered through the defendant and on the third page of the bundle was a document dated 24 April 2017 under the hand of Ratko Josifovski written in Macedonian. The document specified that Ratko Josifovski would lend the defendant $100,000 and it was agreed that the defendant would return that amount upon the sale of the property.
Ratko Josifovski confirmed that he had written the document dated 24 April 2017 and 257 that it was in Macedonian. Ratko Josifovski confirmed that it recorded a loan of $100,000 which he had made to the defendant. When queried why a written record was made of the $100,000 loan to the defendant but not the bequeathing of $76,850, Ratko Josifovski stated that the amounts were for different purposes. The $76,850 was to help build the house whereas the $100,000 was to be returned to him when the 258 defendant was able to.
During the course of cross-examination on the issue of the $76,850, Ratko Josifovski was also referred to the alleged $31,000 owed to him by the first plaintiff. Ratko Josifovski was questioned as to whether he was concerned that the defendant was
250 Ratko Josifovski first statement Tab 10 Exhibit 1 [5]. 251 Ratko Josifovski first statement Tab 10 Exhibit 1 [6]. 252 T353.36. 253 T362.2-17. 254 T362.24. 255 T362.26-34. 256 T363.4-11. 257 T363.22-24. 258 T263.31-40. going to give $76,850 to the first plaintiff when the first plaintiff allegedly owed him 259 $31,000. Ratko Josifovski responded that the debt owed to him by the first plaintiff had nothing to do with the decision to give the defendant the $76,850. It was the evidence of Ratko Josifovski that he trusted the defendant to do the right thing with the 260 $76,850.
Plaintiff Submissions
The plaintiffs submitted that the first plaintiff was earnest and forthright when giving his evidence. Reference was made to the limited computer literacy of the first plaintiff, including his lack of knowledge of how to use templates to create word processing 261 documents.
The plaintiffs stated that the defendant was inexplicably unable to recall key events or circumstances, including the date he had received the $76,850 in cash from his parents. It was submitted that key documents and witnesses which would otherwise be available to support the defendant’s version of events were not adduced into evidence 262 leaving the defendant’s evidence uncorroborated.
The plaintiffs submitted that the court should not accept that the defendant was given $76,850 by his parents shortly before his birthday and that the whole of that amount was then given to the first plaintiff on 1 July 2013.
Without the gift of $76,850, the plaintiffs asserted that the defendant would have had to seek 100 per cent finance of the build cost in his Westpac Loan Application. The plaintiffs also referred to the misinformation as to the loan purpose, being the various references to it being an investment property and the anticipated rental returns. The available inference was that without the $76,850 gift, the finance would not have been 263 available.
The building cost had to be known prior to know how much money was required. The preparation of plans were a prerequisite to determining the building costings. The plans prepared by Robert Jukic were dated 4 June 2013 but bear a house energy rating stamp of 6 June 2013. The plaintiffs submitted that even if the plans were given to the first plaintiff on the day the defendant received them, the earliest date the defendant could have had the plans was 4 June 2013 but it was more likely 6 June 2013.
The plaintiffs submitted that the evidence of Snezana Josifovski was lacking outside of scripted details in that she could not recall details that would otherwise be memorable. It was submitted that Snezana Josifovski was unable to commit to any meaningful circumstances regarding the preparation of the letter dated 7 June 2013 that she 264 signed.
There was no evidence of a discussion between the defendant and his parents as to how the specific amount of $76,850 was arrived at. The plaintiffs noted that $76,850 amount to exactly 20 per cent of the $384,250 build cost as set out in the HIA contract.
259 T365.11-12. 260 T365.14-18, 29-33. 261 Plaintiffs’ submissions in chief 4 December 2019 [6]. 262 Plaintiffs’ submissions in chief 4 December 2019 [7]-[8]. 263 Plaintiffs’ submissions in chief 4 December 2019 [23]. 264 Plaintiffs’ submissions in chief 4 December 2019 [23]. The plaintiffs also stated that this was the amount that the first plaintiff was to contribute to the partnership.
It was submitted that in order for the court to accept the defendant’s version as to the $76,850, the court would have to accept that the specific and idiosyncratic amount of $76,850 was arrived at by pure chance and that it was given to the defendant at some point between 4 and 6 June 2013.
The plaintiffs highlighted that no documents were produced to show the source of that amount of money but instead Snezana Josifovski and Ratko Josifovski gave evidence it had come from an unspecified and unknown amount of cash which they had on hand in their family home. The plaintiffs submitted that the only documentation in relation to the $76,850 was the 1 July 2013 invoice, a highly disputed document in the proceedings.
The plaintiffs also referred to the evidence of the defendant that he had counted the money in his bedroom yet Patrick Bouquiaux had recorded the incorrect amount of $69,000 twice on the loan application. The plaintiffs submitted that as Patrick Bouquiaux was the defendant’s mortgage broker acting on the defendant’s instructions, the court ought to infer that Patrick Bouquiaux was told by the defendant the amount was $69,000. It would be logically implausible for the defendant have been given and to have personally counted the amount as $76,850, yet tell Patrick Bouquiaux he only 265 received $69,000 as a gift.
The plaintiffs reiterated the absence of Patrick Bouquiaux in relation to the $76,850 issue, noting that he could have given evidence as to:
Why he inexplicably twice wrote the wrong gift amount of $69,000 on the loan paperwork.
The circumstances surrounding the creation and timing of the letter dated 7 June 2013 signed by Snezana Josifovski.
The extent of the assurances provided by him as to the defendant’s approval for finance that provided the defendant with the willingness to sign a building contract and pay the first plaintiff $76,850 in cash prior to 266 exchanging on the land.
The plaintiffs invited the court to make a Jones v Dunkel inference to these aspects of the $76,850 that the evidence of Patrick Bouquiaux would have undermined the version 267 of events propounded by the defendant, Snezana Josifovski and Ratko Josifovski. The drawing of this inference does not assist to any significant degree in the resolution of this question of the $76,850.
The plaintiffs referred to the evidence of the defendant in the first statement of the defendant that the first plaintiff asked for a large upfront payment on 1 July 2013 and that the defendant happened to have received that exact amount from his parents as a gift, happened to have the full amount on his person at the meeting and decided to pay it to the first plaintiff, all at the same time.
265 Plaintiffs’ submissions in chief 4 December 2019 [23]-[26]. 266 Plaintiffs’ submissions in chief 4 December 2019 [66]. 267 Plaintiffs’ submissions in chief 4 December 2019 [68].
It was submitted that the cash gift of $76,850 preceded the first plaintiff’s request for that sum by a matter of weeks and that payment of that cash to the first plaintiff occurred before the defendant had even secured land to build the house upon.
In reference to the 1 July 2013 tax invoice, the plaintiffs submitted it was not referable to the format of invoice utilised by the second plaintiff at that point in time. It was instead referable to a form of invoices that the second plaintiff had used previously, including at the time of the Phyllis Ashton project with the defendant and Goran Josifovski.
The plaintiffs emphasised the evidence of Elle Cobanov that she did not recognise the template of the 1 July 2013 invoice, nor did she ever see or use a stamp at the workplace of the second plaintiff that produced a red square with the words “Paid” “Date” and “CHQ No”.
The plaintiffs submitted that the court should draw an inference that the 1 July 2013 tax invoice was authored by the defendant as he had a similar template in his records from the Phyllis Ashton project. The plaintiffs further invited the court to draw an inference that the purpose of the defendant generating the 1 July 2013 tax invoice was for the purposes of obtaining finance, a responsibility of the defendant pursuant to the 268 partnership agreement.
It was submitted that the defendant’s evidence as to the $76,850 failed to add up. The defendant’s evidence was inconsistent with the loan documentation and the defendant’s own witness statements. The plaintiffs claimed the defendant’s version 269 was implausible in isolation and in the context of the remaining evidence.
The plaintiffs submitted that the court would more readily accept the evidence of the first plaintiff that he had never received the $76,850. The better explanation of the 1 July 2013 invoice was that it was created by the defendant and signed by the first plaintiff to represent the 20 per cent contribution of the first plaintiff to the cost of the build and to ensure consistency with the defendant’s loan application. Such a conclusion was consistent with the evidence of the first plaintiff and Elle Cobanov as to 270 the records of the second plaintiff.
In oral submissions on 16 June 2020, counsel for the plaintiffs submitted that the court would have to accept that the amount of $76,850 was arrived at by pure chance by the defendant and his parents. Such was the case in circumstances where there was no evidence to show the source of the amount, instead it was evidence from Snezana Josifovski and Ratko Josifovski that they had an unknown and unspecified amount of 271 cash stored in their home.
Counsel for the plaintiffs also submitted that in circumstances where the defendant was alleging an arm’s length builder/ client relationship, providing the first plaintiff with $76,850 in cash prior to the defendant having a legally enforceable right to build on the 272 land did not stand up to scrutiny.
Counsel for the plaintiffs reiterated its call for an inference to be drawn that the defendant authored the 1 July 2013 invoice from a template he had in records from the
268 Plaintiffs’ submissions in chief 4 December 2019 [24]. 269 Plaintiffs’ submissions in chief 4 December 2019 [25]. 270 Plaintiffs’ submissions in chief 4 December 2019 [26]. 271 T383.13-22. 272 T384.16-35. Phyllis Ashton project and that he had authored the 1 July 2013 invoice for the purposes of obtaining finance which was his responsibility pursuant to the partnership 273 agreement.
Consideration
The first plaintiff conceded that he had signed the 1 July 2013 invoice as paid. The first plaintiff’s evidence was that he only signed the 1 July 2013 invoice as paid as it was required in order to obtain finance for the build. I am satisfied on the evidence on the balance of probabilities that the 1 July 2013 invoice was paid.
I accept that the first plaintiff required the upfront payment to secure trades and materials. The defendant referred to the following events that took place prior to the 1 July 2013 meeting:
The defendant had received the $76,850 from his parents in cash on or about 7 June 2013;
Snezana Josifovski provided a letter dated 7 June 2013 to Patrick Bouquiaux, confirming she had given the defendant $76,850 to assist with the deposit to build his home;
A loan application dated 12 June 2013 had been lodged on the defendant’s behalf to borrow $555,870 from the Westpac Bank to purchase the property and build a house on it;
I reject the first plaintiff’s evidence that the defendant could not afford to fund the project alone and required the first plaintiff to assist in funding, as this finding was not open on the evidence.
I accept the evidence given by the defendant’s parents, Snezana Josifovski and Ratko Josifovski that:
Snezana Josifovski gave the defendant $76,850 in cash a few days before the defendant’s birthday;
The cash was broken up into approximately 6 or 7 bundles or bundles of $10,000 and 1 bundle of $6,850, comprising of multiples of $50 and $100 notes;
The exchange occurred in the living/ dining room in the family home in Harrison;
Snezana Josifovski gave the cash to the defendant in a white envelope; and
The defendant took the cash to his bedroom.
273 T384.46-50. 274 T395.5-9.
I accept the evidence of both Snezana Josifovski and Ratko Josifovski that the $76,850 was the product of life savings which they stored in their home.
I accept the 7 June 2013 letter and the two 22 July 2013 letters signed by Snezana Josifovski, were prepared before any dispute between the parties had arisen and well before the proceedings had commenced. The 7 June 2013 letter stated the gift was an amount of $76,850 and it was to assist with the deposit of the defendant’s home.
The defendant also submitted that a Jones v Dunkel inference was not open to be drawn in relation to Patrick Bouquiaux. It was submitted that as the defendant was not on notice to the content of his cross examination, it could not be foreseen by the defendant that Patrick Bouquiaux would be raised in the manner that he was nor that the loan application form would be used in the manner that it was. The defendant 275 maintained he had no obligation to call Patrick Bouquiaux. Again, the drawing of the inference does not assist to any significant degree in the resolution of this question.
The evidence of the first plaintiff that he was going to pay capital gains tax on his portion of the profit notwithstanding the tax avoidance term is in my view unreliable. I similarly reject first plaintiff’s evidence that he signed the 1 July 2013 invoice as paid although he did not receive the funds.
Counsel for the defendant was queried as to his response to the defendant and his parents arriving at the particular amount of $76,850 and the lack of evidence setting 276 out this process. The apparent coincidence was not explored in the evidence.
The 1 July 2013 invoice was stamped as paid and signed by the first plaintiff.
I am satisfied on the balance of the probabilities of the defendant’s version of the $76,850 on the basis the 1 July 2013 invoice is signed by the first plaintiff and I accept the corroborating evidence of Snezana Josifovski and Ratko Josifovski.
The plaintiffs referred to the issue of the defendant’s parents arriving at the idiosyncratic amount of 20 per cent of the contract sum prior to the contract being drafted and the questionably identical recollections of the defendant, Snezana Josifovski and Ratko 277 Josifovski.
The plaintiffs reiterated the concerns about the stamp on the invoice itself, in circumstances where the first plaintiff and Elle Cobanov gave unchallenged evidence that no such stamp was used by them in the course of the second plaintiff’s business, as well as referring back to the consistency of the 1 July 2013 invoice with the Phyllis Ashton project invoice that had been sent by the defendant to the second plaintiff in 2011.
The plaintiffs submitted that in the circumstances, the court would more readily find that the $76,850 was not paid by the defendant. Further, the 1 July 2013 invoice was generated by the defendant and signed by the first plaintiff for the purposes of obtaining 278 finance.
In oral submissions in reply, the plaintiffs submitted that it was not a mere coincidence as to the idiosyncratic amount of $76,850 nor the 1 July 2013 invoice sharing similarities
275 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [95]. 276 T404.33-41. 277 Plaintiffs’ submissions in reply 16 March 2020 [23]. 278 Plaintiffs’ submissions in reply 16 March 2020 [24]. with the format of the Phyllis Ashton project invoice. The 1 July 2013 invoice was a document generated by the defendant for the express purpose of proof of the first plaintiff’s contribution to the partnership which is why it was signed by the first 279 plaintiff.
Did the first plaintiff pay the defendant $25,000? What was the purpose and legal effect of that payment?
Relevant Legal Principles
Where A makes a voluntary payment to B or pays (wholly or in part) for the purchase of property which is vested either in B alone or in the joint names of A and B, there is a presumption that A did not intend to make a gift to B: the money or property is held on trust for A (if he is the sole provider of the money) or in the case of a joint purchase by A and B in shares proportionate to their contributions. It is important to stress that this is only a presumption, which presumption is easily rebutted either by the counter presumption of advancement or by direct evidence of A’s intention to make an outright transfer….
[R]esulting trust[s] are traditionally regarded as examples of trusts giving effect to the common intention of the parties. A resulting trust is not imposed by law against the intentions of the trustee…but gives effect to his presumed intention.
[I]f the purchase money is provided by two or more persons jointly, and the property is put into the name of one only, there is… presumed to be a resulting trust in favour of the other or others.
Where the doctrine of resulting trust applies where more than one person contributes funds towards the purchase, the result is presumed that the property will be held in shares proportionate to the parties’ corresponding proportion of the purchase price: Bloch v Bloch (1981) 189 CLR 390 at 397.
In Calverley v Green at 252, Gibbs CJ held that ‘the extent of the beneficial interests of the respective parties must be determined at the time when the property was purchased and the trust created’. The repayment of mortgage instalments by one party is not relevant in determining the operation of a resulting trust and the division of the proportion of shares in which the property is held.
The presumption of a resulting trust can be rebutted in the face of an inconsistent actual intention. Evidence as to the actual intention before or at the time of acquisition can
279 T443.45-48. inform whether the presumption has been rebutted: Charles Marshall Pty Ltd v Grimsley (1956) 95 CLR 353 at 364.
Evidence of an intention to merely loan the money towards the purchase can rebut the presumption of a resulting trust: Calverley v Green at 246; Melbourne Orthopaedic Group Pty Ltd v Stamford Aus-Trade & Press Pty Ltd [2015] VSCA 150.
In Potter v Potter [2003] NZLR 145 at [13], the New Zealand Court of Appeal made the following observations about the relationship between loans and resulting trusts:
The point of a resulting trust is to establish a proprietary interest, or right in rem. A loan, on the other hand, is an advance of money coupled with a contract for its repayment, with or without interest and other ancillary obligations. Even if the money is used to purchase property, and subject to the distinct question of mortgages, the lender acquires no interest in the property acquired. The right to repayment is a purely contractual one operating in personam.
Evidence
John Cobanov
In the first witness statement of the first plaintiff, the first plaintiff asserted that on 8 July 2013 he had a meeting with the defendant. At the meeting, the first plaintiff made out a cheque payable to the defendant. As the first plaintiff did not know how to spell the defendant’s surname, he provided the chequebook to the defendant to write in the surname. The first plaintiff then completed the balance of the details of the cheque for $25,000.
The first plaintiff asserted that the $25,000 was required by the defendant for the deposit on the land purchase. The first plaintiff claimed that while this had not previously been discussed, the first plaintiff took the view that they needed to make the venture work one way or another in order to get to the point of sale and then be able to 280 reimburse themselves.
In the second witness statement of the first plaintiff, the first plaintiff asserts that at no 281 stage did he owe Ratko Josifovski $31,000. The first plaintiff confirmed that he used the painting services of Ratko Josifovski for painting at Goran Josifovski’s home and 282 Ratko Josifovski’s own home but that he did not receive invoices for those jobs.
The first plaintiff confirmed that he had also used Ratko Josifovski’s painting services at his home in Forrest in 2011. The first plaintiff provided the materials and the equipment. While Ratko Josifovski did not invoice or provide the first plaintiff any paperwork for those services, the first plaintiff annexed a cheque butt for $3,000 283 payable to Ratko Josifovski dated 24 December 2011. The first plaintiff asserted that 284 the $3,000 was for the painting of his house in Forrest.
The first plaintiff noted that he had built the dwelling at Forrest and had engaged a contract painter to supply the materials and labour for the job. While not having any
280 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [32]. 281 The second witness statement of the first plaintiff Tab 14 Exhibit 1 [8]. 282 The second witness statement of the first plaintiff Tab 14 Exhibit 1[10]. 283 Tab 5 Exhibit 1. 284 The second witness statement of the first plaintiff Tab 14 Exhibit 1 [13]. paperwork for the job, the first plaintiff recalled that it was approximately $10,000 for 285 the materials and labour.
The first plaintiff denied that Ratko Josifovski was capable of undertaking painting work worth $31,000 in circumstances where he did not have employees or subcontractors, 286 nor did he provide the materials or any equipment.
The first plaintiff confirmed that he had never received any invoices, letters, reminders, statements or demands from or on behalf of Ratko Josifovski for payment of any 287 monies owed to Ratko Josifovski.
The first plaintiff also denied ever having conversations with the defendant in relation to the defendant receiving money on behalf of Ratko Josifovski or being Ratko Josifovski’s enduring power of attorney.
At the hearing, the first plaintiff was taken to part of Exhibit 1 which was a photocopy of three cheques. The bottom cheque was dated 8 July with the year obscured and was addressed to the defendant for the sum of $25,000. It was drawn by Slavica Pty 288 Ltd as trustee for Cobanov Family Trust. The first plaintiff gave evidence that he 289 believed the cheque was written on 8 July 2013 but he was unsure.
The first plaintiff was then referred to a document which contained a copy of a cheque butt which contained the words ‘8/7/13, land block 1/104 $25,000’. The security paper of the cheque read ‘land sale’. The first plaintiff gave evidence that he wrote the words 290 on the cheque butt and the words ‘land sale’. The document also contained a Bendigo Bank Transaction History for an account in the name of the second plaintiff which showed a cheque withdrawal on 10 July 2013 for $25,000. The document 291 became Exhibit 2.
When referred to Exhibit 2 in cross examination, the first plaintiff denied that he inserted 292 the writing ‘land sale’ after he wrote the cheque. When queried what the phrase ‘land sale’ meant and its purpose, the first plaintiff stated that it was for the bookkeeper’s records so that he could confirm if it was for 1/104 Casey and that it meant the particular 293 amount of money was a deposit for the land.
During cross examination, Exhibit 4 was tendered through the first plaintiff. It was a th document signed by the first plaintiff addressed to the defendant stating ‘On the 8 of July 2013, a loan of $25,000 was lent to Mr. Josifovski to settle land of 1/104 Casey. This is owed back to John Cobanov. ** interest to be calculated daily’. The first plaintiff stated he was unsure who had in fact produced the document but conceded he had 294 signed it.
285 The second witness statement of the first plaintiff Tab 14 Exhibit 1 [12]. 286 The second witness statement of the first plaintiff Tab 14 Exhibit 1 [9]. 287 The second witness statement of the first plaintiff Tab 14 Exhibit 1 [15]. 288 Tab 31 Exhibit 1. 289 T68.30-32. 290 T68.40. 291 T69.20. 292 T134.38. 293 T134.42-47 & T135.22-23. 294 T136.9-17 & T137.1-22.
The first plaintiff stated that while Exhibit 4 said the ‘loan’, the $25,000 was given to the defendant as part of the intention for the first plaintiff to receive the money back in the 295 division of profits after the sale.
In re-examination the first plaintiff gave evidence that Elle Cobanov may have created 296 Exhibit 4. When asked what he understood the word ‘loan’ to mean, the first plaintiff responded that he believed it was a loan against the property, showing that he had put $25,000 into the project and he was expecting the $25,000 when the profits were 297 divided.
Kiki Josifovski
In the first witness statement of the defendant, the defendant confirmed that he had received $25,000 via a cheque from the first plaintiff on or around 8 July 2013. The defendant stated that the cheque was drawn from another of the first plaintiff’s entities, 298 Slavica Pty Ltd (Slavica).
The defendant denied that the $25,000 was provided by the first plaintiff to cover the deposit for the land. The defendant had already paid the deposit for the land, being an 299 amount of $27,500, which he had paid on or around 1 July 2013.
The $25,000 was unrelated to the purchase of the land or the building of the dwelling itself upon it. The defendant claimed the $25,000 was actually payment for monies owed by the first plaintiff to Ratko Josifovski for painting work Ratko Josifovski had 300 undertaken at the first plaintiff’s home in Forrest in 2012. The amount owing by the first plaintiff to Ratko Josifovski was $31,000.
The defendant received the money on behalf of Ratko Josifovski as his father was unwell and unable to manage his financial affairs at the relevant time. In early January 301 2013, Ratko Josifovski had suffered a severe fall and consequent head trauma.
After multiple hospital admissions, the defendant observed that his father continued to suffer ongoing effects from his injury. The defendant then became Ratko Josifovski’s 302 power of attorney on 18 February 2014 and his primary carer.
The defendant claimed that in early 2013, his father had instructed him to chase up the $31,000 owed by the first plaintiff for the painting in Forrest. The defendant claimed he had asked the first plaintiff for the funds on multiple occasions and that the first plaintiff 303 knew that Ratko Josifovski was unwell.
At some point prior to the HIA Contract being entered but at a date unknown to the defendant, the defendant claimed that he had the following conversation with the first plaintiff:
295 T136.22. 296 T180.39-40. 297 T181.26-28. 298 The first witness statement of the defendant Tab 8 Exhibit 1 [42]. 299 The first witness statement of the defendant Tab 8 Exhibit 1 [43]. 300 The first witness statement of the defendant Tab 8 Exhibit 1 [44]. 301 The first witness statement of the defendant Tab 8 Exhibit 1 [40], [50]. 302 The first witness statement of the defendant Tab 8 Exhibit 1 [51], Tab 33 Exhibit 1. 303 The first witness statement of the defendant Tab 8 Exhibit 1 [47]-[48]. Defendant: Dad’s asking when you’re going to pay him for the work he did at your place. You know he’s unwell – it’s not fair for him to worry about that as well.
First Plaintiff: I’ll pay him what I can now and get the rest to him later. 304 Defendant: Ok great.
The defendant confirmed that he banked the $25,000 cheque on 8 July 2013 and it was paid into his personal Commonwealth Bank account on the same date. The funds were received into the defendant’s personal account on 8 July 2013 and the defendant then proceeded to transfer the amount to another Commonwealth Bank account in his name. The second bank account of the defendant was for the defendant to manage his 305 father’s funds or keep them for safekeeping.
The $25,000 cheque was made out to the defendant because Ratko Josifovski was unable to manage his financial affairs at that time. The defendant stated that Ratko Josifovski would not have had the capacity to bank the cheque and did not have any method of managing his financial affairs at that time as he did not use internet banking. Ratko Josifovski had requested that the cheque be made out to the defendant’s name 306 and bank account.
The defendant noted that he would receive money on his father’s behalf on other occasions after the injury, in order to facilitate payment for groceries and medical bills. 307 The management of Ratko Josifovski’s financial affairs was not a fixed arrangement.
After receiving the $25,000 cheque on 8 July 2013, the defendant stated he sent an email to the first plaintiff on 1 April 2014. That email included a direction to pay the remaining monies owing to Ratko Josifovski for the painting works to the defendant’s 308 bank account. The email was annexed to the first witness statement of the 309 defendant. The relevant portion of the email reads as the following:
John,
…
Account details for dad:
I have to western union it to him so just send to me.
CBA:
[Bank account information of the defendant]
…
Thanks
Kiki
304 The first witness statement of the defendant Tab 8 Exhibit 1 [47]. 305 The first witness statement of the defendant Tab 8 Exhibit 1 [46]. 306 The first witness statement of the defendant Tab 8 Exhibit 1 [52]. 307 The first witness statement of the defendant Tab 8 Exhibit 1 [53]-[54]. 308 The first witness statement of the defendant Tab 8 Exhibit 1 [49]. 309 Tab 34 Exhibit 1.
The defendant stated that the first plaintiff never paid the remaining monies owed to 310 Ratko Josifovski.
The first witness statement of the defendant referred to the document that had been produced and later became Exhibit 4 in the proceedings: the undated letter saying a loan of $25,000 had been lent to the defendant to settle land of 1/104 Casey. The defendant stated that he never seen the document prior to its production in the 311 proceedings.
The defendant also referred to the payment of stamp duty for the property. On 17 July 2013, the defendant was notified by his solicitors that $7,267.50 had to be paid to the ACT Revenue Office for stamp duty by 24 July 2013. The defendant provided a bank cheque from Commonwealth Bank to satisfy this payment and exhibited a copy of the bank cheque, ACT Revenue Office record and email from his solicitor regarding the 312 stamp duty.
In cross examination the defendant admitted he had received a cheque for $25,000 from the first plaintiff on 8 July 2013. The defendant accepted that Ratko Josifovski had 313 never given him any quotes nor documents to support the claim for $31,000.
The defendant confirmed that he had emailed the first plaintiff a demand for the monies owed but conceded no documentary evidence of the work undertaken by Ratko 314 Josifovski had been attached.
It was put to the defendant that there were no records in existence for the work Ratko Josifovski had performed on the first plaintiff’s Forrest home but the defendant responded that he did not know if that was the case. The defendant denied that there were no records due to the fact that Ratko Josifovski never undertook works to the value of $31,000. The defendant further denied that he never claimed the $31,000 from the first plaintiff, instead he asserted that he requested the money several times over a 315 long period.
When queried about paying the second plaintiff $76,850 in alleged circumstances where Ratko Josifovski was owed $31,000, the defendant gave evidence he was 316 content to pay the money to the second plaintiff.
Ratko Josifovski
In the first witness statement of Ratko Josifovski, he could not recall the exact date but recalls undertaking painting work for the first plaintiff. Ratko Josifovski estimates that it was approximately a year or so prior to the defendant purchasing the land in Casey in 317 2013.
The painting work occurred at the first plaintiff’s home in Manuka or Forrest. It was a large duplex and the first plaintiff was going to live in one of the two dwellings with his wife. Ratko Josifovski painted the exteriors of both houses, as well as the interior and
310 The first witness statement of the defendant Tab 8 Exhibit 1 [49]. 311 The first witness statement of the defendant Tab 8 Exhibit 1 [55]. 312 Tab 35 Exhibit 1. 313 T298.14-15, 31-35. 314 T298.41-46. 315 T299.1-2, 4-5, 7-8. 316 T330.14-24. 317 Ratko Josifovski first statement Tab 10 Exhibit 1 [7]. basement parking area of the first plaintiff’s house. Ratko Josifovski claimed that the 318 total cost of the job was $31,000 and that he recalled quoting it to the first plaintiff.
The painting works at the first plaintiff’s home was the last painting job that Ratko Josifovski had undertaken prior to becoming ill. Ratko Josifovski could not recall exactly 319 when he suffered from his head injury.
After becoming ill, Ratko Josifovski instructed the defendant to look after his medical appointments and financial affairs, including:
Depositing money that the defendant received on behalf of Ratko Josifovski into a bank account controlled by the defendant;
Paying Ratko Josifovski’s expenses from those funds; 320 3. Transferring funds to Ratko Josifovski when he was overseas.
Ratko Josifovski stated that he recalled frequently asking the defendant to chase the first plaintiff for the $31,000 he was owed. Ratko Josifovski frequently said to the defendant words to the effect of “please ask John to pay the money he owes me. He 321 still hasn’t paid me. He can pay you as you will need to look after me”.
Sometime after, Ratko Josifovski recalled having a conversation with the defendant where words to the following effect were exchanged:
Defendant: Dad, John has paid you $25,000 from the money he owes you. 322 Ratko Josifovski: I am lucky he paid anything – you look after it.
Pursuant to Ratko Josifovski’s instructions, the $25,000 paid by the first plaintiff to the defendant was kept in the defendant’s bank account so that the defendant could pay 323 his father’s bills and send money to him overseas when required.
In his second witness statement, Ratko Josifovski denied that he was unable to undertake the painting works at Forrest as alleged by the first plaintiff. Ratko Josifovski contended that he had used his own materials and equipment to undertake the job at 324 Forrest.
Prior to undertaking the work at Forrest, Ratko Josifovski claimed he provided a quote to the first plaintiff and that they had agreed to the cost of that work which he 325 subsequently undertook.
Ratko Josifovski further denied receiving the $3,000 from the first plaintiff on 24 326 December 2011.
After completing the work at Forrest, Ratko Josifovski stated that it was difficult to obtain payment from the first plaintiff. Ratko Josifovski was regularly contacting the first
318 Ratko Josifovski first statement Tab 10 Exhibit 1 [7]. 319 Ratko Josifovski first statement Tab 10 Exhibit 1 [8], [11]. 320 Ratko Josifovski first statement Tab 10 Exhibit 1 [12]-13]. 321 Ratko Josifovski first statement Tab 10 Exhibit 1 [9]. 322 Ratko Josifovski first statement Tab 10 Exhibit 1 [10]. 323 Ratko Josifovski first statement Tab 10 Exhibit 1 [17]. 324 Ratko Josifovski second statement Tab 16 Exhibit 1 [5]-[6]. 325 Ratko Josifovski second statement Tab 16 Exhibit 1 [9]. 326 Ratko Josifovski second statement Tab 16 Exhibit 1 [8]. plaintiff by phone to seek the payment. It was after becoming ill that Ratko Josifovski 327 then instructed the defendant to chase the first plaintiff for payment.
Under cross examination, Ratko Josifovski gave evidence that the $31,000 owed by the first plaintiff to him was not just for works undertaken at Forrest, but perhaps four 328 or five other suburbs. Ratko Josifovski also gave evidence that he had said he was 329 owed $25,000 to the first plaintiff when finishing the Forrest house painting.
When asked whether he had invoices or documents for the four or five other jobs, Ratko Josifovski responded that he had given the first plaintiff invoices and that they would be in the custody of the first plaintiff.
Ratko Josifovski confirmed he understood the first plaintiff paid the $25,000 to the 330 defendant. When asked whether the defendant had transferred the funds to him, Ratko Josifovski responded that the defendant took him to the doctor and continued to look after him. Ratko Josifovski stated that when the defendant received the money, he told the defendant to keep it in the defendant’s bank account. Upon receiving the $25,000, Ratko Josifovski gave evidence that he said to the defendant “thank you God. 331 He pay me a little bit of money. It doesn’t matter that it is not all of it, but he paid me”.
As referenced in the above issue on the $76,850, Ratko Josifovski gave evidence that he was not concerned the defendant was going to give $76,850 to the first plaintiff even 332 though the first plaintiff owed him $31,000, as he trusted the defendant.
Plaintiff Submissions
Purpose of the $25,000 Cheque
The plaintiffs submitted that the reason the first plaintiff caused $25,000 to be paid by cheque to the defendant was as a contribution towards the deposit for the land, pursuant to the partnership agreement. The plaintiffs asserted that the alternative reason advanced by the defendant, that it was for monies owed to Ratko Josifovski, 333 ought to be rejected.
Reference was made to Ratko Josifovski’s evidence at the hearing that the first plaintiff owed him money for a number of jobs in numerous suburbs in Canberra. The plaintiffs highlighted that no documents had been provided to support the claim, either for the $31,000 for the entirety of the Forrest job or breakdowns of costings for the other jobs in Canberra. It was noted that there had been no evidence as to a written demand for payment from the first plaintiff at point prior to the $25,000 being paid to the defendant, 334 nor was there any evidence of demand for the outstanding balance of $6,000.
The plaintiffs submitted that the defendant and Ratko Josifovski’s claim was inherently implausible due to the lack of documentation or any written demand for the monies 335 owed. While referring to the email sent to the first plaintiff by the defendant that referred to transferring the funds via Western Union to Ratko Josifovski, the plaintiffs
327 Ratko Josifovski second statement Tab 16 Exhibit 1 [9]. 328 T364.3-30. 329 T364.11-13, 39-41. 330 T364.43-44. 331 T364.46-47 & T365.1-5. 332 T365.29-30. 333 Plaintiffs’ submissions in chief 4 December 2019 [37]. 334 Plaintiffs’ submissions in chief 4 December 2019 [40]. 335 Plaintiffs’ submissions in chief 4 December 2019 [40]. noted this was the only reference to the defendant’s father in the material and that email 336 was dated 2 April 2014, many months after the cheque was written on 8 July 2013.
The plaintiffs also highlighted that Ratko Josifovski’s evidence indicated that he was not concerned about the defendant retaining the second plaintiff to build the home, notwithstanding the alleged circumstances that the first plaintiff supposedly owed him 337 the significant sum of $31,000 for at least one year.
It was submitted that in circumstances where Ratko Josifovski was aware that the defendant also was to pay the second plaintiff $76,850 notwithstanding the $31,000 owed, it was illogical that he would not have objected to the defendant providing that 338 sum of money to the second plaintiff.
Such concern ought to have also been shared by the defendant himself if he had actually been making demands for payment for monies owed to Ratko Josifovski. The plaintiffs submitted that if the defendant had been making demands to the first plaintiff, he would have formed his own concerns as to the trustworthiness of the first plaintiff 339 and not provided him the $76,850 payment.
In oral submissions, counsel for the plaintiffs again urged the court not to accept the defendant’s version that the $25,000 was received against monies owed to Ratko 340 Josifovski. The plaintiffs submitted that there was a disconnect between the evidence given by the defendant and Ratko Josifovski, in that the defendant said $31,000 was owed for the painting work undertaken at the first plaintiff’s Forrest home. Whereas Ratko Josifovski gave evidence at the hearing that the monies were owed for a number 341 of different jobs in different suburbs.
Counsel for the plaintiffs emphasised the lack of quotes, invoices and formal written demands for payment from the first plaintiff. Reference was also made to the alleged outstanding balance of $6,000 which was also not the subject of any written demands, nor was there any evidence from the defendant or Ratko Josifovski requesting that the 342 remaining $6,000 be obtained.
It was submitted that if the court accepted the defendant’s version of events as to the monies owed to his father for over a year, the defendant would have been concerned 343 and troubled as to engage the first plaintiff to act as builder.
The plaintiffs also noted that the first plaintiff had not been cross examined as to the purpose of the $25,000 payment. It had not been put to the first plaintiff that the cheque 344 was instead for monies owed to Ratko Josifovski.
The plaintiffs ultimately submitted that the court should prefer the inference proffered by the plaintiffs as to the purpose of the $25,000 in that it was to support the first plaintiff’s contribution to the partnership. The alternative inference advanced by the
336 Plaintiffs’ submissions in chief 4 December 2019 Footnote 18. 337 Plaintiffs’ submissions in chief 4 December 2019 [41]. 338 Plaintiffs’ submissions in chief 4 December 2019 [41]-[42]. 339 Plaintiffs’ submissions in chief 4 December 2019 [42]. 340 T386.29-35. 341 T386.43-48. 342 T387.24-37. 343 T387.39-46. 344 Plaintiffs’ submissions in chief 4 December 2019 [44]. defendant that the $25,000 cheque was for monies owing to Ratko Josifovski ought to be rejected.
Legal effect of the $25,000 cheque
In the amended statement of claim, the plaintiffs pleaded that the $25,000 supported the inference that from 16 August 2013 upon settlement onwards, the property was 345 property of the partnership pursuant to s 24 of the Partnership Act.
In oral submissions, counsel for the plaintiffs submitted that the first plaintiff’s use of the word ‘loan’ on Exhibit 4 was a non-expert use of the term, in that the first plaintiff used the word ‘loan’ to mean monies he was to receive after the division of profits as a partner rather than as a debt owed. The plaintiffs denied that the $25,000 was a loan and highlighted that the defendant’s case was not that the money had in fact been 346 loaned to him by the first plaintiff.
The plaintiffs sought a declaration that the defendant held the property and any proceeds from the sale thereof on trust for the partnership. Alternatively, specifically in relation to the $25,000, the plaintiffs sought a declaration that the defendant held the property and any proceeds from the sale thereof on resulting trust for the first plaintiff, the second plaintiff and the defendant as a result of the first plaintiff’s contribution to the purchase price for the property and the second plaintiff’s contribution to the 347 construction costs for the development of the property.
Consideration
Purpose of the $25,000 cheque
I do not accept that the $25,000 was paid by the first plaintiff to the defendant to go towards the deposit to acquire the property. The defendant had already exchanged sale contracts to acquire the property on 2 July 2013 for the agreed price of $277,500. The defendant had deposited 10 per cent of the purchase price, being an amount of 348 $27,750 into the vendor solicitors trust account on 1 July 2013. This money was paid from a Commonwealth Bank account in the name of the defendant.
The defendant paid the $27,750 before the first plaintiff contended he made the $25,000 available. I do not accept the plaintiffs’ assertion that the defendant required the funds.
The defendant highlighted that Slavica was not a party to the proceedings and that beyond the cheque itself naming Slavica as the drawer and the Bendigo Bank transaction history for the second plaintiff, there was no evidence as to the relationship between Slavica and the plaintiffs. No reference had been made to Slavica acting as 349 an agent for either or both of the plaintiffs.
The defendant admitted to receiving the $25,000 cheque on 8 July 2013 from the first plaintiff drawn by Slavica. The defendant submitted that the payment was for monies
345 Plaintiffs’ amended statement of claim 22 October 2019 [22]. 346 T386.37-41. 347 Plaintiffs’ amended statement of claim 22 October 2019 [54A], [54C]. 348 Tab 30 Exhibit 1. 349 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [100]. owed to Ratko Josifovski for painting works undertaken at the first plaintiff’s home in 350 Forrest and at other locations in Canberra.
As the defendant was managing Ratko Josifovski’s financial affairs at the relevant time, the $25,000 was deposited into a bank account in the name of the defendant and transferred to a second bank account of the defendant used for safe keeping of funds for his father. The money was then disbursed when needed to look after Ratko 351 Josifovski.
The defendant referred to the evidence of Ratko Josifovski that he had instructed the defendant to accept the $25,000 cheque and also the evidence of Ratko Josifovski that he was owed $25,000.
I am not satisfied on the balance of probabilities that the first plaintiff gave the defendant $25,000 as the first plaintiff’s contribution to the purchase price of the property.
Legal effect of the $25,000 cheque
In the defendant’s case summary, the defendant submitted that the court would not be satisfied that the $25,000 had the effect that the defendant held the property on resulting trust for the benefit of the first plaintiff, the second plaintiff and the 352 defendant.
The defendant noted that the payment of the $25,000 cheque was made on 8 July 2013, which was made after the exchange date on 2 July 2013. The $25,000 cheque was also preceded by the defendant having made the payment of the 10 per cent 353 deposit, being $27,500 paid on or around 1 July 2013.
The defendant highlighted that the initial presumption arising from the registration of ownership on the title to property is that the registered owner has ownership in the property specified on the title and that there is no beneficial interest in favour of someone else: Calverley v Green at 267, Black Uhlans Inc v NSW Crime Commission [2002] NSWSC 1060 at [128].
That presumption is replaced by a further presumption that the beneficial ownership of the property is held in the proportions in which they contributed purchase money, that is a presumption of a resulting trust: Calverley v Green at 247. Determination of the extent of beneficial interests of respective parties occurs at the time the acquisition is purchased, that is the point in time when the resulting trust will be created: Calverley v Green at 252.
The defendant noted that it was uncontroversial that the defendant procured a loan from Westpac Bank, that the defendant paid the 10 per cent deposit and the balance of the purchase.
The defendant referred to s 201(1)(a) of the Civil Law (Property) Act which establishes that an interest in land cannot be created or disposed of by a person except by writing signed by the person or by the person’s agent properly authorised in writing. s 201(4)(a)
350 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [104]. 351 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [104]. 352 Defendant’s case summary 18 October 2019 [52]. 353 Defendant’s case summary 18 October 2019 [49]. of the Civil Law (Property) Act confirms that s 201 does not affect the creation or operation of a resulting trust.
The defendant further referred to s 204(1) of the Civil Law (Property) Act which provides that a proceeding does not lie against a person on a contract for the sale or other disposition of land unless the agreement on which the proceeding is brought, or a memorandum or note of the agreement, is in writing signed by the person or by the person’s agent properly authorised in writing.
The defendant submitted that the court would not be satisfied that the $25,000 cheque had the effect of creating a resulting trust that would satisfy the exception in s 201(1)(a) 354 of the Civil Law (Property) Act.
It was submitted that if the court was to conclude that the defendant was liable to the plaintiffs for the $25,000, Slavica would still be able to bring a separate claim for the $25,000 if it was minded to. Such a result would be possible as Slavica was not a party to the current proceedings and would not be estopped or barred from making the claim pursuant to the doctrine in Port of Melbourne Authority v Anshun [1981] HCA 45; 147 CLR 589. This could have the ultimate result of the defendant being ordered to pay the 355 $25,000 twice.
In oral submissions, counsel for the defendant submitted that as the cheque was drawn by Slavica it would not be open for the court to conclude that the $25,000 was money paid by the plaintiffs. As a result, even if the court rejected the defendant and Ratko Josifovski’s version of the $25,000, the plaintiffs were not the proper plaintiffs for the 356 $25,000.
The defendant asserted that even if the court was to conclude that the plaintiffs had made the payment on the Slavica cheque, the payment of $25,000 would not create any rights in the land for the plaintiffs as the property was purchased on 2 July 2013 with the deposit paid by the defendant. The balance was paid with the funds borrowed 357 from Westpac at settlement on 26 July 2013.
As Calverley v Green at 252 establishes that the extent of any beneficial interest must be determined at the time the property was purchased, the plaintiffs would have no beneficial interest in the land as a result of the $25,000 in circumstances where Slavica 358 made the funds available after the deposit had already been paid by the defendant.
The defendant referred to the use of the word ‘loan’ in Exhibit 4 to further assert that a mere unsecured loan would not have created a right in the land. Further reference was made to Calverley v Green at 246 where Gibbs CJ affirmed that for the resulting trust presumption to apply to contributed funds, the money must have been provided by the 359 purchaser in the capacity as such, not for a loan.
Conclusion
354 Defendant’s case summary 18 October 2019 [51]. 355 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [100]. 356 T411.33-48. 357 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [101]. 358 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [101]. 359 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [108]-[109]. deposit of the property. As I have found that the $25,000 did not go towards the purchase price of the property, the cheque did not have the effect of creating a resulting trust.
Does the evidence support a conclusion that the defendant sought, and/or directed the alleged Additional Works?
Did the plaintiffs pay for the alleged Additional Works? Were they performed? Were they additional to the requirements in the HIA Contract?
Evidence
John Cobanov
(a) Changes to the framework, namely changing door heights, changing cavity sliding opening in master bedroom walls, and changing walls for ducting;
(b) Changes to the plasterboard;
(c) Changes to the front and back doors;
(d) Changes to the flooring;
(e) The addition of a barbeque and alfresco dining area;
(f) Changes to the stairs;
(g) The addition of a retaining wall, including construction of the wall and its footings;
(h) The decision to render the entire exterior of the dwelling to a smooth finish;
(i) Extensive additional joinery to the kitchen and other areas;
(j) Additional extra external cladding;
(k) The addition of glass splash back, custom mirrors and fire rating to the kitchen;
(l) Changing the walk-in pantry to a butler’s pantry with sink and associated works;
(m) Change to full height tiling and associated works;
(n) The addition of a back patio including decking made from specialty timber, custom stairs and associated works;
(o) Construction of a cellar including associated design and engineering; and (p) Supply of black concrete for driveways and footpaths.
The first plaintiff alleged that additional expenses were incurred as a result of carrying out the Additional Works, including debts on established accounts that the first plaintiff and second plaintiff had with trade suppliers. The second plaintiff did not seek a variation of the HIA Contract, put in a progress claim nor otherwise seek payment for 361 any of the Additional Works.
In November 2013, the first plaintiff asserted that the defendant had the architect Robert Jukic amend the plans for the dwelling in order to accommodate variations that 362 the defendant had sought.
The first plaintiff stated that he raised his concerns with the defendant regarding the increased costs the defendant was incurring with variations and choices of specifications, including the significant debts with trade suppliers. The defendant responded with words to the effect that the increased costs would be recovered upon the sale of the property.
In or around July 2014, the first plaintiff contacted Robert Jukic and requested an updated site plan for the property that included all of the extra or additional areas that 363 had not been calculated in the total square metres on the original plans.
On 7 July 2014, the first plaintiff received an updated site plan from Robert Jukic. In addition to the original plan of 269.8 square metres, the updated site plan listed an additional 60.97 square metres of floor area for:
Alfresco area 26.47 square metres;
Portico area 4.3 square metres;
External stairs and landing to laundry 5 square metres;
Sub floor area 12 square metres; 364 5. External timber deck 12.2 square metres.
On 5 December 2014, there was a dispute between the first plaintiff and the defendant as to unpaid invoices and accounts. The was a further heated phone call that took place between the first plaintiff and the defendant on 24 December 2014 about the sewerage 365 system at the property.
After the disagreement on 24 December 2014, the first plaintiff asked Elle Cobanov to gather all the receipts, supplier invoices and total paperwork that she could find in relation to the development of the property. Elle Cobanov then complied them all into 366 a hardcopy, ring binder style folder.
In January 2015, the first plaintiff and the defendant had agreed to meet at the office address of the second plaintiff to go through a reconciliation of all of the expenses and
360 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [48]. 361 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [49]. 362 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [37]. 363 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [52]. 364 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [54]. 365 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [61], [64]. 366 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [65]. contributions. The parties ended up having a discussion in the carpark upon the 367 defendant’s arrival.
The conversation then escalated into a heated argument as the first plaintiff and defendant argued over whose fault the high expenses were. Elle Cobanov came out to 368 say to the first plaintiff and the defendant and asked them to stop screaming.
The first plaintiff gave the defendant the ring binder style folder and the following conversation took place:
First Plaintiff: Here, take this away with you and you can study it.
Defendant: I don’t have any money. I’ll give you $10,000 out of my credit card and call it quits. 369 First Plaintiff: It’s not $10,000. It’s more like $150,000.
The first plaintiff then requested the ring binder style folder back but the defendant retained it, walked to his car and drove away from the office address of the second 370 plaintiff.
Approximately a week later, the defendant called the first plaintiff and said words to the effect of “there’s $80,000 worth of damage to the property. I’m not going to pay you 371 anything”.
The first plaintiff responded saying words to the effect that “all workmanship is guaranteed and if their accounts are paid the tradesmen will quite happily return to attend to any defects or outstanding works. Some of them I have known for 25 years 372 and I know they will come to repair willingly if they were paid”.
At the hearing during examination in chief, the first plaintiff was taken to a document titled ‘1/104 – Expenditure Lists’. The first plaintiff gave evidence that the document was a report generated by Elle Cobanov that she had put together after going through the accounts of the first and second plaintiff against the project of the development of 373 the property. The first plaintiff confirmed that he had checked the document after Elle 374 Cobanov had prepared it.
Counsel for the plaintiffs sought to tender the document titled ‘1/104 – Expenditure Lists’ through the first plaintiff. This course was objected to by counsel for the defendant on the basis that the first plaintiff was not the author of the document, particularly in circumstances where it was a typed document and the first plaintiff had given evidence 375 he was not familiar with computers or word processing programs. The document was instead marked for identification, with an indication that it would be tendered through Elle Cobanov.
367 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [66]. 368 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [67]-[68]. 369 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [69]-[72]. 370 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [73]. 371 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [75]. 372 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [76]. 373 T70.18-23. 374 T70.22-23. 375 T70.41-46.
The first plaintiff was also taken to a collection of documents that read in typed font‘ Extras for Section 1 Block 104 Casey’. Underneath the title, it read’ ‘Client: Kiki Josifovski’. The word client had been struck out with a pen and the word ‘Partner’ was handwritten underneath. It contained an index of invoices as well as the invoices themselves. Included in the collection of invoices were invoices payable to the second plaintiff bearing the logo of the second plaintiff.
The first plaintiff stated the invoices were invoices for the defendant’s job and that Elle 376 Cobanov had prepared the summary. In relation to the invoices payable to the second plaintiff, the first plaintiff gave evidence that Elle Cobanov knew what information to populate the invoices with based on the instructions given to her by the 377 first plaintiff. The documents were marked for identification, included in a bundle with the ‘1/104 – Expenditure Lists’. The bundle was paginated and was 73 pages long.
Although the tender of both ‘1/104 – Expenditure Lists’ and ‘Extras for Section 1 Block 104 Casey’ were to be deferred to the evidence of Elle Cobanov, counsel for the defendant wished for his objections to the material to be dealt with prior to the cross 378 examination of the first plaintiff.
In making the objection, counsel for the defendant understood ‘1/104 – Expenditure Lists’ and ‘Extras for Section 1 Block 104 Casey’ to be advanced as the Additional 379 Works. Counsel for the defendant noted that the first 16 pages of the bundle were summaries, and pages 17 to 73 were individual invoices. The document ‘1/104 – Expenditure Lists’ had a total of 184 entries for monetary amounts owed to suppliers, 380 some with invoice reference numbers.
Counsel for the defendant asserted that ‘1/104 – Expenditure Lists’ was an inaccurate summary of the resulting invoices by virtue of there being 184 entries on the summary 381 yet only 57 invoices succeeding it. Further, the invoices included in the bundle were ambiguous in that there was nothing on the face of discrete invoices that recorded it 382 was for an Additional Work. It was also unclear from the invoices whether there had been a record of payment made as there had been no authentication of business 383 records by the relevant third parties.
Counsel for the defendant maintained the objection on the basis of s 135 of the Evidence Act as the bundle presented as a burden to the defendant as an unquantified 384 claim for money.
In responding to the objection raised referred to the bundle, counsel for the plaintiffs referred to the evidence of the first plaintiff that Elle Cobanov collated all of the original documents chronologically along with proof of payment and that material in the ring binder folder was given to the defendant with no copy made. Counsel for the plaintiffs
376 T72.10-12. 377 T72.17-18. 378 T84.12-13. 379 T85.35-39. 380 T87.14-16. 381 T88.10. 382 T89.21-26. 383 T92.28-36. 384 T91.17-20. submitted that the court could receive the bundle subject to weight and then it would 385 be up to the plaintiffs to make good the claim for Additional Works.
I determined that the bundle could later be tendered through Elle Cobanov and the court would then receive it, subject to weight. If counsel for the plaintiffs failed to the link the material contained in the bundle to the HIA Contract to demonstrate the works 386 were in fact additional, the material itself would have zero weight.
Further evidence in chief was then taken of the first plaintiff. When referred to the document titled ‘Extras for Section 1 Block 104 Casey’, the first plaintiff gave evidence that the index included in the document contained dates with invoice numbers and 387 amounts paid. The invoices were from subcontractors for services and materials for 388 the development of the property, which had been sent to the second plaintiff.
The first plaintiff gave evidence that he paid for all of the amounts set out in the invoices and that there would be a paper trail from cheque books and bank statements. The first 389 plaintiff confirmed that he was not repaid for any of the amounts.
When asked what was meant by the word ‘extra’ in the title ‘Extras for Section 1 Block 104 Casey’, the first plaintiff said extra referred to works that were outside the scope of the build where changes were made, work was performed but no payment was 390 received.
The first plaintiff gave an example of a work that was outside of the scope of the build as being the change to the front door and back door. The first plaintiff stated that the doors were already in place and then the defendant wanted them changed from being 391 a timber door to a glass door with an aluminium frame.
Reference was made to an invoice for changing of doors included in the bundle that was payable to the second plaintiff. The first plaintiff confirmed that the invoice was dated 13 July 2015 because the original invoice had been given to the defendant and a new invoice had to be generated. The first plaintiff gave evidence that the invoice 392 date did not reflect the date on which the works were performed.
The invoice overleaf was from the company that the doors were obtained from, Trend Windows. The first plaintiff gave evidence that he received the invoice from Trend 393 Windows, that he paid the invoice and that he was not reimbursed for doing so.
During cross examination, the first plaintiff was taken to the version of the HIA Contract he said he entered into on behalf of the second plaintiff with the defendant. The first plaintiff was referred to clause 21, which sets out the proceeding for variations to the building works.
Clause 21 provides:
385 T98.1-3. 386 T91.22-24 & T100.43. 387 T102.30-32. 388 T102.37-39. 389 T104.9-11, 13-14. 390 T104.16-18. 391 T104.23-26. 392 T105.16. 393 T105.20-30. In each of [the] cases the price for the variation, including an amount for the builder’s margin, is added to the contract price. Payment for the variation must be made at the next progress stage.
Variation by Agreement
The owner and the builder may agree in writing to vary the building works.
Variation requested by the owner
If the owner asks for a variation, the builder must reply in writing to the owner within 5 days of the request, or as soon as is reasonably practicable.
The builder has the right to refuse a variation.
The builder and the owner must both agree in writing to the variation, its details and how much it will cost or save prior to commencement of the variation work.
Payment for variations to the building works
The price or cost of the variation, as the case may be, is added to or deducted from the contract price. Payment for the variation must be made at the next progress payment stage (unless a different time is stated in the variation agreement.
The first plaintiff agreed with the contents of clause 21 but claimed the process for variations was not followed as the first plaintiff and the defendant were in a 394 partnership. The first plaintiff admitted that he never confirmed a variation in writing, 395 nor did he seek an increase in contract price.
The first plaintiff was referred to Exhibit 5, the document titled ‘1/104 – Expenditure Lists’. On the first page was a reference for a cement supplier, with an invoice reference and an amount of $70.24. When asked whether it was in fact the defendant who had paid this invoice, the first plaintiff responded that he was not sure and that if the defendant had paid it, it would have been removed from the list. The first plaintiff said the purpose of giving the defendant the ring binder folder was for the defendant to go 396 through the material and make his own judgments.
Reference was also made to an invoice of the second plaintiff contained within Exhibit 7 that was for ‘electrical extras for 1/104’ with a total balance of $6,081.20, behind the invoice of the second plaintiff were three invoices for Scott Dickason Electrics which were what was then incorporated into the second plaintiff’s invoice. Counsel for the defendant put it to the first plaintiff that it was actually the defendant who paid the invoice to Scott Dickason and the first plaintiff conceded this. The first plaintiff further conceded it was inappropriate for this invoice to be included within the Additional Works 397 bundle.
The first plaintiff was then taken to another invoice of the second plaintiff within Exhibit 7 where the first line read ‘supply tiles’ for an amount of $5,521.38, the invoice also included a line that said an amount of $3,272.73 had been deducted as a refund. Behind this invoice was an invoice from Artmar Natural Stone Warehouse for
394 T132.40-43. 395 T133.3-7. 396 T168.38-42. 397 T171.31-46. $5,521.38. It was put to the first plaintiff that he had in fact received a refund for 398 $5,521.38, but this was denied.
The first plaintiff was referred to an invoice of the second plaintiff for ‘plumbing for 1/104 Casey: plumbing for alfresco and butlers (sic) kitchen sinks’ for $3,000. Counsel for the defendant claimed that the $3,000 was for correcting faulty workmanship. The first 399 plaintiff denied this and stated that it was due to the plans being updated.
Reference was also made to an invoice of the second plaintiff for a ‘retaining wall for 1/104 Casey’ for $6,670. Although it was put to the first plaintiff that the defendant had 400 paid for $5,300 for the retaining wall to be built, the first plaintiff denied this.
Counsel for the defendant also referred the first plaintiff to an invoice of the second plaintiff for ‘bookeeping (sic) for 1/104 Casey’ for $2,000. The first plaintiff conceded that he had not approached the defendant and asked him for approval to incur bookkeeping costs. However, the $2,000 was on account of the material having to be 401 reconstructed after the ring binder folder went missing.
An invoice of the second plaintiff for ‘base work to below floor level of 1/104 Casey’ was also referred to, it included a line reading ‘Piers by drilling and pouring of concrete’ for $3,000. When asked how this was an additional work, the first plaintiff stated that it was additional because the height of the base had been exceeded and piers had to be 402 inserted.
The first plaintiff was referred to two further invoices of the second plaintiff. When queried why the corresponding invoices from suppliers were addressed to G & M Cobanov and who that entity was, the first plaintiff gave evidence that it was his father’s account that he had taken over. The first plaintiff claimed that it did not matter that the invoices were addressed to G & M Cobanov in circumstances where he had paid the 403 accounts.
In re-examination, the first plaintiff gave evidence that he did not confirm any variations in writing pursuant to clause 21 of the HIA Contract because he and the defendant were 404 operating as partners.
Elle Cobanov
In her witness statement, Elle Cobanov states that in January 2015 the first plaintiff asked her to put together all of the supplier and subcontractor invoices and expenses 405 incurred on the project, with all of the receipts for payments made.
Elle Cobanov organised the material chronologically and compiled it into a ring binder 406 style folder and provided it to the first plaintiff. No copy of the folder was made. Elle
398 T172.21-25. 399 T173.4-11. 400 T173.15-24. 401 T173.30-37. 402 T175.7-12. 403 T175.35-37 & T176.6-7. 404 T180.12-14. 405 Elle Cobanov statement Tab 13 Exhibit 1 [20]. 406 Elle Cobanov statement Tab 13 Exhibit 1 [20]. Cobanov produced invoices from the second plaintiff as she usually would by grouping 407 types of expenses together and adding a margin of 15 per cent.
Approximately a couple of days after providing the ring style binder file to the first plaintiff, Elle Cobanov recalled being in the office of the second plaintiff and overhearing yelling from the carpark. She recognised the voices to be that of the first plaintiff and 408 the defendant.
Elle Cobanov walked outside and saw the first plaintiff and the defendant having an argument. She asked them to keep it down and to work out the dispute without 409 screaming. Elle Cobanov then proceeded to go back inside of the office.
During examination in chief, Elle Cobanov was shown the bundle of material that had been marked for identification during the evidence of the first plaintiff. Elle Cobanov was first shown the document titled ‘1/104 Casey – Expenditure Lists’, which became Exhibit 5. Elle Cobanov was also shown a document included in the bundle that was titled ‘Expenses Summary’, which became Exhibit 6.
In relation to Exhibit 5 and Exhibit 6, Elle Cobanov gave evidence that:
The document ‘1/104 Casey – Expenditure Lists’ was a list of company payments.
The document ‘Expenses Summary’ was a summary.
She had prepared both ‘1/104 Casey – Expenditure Lists’ and ‘Expenses Summary’.
The first plaintiff had asked her to prepare both documents.
The first plaintiff had provided her with the information to populate 410 both documents.
Elle Cobanov was also shown the document in the bundle that was titled ‘Extras for Section 1 Block 104 Casey’, which became Exhibit 7. In relation to Exhibit 7, Elle Cobanov gave evidence that:
She had prepared the index of invoices contained within that bundle. 411 2. The invoices had come from the software program MYOB.
During cross examination, Elle Cobanov was again referred to the document ‘1/104 Casey – Expenditure Lists’, Exhibit 5. Elle Cobanov stated that she had looked at invoices in order to prepare the tables. She further claimed that the invoices she had 412 looked at to prepare the tables were the same invoices that formed part of Exhibit 7.
When referred to the documents ‘Expenses Summary’, Exhibit 6, Elle Cobanov was asked whether a table with a header above it ‘Breakdown of Expenses from expenditure list supplied to Kiki’ had been populated using the invoices in Exhibit 7 or
407 Elle Cobanov statement Tab 13 Exhibit 1 [21]. 408 Elle Cobanov statement Tab 13 Exhibit 1 [22]. 409 Elle Cobanov statement Tab 13 Exhibit 1 [69]. 410 T146.28-34 & T147.29-40. 411 T148.28-34. 412 T150.46-47 & T151.1-9. further material. Elle Cobanov stated that it was generated from invoices in Exhibit 7 413 and from other material, from other invoices and cheques.
Elle Cobanov then gave evidence that the tables had been populated after the folder of original material had been provided to the defendant, never to be seen again. When asked how the tables were prepared in circumstances where the original invoices were missing, Elle Cobanov responded that she had contacted all of the suppliers and gone 414 through all of the cheques.
Elle Cobanov claimed that she had been able to regather the information and reconstruct it afresh. Elle Cobanov did however concede that she was unable to remember whether which invoices she had and which she did not when constructing 415 the summary tables in Exhibits 5, 6 and 7.
Kiki Josifovski
Around November 2013, upon viewing the work that had been completed, the defendant discovered that the foundations had not been constructed in accordance with the plans. The sub-floor cellar, which was to be underneath the bedrooms, had not been constructed, nor access to that area. The sub-floor cellar could not be installed under the bedrooms at that stage. The defendant also observed that an error had been 416 made in relation to the location of the water point for the refrigerator in the kitchen.
The defendant denied that he instructed Robert Jukic to accommodate elective variations to the plans. The defendant claimed that the variations were required as ‘work-arounds’ because of errors in construction. The amended plans also provided for more detail of the existing design to assist the trade subcontractors to interpret the 417 plans as the development went on.
The defendant raised the issues with the construction with the first plaintiff who requested the defendant liaise with Robert Jukic in order to discuss the possibility of an alternative area for the sub-floor cellar and for the water point for the refrigerator to 418 be moved.
The defendant called Robert Jukic and had a conversation to the following effect:
Defendant: Hi Robert, some errors have been made in the build. They’ve missed the sub-floor access, a water point in the kitchen for the fridge and a host of other things. John’s asked whether the access can be moved to under alfresco and water point moved to the butler’s pantry -can you mock up plans? I also need more details in the plans labelling materials and dimensions etc., as John is often away and the subcontractors often ask me for directions and I don’t know what to tell them.
413 T151.32-44. 414 T152.43-44 & T152.45-47. 415 T153.17-19. 416 The first witness statement of the defendant Tab 8 Exhibit 1 [73]. 417 The first witness statement of the defendant Tab 8 Exhibit 1 [74]. 418 The first witness statement of the defendant Tab 8 Exhibit 1 [75]-[77]. Robert Jukic: No problem I’ll get it done and let you and John know.
The amended plans were dated 22 November 2013 and exhibited to the first witness 420 statement of the defendant. The amended plans reflect the amended sub-floor entry 421 and the revised position of the water point for the refrigerator.
The defendant stated that he did not instruct any variations to the plans which necessitated amendment. The plans were only required to be amended in light of the 422 second plaintiff’s failure to construct in accordance with the original approved plans.
The defendant denied adding any additional areas other than a deck that was never in fact undertaken by the second plaintiff. The defendant maintained that the gross floor area of the build remained the same in the amended plans 22 November 2013, being 423 at 269.8 square metres.
The defendant denied having an argument with the first plaintiff in the carpark in early 424 2015 and further denied that Elle Cobanov told them to “keep it down”.
In response to the first plaintiff’s claim that the defendant sought and/ or directed a number of changes to the original plans, the defendant addressed each alleged 425 variation in Schedule C of the defendant’s first witness statement.
(a) Changes to the framework, namely changing door heights, changing cavity sliding opening in master bedroom walls, and changing walls for ducting.
(b) Changes to the plasterboard;
(c) Changes to the front and back doors;
The defendant denied that this was a variation, noting that the front door and internal doors were the subject of a $1,500 allowance in the inclusions list. The defendant noted that the inclusions list t did not indicate what kind of doors were to be used.
The defendant further noted that the second plaintiff incurred $1,200 against the allowance and no deduction was made from the contract sum.
419 The first witness statement of the defendant Tab 8 Exhibit 1 [78]. 420 Tab 42 Exhibit 1. 421 The first witness statement of the defendant Tab 8 Exhibit 1 [80]. 422 The first witness statement of the defendant Tab 8 Exhibit 1 [81]. 423 The first witness statement of the defendant Tab 8 Exhibit 1 [116]. 424 The second witness statement of the defendant Tab 15 Exhibit 1 [18]. 425 Tab 72 Exhibit 1.
(d) Changes to the flooring;
(e) The addition of a barbeque and alfresco dining area;
The defendant denied directing variations in relation to a barbeque and or alfresco dining area. The defendant noted that a ‘gas point’ and ‘covered dining area’ were shown in the original plans dated 4 June 2013.
The defendant denied that the works undertaken in the alfresco dining area differed from the scope of works in the HIA Contract, also noting that the second plaintiff never installed a gas point nor a barbeque.
(f) Changes to the stairs;
The defendant denied that changes to the stairs were a variation. The defendant noted that the stairs were the subject of a $10,000 allowance in the inclusions list, which did not indicate what kind of stairs were to be installed.
The defendant further claimed that the second plaintiff only incurred $1,853.50 in relation to the stairs and that no deduction was made to the Contract Sum.
(g) The addition of a retaining wall, including construction of the wall and its footings;
The defendant denied that the addition of the retaining wall was a variation. The defendant claimed that the retaining wall was the subject of a $6,500 allowance in the inclusions list, again noting that the specific type of retaining wall to be installed was not indicated in the inclusions list.
The defendant noted that the second plaintiff incurred only $3,700 for the retaining wall and again, no deduction was made to the Contract Sum. The defendant also noted that he had incurred $3,700 in costs relating to the retaining walls and that he paid for it directly due to the failure of the second plaintiff to pay for the retaining wall works.
(h) The decision to render the entire exterior of the dwelling to a smooth finish;
The defendant denied that this was a variation. The exterior rendering was the subject of an $18,500 allowance in the inclusions list. Again, the inclusions list did not indicate the type of rendering to be used.
The defendant noted that only $5,900 was spent on rendering and no deduction was made by the second plaintiff to the Contract Sum. The defendant claimed he incurred $6,900 in costs relating to rendering works on account of the second plaintiff refusing to pay the renderer.
(i) Extensive additional joinery to the kitchen and other areas;
The defendant noted that joinery was the subject of various allowances in the inclusions list comprising: $40,000 for the kitchen (including appliances), $3,000 for the bathroom vanities, $3,000 for wardrobes and $2,000 for the laundry. The defendant noted that the HIA Contract did not specify what joinery works were to be installed.
The defendant noted that the total amount incurred by the second plaintiff for the joinery items and including appliances was $45,903.60, which may have exceeded what was allowed for in the inclusions list. The defendant however claimed that he had paid for the appliance, incurring $3,986 and in which no deduction was made to the Contract Sum.
(j) Additional extra external cladding;
(k) The addition of glass splash back, custom mirrors and fire rating to the kitchen;
(l) Changing the walk-in pantry to a butler’s pantry with sink and associated works;
The defendant denied that he directed any variation to the change in relation to the walk-in pantry which is included in the original plans dated 4 June 2013. The defendant also noted that any variation was an agreed work around due to the second plaintiff’s failure to construct the works in accordance with the HIA Contract.
The defendant further noted that the works undertaken in relation to the walk-in pantry only differed from the scope of works in the HIA Contract as to the inclusion of the water point in the plans dated 22 November 2013. The inclusion of the water point in the walk-in pantry was a further around agreed between the defendant and the first plaintiff as the second plaintiff had failed to install a water point for the fridge in the kitchen, where it was originally meant to be pursuant to the original plans dated 4 June 2013.
(m) Change to full height tiling and associated works;
(n) The addition of a back patio including decking made from specialty timber, custom, stairs, and associated works;
(o) Construction of a cellar including associated design and engineering;
The defendant denied that he instructed a variation in relation to the sub-floor cellar, other than the agreed work around due to the second plaintiff’s failure to construct the works in accordance with the HIA Contract.
The defendant contended that the works undertaken in relation to the sub-floor cellar did not differ from the scope of works in the HIA Contract, save for the actual location of the sub-floor cellar.
The defendant referred to the original plans dated 4 June 2013 which showed an entry to the cellar under bedroom 4. In initial conversations with the first plaintiff prior to the execution of the HIA Contract, the parties had agreed that the sub-floor cellar would be a walled and floored area.
The second plaintiff failed to install access and the sub-floor cellar underneath bedroom 4. Subsequently, as a ‘work around’ agreed between the defendant and the first plaintiff, the second plaintiff moved the sub-floor access to underneath alfresco area which is depicted in the updated plans dated 22 November 2013.
The defendant contended that the revised sub-floor cellar was a significantly more cramped space than was contemplated in the original plans dated 4 June 2013. The second plaintiff did not construct the sub-floor cellar itself, instead only constructing access to the area. Further, the sub-floor area was defective as it lacked sufficient ventilation
(p) Supply of black concrete for driveways and footpaths.
The defendant denied that he instructed any variation in relation to the colour of the concrete for driveways or footpaths. The defendant claimed that the second plaintiff never provided a driveway as depicted in the original plans dated 4 June 2013. Instead, the second plaintiff installed a thin strip of concrete and it was not black in colour. The second plaintiff also failed to install the footpaths as contemplated in the original plans dated 4 June 2013.
The defendant claimed he incurred $2,663.23 in completing the driveway and that he paid for this amount directly. The defendant stated that he painted the driveway black himself.
In the first witness statement of the defendant, it was asserted that on 18 February 2015 the defendant made an agreement with the first plaintiff that he would pay the first plaintiff more money on the basis that the first plaintiff would then agree no more 426 monies were owing upon receipt of $4,227.15 in full satisfaction. The agreement referred to as the Construction Contract Settlement Agreement stated the following:
This agreement confirms that the client, Kiki Josifovski, has completely fulfilled his financial obligation in relation to the contract with the Builder, John Ivo Cobanov of ASHELL Homes Pty Ltd for the construction of a residential property at 48 Wighton Terrace Casey.
426 The first witness statement of the defendant Tab 8 Exhibit 1 [143]. John Ivo Cobanov also confirms that all work undertaken at the above address are free of any financial encumbrances/debts and hereby acknowledge that any debts associate to this work are solely the responsibility of John Ivo Cobanov (ASHELL Homes Pty Ltd).
The builder, John Cobanov, acknowledges that there is no outstanding payment due by Kiki Josifovski for the construction of 1/104 Casey ACT and hereby declares that the aforementioned contract has been financially fulfilled and settled.
The Construction Contract Settlement Agreement was originally exhibited to the first witness statement of the defendant. However, at the hearing counsel for the defendant did not read the line in the statement that said the Construction Contract Settlement 427 Agreement was exhibited and the document itself was removed from Exhibit 1. Proof of the $4,227.15 remained exhibited to the statement and part of Exhibit 1.
During cross examination, the defendant was taken to letters sent in the course of these proceedings from the plaintiffs’ solicitor to the defendant’s solicitor and vice versa. This included a letter from the defendant’s solicitor which enclosed a copy of the Construction Contract Settlement Agreement as part of an answer to the plaintiffs’ claim. This letter enclosing the Construction Contract Settlement Agreement became 428 Exhibit 10 in the proceedings.
The defendant gave evidence that the Construction Contract Settlement Agreement bore his signature. He stated that the first plaintiff had not signed the document in his 429 presence, nor had he seen the first plaintiff sign it.
The defendant was then shown an affidavit he had deposed on 23 May 2019 in response to a request for interrogatories. The affidavit became Exhibit 11 in the proceedings. In paragraph 2 of the affidavit, the defendant states that he drafted the Construction Contract Settlement Agreement.
In paragraph 5 of the affidavit, the defendant states that in relation to the Construction Contract Settlement Agreement, he recalled that both he and the first plaintiff were present at the execution. In paragraph 6 of the affidavit, the defendant stated that he recalled the first plaintiff executed the Construction Contract Settlement Agreement above where his name had been typed out.
The defendant denied that his evidence in paragraph 6 of the affidavit recalling the first plaintiff executing the Construction Contract Settlement Agreement was inconsistent with his evidence at the hearing that he had not seen the first plaintiff sign the document.
When asked how this was reconcilable with his evidence in paragraph 5 of the affidavit that they were both present upon execution, the defendant claimed it had been signed 430 above the first plaintiff’s name when it was presented back to the defendant.
The defendant gave evidence that on or around 18 February 2015, he provided the first plaintiff with the Construction Contract Settlement Agreement and the first plaintiff took 431 it away to check it. The defendant asserted that he then got the signed version back
427 T202.30. 428 T218.2-4. 429 T220.24-28. 430 T221.32. 431 T223.12-15. when they next met within days and upon seeing the first plaintiff had signed, the 432 defendant signed the document.
The defendant conceded that his first witness statement did not make mention of a second meeting between the first plaintiff and himself in relation to the Construction Contract Settlement Agreement. It was put to the defendant that the second meeting 433 never happened but the defendant denied this.
The defendant admitted that that there was no reference to $4,227.15 in the 434 Construction Contract Settlement Agreement itself. The defendant was referred to the part of his witness statement where he said $4,227.15 was paid pursuant to the Construction Contract Settlement Agreement and payment records of that amount.
When referred to the payment records of that amount, being a snapshot of the defendant's bank account, it was pointed out to the defendant that the amount for $4,227.15 had been paid to the second plaintiff on 17 February 2014. The defendant maintained that this was the amount paid pursuant to the Construction Contract 435 Settlement Agreement.
The defendant agreed that he had instructed his solicitors to include the Construction Contract Settlement Agreement in the defence and counterclaim. The defendant agreed that between 20 November 2017 and 30 September 2019, the defendant had relied on the Construction Contract Settlement Agreement as presenting an answer to the plaintiffs’ claim and confirmed that such reliance was abandoned on 30 September 436 2019.
It was put to the defendant that the Construction Contract Settlement Agreement was abandoned in response to the plaintiffs seeking to file an application to adduce expert 437 handwriting evidence about the veracity of the first plaintiff’s signature. The defendant denied this. When asked whether the Construction Contract Settlement Agreement had been abandoned because the expert evidence would have called into question his credibility, the defendant claimed that he did not know if that would be the 438 case.
Counsel for the plaintiffs sought for the defendant to compare the signature of the first plaintiff on the Construction Contract Settlement Agreement with the signature of the first plaintiff on the 1 July 2013 invoice for $76,850. Counsel for the defendant objected to the exercise of comparing the signatures as it fringed into the territory of expert 439 evidence to be given by a handwriting expert.
Prior to the hearing, the plaintiffs filed an application to seek leave to serve a late expert report of a handwriting expert that concluded the signature on the Construction Contract Settlement Agreement. Pursuant to r 1241(4)(a) of the Court Procedure Rules 2006 (ACT), the court must not give leave unless there are exceptional circumstances that justify the granting of leave. The application came before Elkaim J on 27
432 T223.35-39. 433 T224.7-8. 434 T224.37-38. 435 T225.21-23. 436 T228.21-36. 437 T2298.38-40. 438 T231.16-17. 439 T230-T232. September 2019 who determined that the plaintiffs’ failed to establish exceptional circumstances and the plaintiffs’ application was dismissed: Cobanov & Anor v Josifovski [2019] ACTSC 269 at [16]-[17].
I determined that the line of questioning did trespass into asking the defendant to express an expert opinion and that there was no forensic utility in the exercise of asking the defendant to overlay the signature on the Construction Contract Settlement 440 Agreement over the signature on the 1 July 2013 invoice.
The defendant then denied that the first plaintiff did not sign the Construction Contract Settlement Agreement and rejected that the first plaintiff had not seen the Construction Contract Settlement Agreement until the letter was sent by the defendant’s solicitor 441 attaching it on 28 November 2017.
The defendant agreed that he drafted the Construction Contract Settlement Agreement and that he had a copy of the 1 July 2013 invoice for $76,850. The defendant denied that he copied the first plaintiff’s signature from the 1 July 2013 invoice to the 442 Construction Contract Settlement Agreement.
The defendant was also directed to the version of the HIA Contract he says he entered 443 into with the second plaintiff, which was contained in Exhibit 1. The defendant was referred to Clause 20 of the HIA Contract which relevantly reads:
The owner or an authorised officer of the lending authority must not give directions to the builder’s employees, subcontractors or suppliers without the builder’s written consent.
The defendant claimed that he did have written consent to direct subcontractors and suppliers as referred by the series of emails between the parties and various 444 subcontractors and suppliers.
The defendant was referred to the email correspondence between Andrew Desmond and the parties. In particular, the defendant was directed to an email sent by Andrew 445 Desmond to the first plaintiff on 13 October 2014 that read:
Hi John,
Please find attached an invoice for the variations completed as per discussions with Kiki. These included installing speakers in the theatre room and alfresco area. Also install light and power in cellar.
Please call if you’d like to discuss further.
Thanks
Drew
440 T232-T233. 441 T234.7-10. 442 T234.18-19. 443 Tab 79 Exhibit 1. 444 T291.19-22. 445 Tab 77 Exhibit 1.
Robert Jukic
Robert Jukic prepared a witness statement dated 25 February 2019 that formed part of 447 Exhibit 1. Robert Jukic did not give evidence at the hearing.
Robert Jukic is the director of R Inventive Design Pty Ltd and is an architect. Robert Jukic recalled that in around mid-2013, he prepared plans dated 4 June 2013 for the 448 defendant for the construction of a dwelling on the Casey property.
In about November 2013, Robert Jukic was instructed to make changes to the original plans including:
(a) Adding subfloor access from underneath bedroom 4 to underneath the alfresco area; 449 (b) Including a water point in the butler’s pantry.
Robert Jukic prepared updated plans reflecting the above change and the updated 450 plans were dated 22 November 2013.
Robert Jukic could not recall whether it was the first plaintiff or the defendant who had instructed the changes to the original plans but recalled discussing the changes with 451 both of them.
Robert Jukic was instructed by either the first plaintiff or the defendant that the change to the subfloor access was required because it had been bricked over the original subfloor access point. The preference was to relocate the subfloor door, rather than 452 rip out the bricks.
Robert Jukic was also instructed by either the first plaintiff or the defendant that a water point had not been installed for the fridge in the kitchen, which he thought was the 453 reason why one was then included in the butler’s pantry.
Plaintiff Submissions
446 T315.21-31. 447 Tab 9 Exhibit 1. 448 Robert Jukic statement Tab 9 Exhibit 1 [3]; Tab 22 Exhibit 1. 449 Robert Jukic statement Tab 9 Exhibit 1 [4]; Tab 42 Exhibit 1. 450 Robert Jukic statement Tab 9 Exhibit 1 [8]. 451 Robert Jukic statement Tab 9 Exhibit 1 [5]. 452 Robert Jukic statement Tab 9 Exhibit 1 [6]. 453 Robert Jukic statement Tab 9 Exhibit 1 [8]. 454 Plaintiffs’ submissions in chief 4 December 2019 [7].
The plaintiffs emphasised that the defendant had accepted he drafted the Construction Contract Settlement Agreement but submitted that the defendant gave conflicting evidence as to who was present and when it was actually executed. The difference between the defendant’s answers to interrogatories in the affidavit that became Exhibit 11 and the evidence given under cross examination was stark. In the former, the defendant claimed he was present when it was executed by the first plaintiff and under cross examination the defendant had claimed there had been another meeting between the parties as to when the unsigned document was present to the first plaintiff which 455 had previously been unmentioned in the proceedings.
It was submitted that the defendant’s evidence that he paid $4,227.15 pursuant to the Construction Contract Settlement Agreement could not be accepted when evidence of that payment demonstrated it was made in February 2014. That is, a year prior to the 456 Construction Contract Settlement Agreement allegedly coming into existence.
Emphasis was placed on the defendant’s reliance on the Construction Contract Settlement Agreement from November 2017 until September 2019, upon which the defence was amended. The plaintiffs noted that the defendant denied this change was protect his credibility, yet the defendant did not offer any alternative explanation as to 457 why the reliance was abandoned right before the hearing. No plausible explanation was proffered as to why what would have otherwise been a complete defence to the 458 claim was abandoned inexplicably.
The plaintiffs submitted that the signature of the first plaintiff on the Construction Contract Settlement Agreement was identical to his signature on the 1 July 2013 invoice for $76,850, which the defendant had admitted was in his possession. The plaintiffs urged a conclusion that the Construction Contract Settlement Agreement was not a genuine document and that it was created by the defendant to attempt to defeat 459 the plaintiffs’ claim.
The plaintiffs submitted that the works detailed in the ‘Expenses Summary’ (Exhibit 6) were works that were required to be performed at the request of the defendant. It was claimed that Exhibit 6 provided a basis for the court to conclude that the defendant 460 requested the Additional Works.
In claiming that the court could be satisfied that the plaintiffs’ paid for the Additional Works and that they were additional to the HIA Contract requirements, the plaintiffs referred to the evidence given by the first plaintiff that he paid or caused to be paid each of the items set out in the summary table in Exhibit 5 and the invoices in Exhibit 7. Further reliance was placed on the corroborative evidence given by Elle Cobanov and submitted that the defendant only identified one instance when the evidence was mistaken. The plaintiffs submitted that the court could conclude the Additional Works 461 were performed and paid for.
455 Plaintiffs’ submissions in chief 4 December 2019 [69]. 456 Plaintiffs’ submissions in chief 4 December 2019 [70]. 457 Plaintiffs’ submissions in chief 4 December 2019 [71]. 458 Plaintiffs’ submissions in chief 4 December 2019 [73]. 459 Plaintiffs’ submissions in chief 4 December 2019 [20]. 460 Plaintiffs’ submissions in reply 16 March 2020 [27]. 461 Plaintiffs’ submissions in reply 16 March 2020 [30]. Consideration
In my view, there is insufficient evidence to support a conclusion that the alleged Additional Works were indeed additional. The plaintiffs’ case was not clear in this regard.
The defendant referred to the tendering of Exhibits 5, 6 and 7, effectively the Additional Works bundle, that the court had received over objection. The defendant referred to the ruling that the Additional Works Bundle was admissible but that if the plaintiffs failed to marry it up to the building contract to demonstrate how the works were additional, it 462 would have negligible or zero weight.
In submissions, the defendant reiterated the concerns voiced at the time of objection:
a. There are more entries in the summary contained in ‘1/104 – Expenditure Lists’ (Exhibit 5), than the number of invoices in Exhibit 7. The defendant noted that the summary in Exhibit 5 was proffered as a summary of the invoices in Exhibit 7. Therefore, there ought to have been as many invoices as there were entries.
b. The invoices that were included in Exhibit 7 did not demonstrate that they are works or additional to the works required in the HIA Contract. Invoices that were included were vague or even nondescript.
c. There was no evidence that either the first or the second plaintiffs actually paid any of the invoices. The invoices had not been produced under subpoena by the parties said to have issued the invoices nor was any evidence obtained from those third parties to confirm they were paid for those works. Further, no bank statements were utilised to confirm payments 463 for the items in the invoices.
The first plaintiff accepted that the inclusion of an invoice from Scott Dickason in the Additional Works bundle was inappropriate as it had been paid by the defendant. The defendant also drew upon the inappropriate nature of an invoice for bookkeeping being 464 included as there was no basis for the claim whatsoever as an additional work.
The defendant summarised the evidence of Elle Cobanov at the hearing as follows:
a. Elle Cobanov could not remember the extent of primary data she had relied on to create the summary in ‘1/104 – Expenditure Lists’ (Exhibit 5) and the ‘Expenses Summary’ (Exhibit 6);
b. Elle Cobanov prepared the tables after the invoices were lost after the ring binder folder was given to the defendant;
c. Elle Cobanov was not confident the tables reflected all the invoices she once had; and
d. Elle Cobanov could not tell the court which invoices identified in the tables had gone missing before she prepared the tables.
462 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [69]. 463 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [69]. 464 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [70]-[73].
The plaintiffs have failed to address the deficiencies in relation to the Additional Works bundle. No further evidence was led. In my view, the Additional Works bundle cannot be ascribed significant weight. The evidence is insufficient to establish that the alleged works were additional to those specified in the building contract.
In oral submissions, counsel for the defendant addressed the issue of the Construction Contract Settlement Agreement. Counsel for the defendant asserted that the cross-examination of the defendant merely explored but did not resolve that the reason the defendant had abandoned reliance on the Construction Contract Settlement Agreement was because it was in his best interests to do so in circumstances where 465 the document was not authentic.
Counsel for the defendant stated that the plaintiffs had invited the court to perform a quasi-expert role by comparing the signature of the first plaintiff on the Construction Contract Settlement Agreement with the signature on the 1 July 2013 invoice for 466 $76,850. It was submitted that the plaintiffs were attempting to use the Construction Contract Settlement Agreement for the court to conclude that there was a nefarious 467 reason that the defendant had abandoned reliance on it as part of his defence.
Counsel for the defendant then submitted that the Construction Contract Settlement Agreement was of no benefit to either of the parties other than the point advanced by the plaintiffs as to the defendant’s credit. It was submitted that the Construction Contract Settlement Agreement itself was a nonsensical statement and contained many defects that prevented the document from actually amounting to the agreement 468 it purported to be.
It was submitted that the reliance on the Construction Contract Settlement Agreement had been withdrawn after the plaintiffs had suggested that the parties ought to incur 469 significant costs for expert evidence on authenticity of the signature. Counsel for the defendant asserted that the aspersion of the defendant’s credit could not be made in relation to the Construction Contract Settlement Agreement in light of the submission that reliance was withdrawn due to the fact that it did not amount to an agreement at 470 law that could be pleaded as a defence.
In oral submissions, counsel for the plaintiffs addressed the submissions advanced by the defendant in respect of the Construction Contract Settlement Agreement. It was submitted that the defendant continuously urged weight to be placed on the face of documents throughout the proceeding, such as the signed 1 July 2013 invoice for $76,850, yet then asked the court to place no weight on a document that formed a key 471 plank of the defence for almost two years. Counsel for the plaintiffs submitted that there was no evidence to support the conclusion that the defendant had advanced in 472 oral submissions as to why reliance was abandoned.
Conclusion
465 T447.5-8. 466 T447.15-18. 467 T447.25-28. 468 T448.10-24. 469 T448.31-35. 470 T448.43-45. 471 T449.8-11. 472 T449.23-26.
As I have stated earlier in the judgment concerning credit and reliability at [6]-[13], there are unsatisfactory aspects in the evidence that do not reflect well on the reliability of the evidence of the first plaintiff or of the evidence of the defendant. Nevertheless, ultimately there is no forensic utility in determining this discrete credit point concerning the Construction Contract Settlement Agreement.
In my view, there is insufficient evidence to support a conclusion that the Additional Works were in fact additional nor that the defendant directed the additional works. The plaintiffs’ case is not clear in this regard. I am not satisfied on the balance of probabilities that the claim for Additional Works is made out by the plaintiffs.
If the whole of the partnership is illegal, are the plaintiffs entitled to restitution for monies spent and payments not claimed?
Are the plaintiffs entitled to restitution for the alleged Additional Works?
If the alleged partnership was not formed, are the plaintiffs, or either of them entitled to restitution? If so, how much?
Consideration
In the event that the partnership was held to be void for illegality, the plaintiffs submitted they are entitled to restitution in the sum reflecting the unjust enrichment which the defendant received as a result of the matters being the $25,000, the $76,850 and the Additional Works pursuant to David Securities Pty Ltd v Commonwealth Bank of Australia [1992] HCA 48; 175 CLR 353. I have determined that no partnership existed and in the alternative, if it did exist it would be void for illegality or unenforceable as 473 against public policy.
As the plaintiffs expressly sought restitution for the $25,000, the $76,850 and the Additional Works, in the context of an illegal partnership the claim for restitution for these amounts must fail in light of my previous findings that address those specific amounts. The plaintiffs are not entitled to restitution as the defendant did not in my view receive unjust enrichment as a result of the $25,000, the $76,850 and the Additional Works as discussed above.
The plaintiffs confirmed that the claim for restitution was alternative to the primary relief sought by way of declaration of the partnership. As to whether the plaintiffs were entitled to restitution for the Additional Works or whether either of the plaintiffs were entitled to restitution if the partnership was not formed, it was submitted that the court would be satisfied that the second plaintiff had performed a significant amount of work to develop the property. The plaintiffs submitted that the defendant reaped the benefit 474 of the plaintiffs’ work when he sold the property for $1,125,000. I have already
473 Plaintiffs’ submissions in reply 16 March 2020 [19]. 474 Plaintiffs’ submissions in reply 16 March 2020 [33]-[34]. determined that the evidence as to the Additional Works is unsatisfactory and the claim is not made out. The remaining claims for restitution must fail.
At the further hearing date of 16 June 2020, counsel for the defendant submitted that his position was that the illegality of the partnership agreement would infect the court’s discretion to order restitution. It was submitted that if the court was to conclude there were amounts as owing, the court would not order them to be payable to either the first 475 or second plaintiff due to the infection of the illegality.
In Brenner v First Artists Management Pty Limited [1993] 2 VR 221 at 262 where Byrne J held that when assessing a restitution claim and the quantum of that claim, the court must ‘ascertain what is fair and reasonable compensation for the benefit of the services performed and accepted actually or constructively by the recipient’.
In my view, the plaintiffs’ claim for restitution must fail.
Conclusion on the Plaintiffs’ Claim
The amended statement of claim sought damages by reason of the defendant’s breach of the partnership agreement for the contributions to the development of the property and 50 per cent of the profit realised on the sale of the property. The plaintiffs’ sought:
A declaration that the defendant held the property, and any sale proceeds, on trust for the partnership;
A declaration that the defendant owed the first plaintiff fiduciary and statutory obligations as a partner and was obliged to account to the plaintiffs’ for their contributions to the development of the property and 50 per cent of the net proceeds of sale of the property.
In the alternative to the court finding a partnership between the first plaintiff and the defendant, the plaintiffs’ claimed that the second plaintiff was entitled to be paid the full sum set out in the HIA Contract and entitled to recoup the extra expenses incurred for the development of the property. The plaintiffs’ sought:
A declaration that the defendant held the property and any proceeds from the sale thereof on resulting trust for the first plaintiff, second plaintiff, and defendant in such shares as the court deemed just and equitable as a result of the $25,000 and the second plaintiffs’ contribution to construction costs.
Further in the alternative, the plaintiffs’ sought an order that the defendant pay equitable compensation for the losses caused by breaches of fiduciary and statutory duties. The plaintiffs’ also sought in the alternative judgment for the second plaintiff against the defendant on the HIA Contract and restitutionary claims
For the preceding reasons on the plaintiffs’ claim, the partnership agreement is not made out. There is therefore no remedy available for any breach of a partnership agreement, be it a breach of the Partnership Act or a breach of any fiduciary duty. There is also no resulting trust as a result of the $25,000. Further, as the Additional Works claim is also not made out on the balance of probabilities, the plaintiffs’ are not entitled
475 T410.44-49. to remedies for breach of the HIA Contract nor restitution for the $25,000, the $76,850 or the Additional Works. The plaintiffs’ claims for remedies must fail.
Defendant’s Counterclaim
Which version of the HIA Contract did the second plaintiff and the defendant enter? Mr Cobanov’s version at page 394 of Exhibit 1 or Mr Josifovski’s version with the inclusions list at page 420 of Exhibit 1?
Did the parties intend to incorporate the inclusions list and building plans in the HIA Contract?
Evidence
John Cobanov
In the first witness statement of the first plaintiff, the first plaintiff states that in early June 2013, the defendant provided him with a copy of the original plans dated 4 June 2013 produced by Robert Jukic. The defendant then said “we need a building contract 476 to give to Patrick for the finance application”.
The first plaintiff then obtained a blank, standard form HIA Contract that he had in his possession and undertook calculations to reach the contract price. Using the original 477 plans, the first plaintiff calculated the total price as $384,250.
The first plaintiff completed Item 13 of the HIA Contract, which involved calculating the amounts for the 8 progress payments and handwriting in the quantum for each progress payment. The first plaintiff also completed Item 3 of the HIA Contract, which asks for the builder’s information. The details of the second plaintiff were handwritten by the first plaintiff into Item 3.
The first plaintiff then provided to the HIA Contract to the defendant. The first plaintiff contended that no inclusions list was attached to the HIA Contract but that he understood the defendant would prepare the inclusions list and it would be annexed in due course, along with any further information required for the defendant’s application 478 for finance.
476 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [23]. 477 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [25]. 478 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [26].
The first plaintiff claimed that on or around 12 June 2013, he signed the contract. In the second witness statement of the first plaintiff, the first plaintiff asserted that after he signed the contract on 12 June 2013, he did not discuss any amendments to it with the defendant nor with Patrick Bouquiaux. Further, the first plaintiff claimed that he did not 480 agree to any amendments to the HIA Contract.
The version of the HIA Contract that the first plaintiff relies upon was included in Exhibit 481 1 and was derived from the plaintiff’s list of discoverable documents. Of note, Item 9 of the HIA Contract, which refers to the completion time for when the building works are to reach the stage of practical completion, was left blank and no timeframe had been written in for how many days the build was to take. There is also no inclusions list annexed to the first plaintiff’s version of the HIA Contract.
In examination in chief, the first plaintiff was taken to the version of the HIA Contract that was derived from the plaintiffs’ list of discoverable documents in Exhibit 1. The first plaintiff gave evidence that he had signed this document on behalf of the second plaintiff on 12 June 2013 and confirmed that this was the version of the HIA Contract 482 he had signed on that date.
In cross examination, the first plaintiff was asked to compare the version of the HIA Contract he relied upon with the version of the HIA Contract that had been advanced by the defendant. The first plaintiff was given time to compare the difference between 483 the two versions of the HIA Contract.
The first plaintiff maintained that the version of the HIA Contract that had come from the plaintiffs’ list of discoverable documents was the contract he had entered into on 484 behalf of the second plaintiff with the defendant.
When asked what the purpose of the HIA Contract was, the first plaintiff stated that it 485 was required by the defendant to obtain finance. The first plaintiff gave evidence that he had written information into the HIA Contract, such as the quantum for each progress payment, to work out a sum for the property that was to be built. The first 486 plaintiff confirmed that his version of the HIA Contract was accurate in all respects.
Counsel for the defendant took the first plaintiff to explanatory note 1 of the HIA Contract which read:
1 The contract and the attachments
In Attachment A of this contract you and the builder must fill in the details left blank. If necessary you should also add some details in the other attachments.
If you do not use an attachment, please cross it out and initial it.
….
479 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [28]. 480 The second witness statement of the first plaintiff Tab 14 Exhibit 1 [2]. 481 Tab 79 Exhibit 1. 482 T37.41-46. 483 T108.30-34. 484 T109.42-44. 485 T110.15-16. 486 T110.18-19, 24-26. 2 Plans and specifications
Plans and specifications are also part of this contract. You and the builder must sign and date them. You both must keep a copy of this contract and of the plans and specifications.
When asked what his understanding of the phrase ‘plans and specifications’ was, the first plaintiff stated that it meant the actual plans that were approved by the government 487 and the specifications referred to specifications rendered with the HIA Contract.
The first plaintiff was then referred to the inclusions list that the defendant asserted formed part of the HIA Contract entered into by the parties. The first plaintiff agreed that the document was entitled an 'inclusions list’ but asserted that it was not an inclusions list that he had been annexed to the HIA Contract when he executed it on 12 June 2013 in the presence of the defendant and Patrick Bouquiaux. The first plaintiff noted that the inclusions list did not bear his own initials nor the initials of the 488 defendant.
Counsel for the defendant requested that the first plaintiff refer back to his version of the HIA Contract and the same time as having access to the inclusions list advanced by the defendant as forming part of the HIA Contract. When asked where the specifications were in the first plaintiff’s version of the HIA Contract and whether there was another attachment with specifications, the first plaintiff stated that there were no 489 specifications and no other attachments addressing specifications.
When asked where in his version the HIA Contract the specifications were as to the kitchen, Colourbond fencing, and showers, the first plaintiff stated that there were 490 none.
The first plaintiff was then referred back to the inclusions list. It was put to the first plaintiff that the inclusions list was on the stationery of the second plaintiff and that it also had the name of the second plaintiff on it. The first plaintiff confirmed that the inclusions list had the second plaintiff’s name on it but denied that it was on the 491 stationery of the second plaintiff.
Counsel for the defendant put it to the first plaintiff that it had been the first plaintiff who had inserted the details on the cover page of the inclusions list, which had the name and address of the second plaintiff, ‘June 2013’ and ‘Block 1 Section 104 Casey, ACT 2913 Client: Kiki Josifovski’ typed on it. The first plaintiff denied that he had inserted 492 this information onto the cover page of the inclusions list.
The first plaintiff was queried whether he honestly was to tell he court that the document bearing the details of the second plaintiff was prepared by someone other than himself. The first plaintiff maintained that the inclusions list had been prepared by someone else. When it was put to the first plaintiff that he prepared the inclusions list, the first 493 plaintiff again stated that he did not prepare it.
487 T111.8-11. 488 T11.23-26. 489 T113.38-42. 490 T113.44-46 & T114.1-8. 491 T114.31-33. 492 T114.35-37. 493 T115.2-14.
Construction Site cut (+/- 300mm deviation) and fill. Excludes rock Engineered concrete stiffened raft or waffle slab (as per engineers report). Footings and slabs to AS2870 Termite resistant timber wall frames and roof trusses Bristille Concrete tiles roof, colorbond fascia, and 100x50mm downpipes Aluminium power-coated windows, sliding doors, security screen doors and fire rate flyscreens as per plan Selected face brickwork $600 (inc. GST) p/1000 2700mm ceiling height lower floor as per plans 2400mm ceiling height upper floor as per plans Insulation to specifications (as per energy report) 495
Counsel for the Defendant: That type of information – the information on that page is rather specific, isn’t it?
First Plaintiff: It is, but if you look at the specifics of it, it doesn’t correlate with the plans. You’ve got heights there of 2.7, which are not in the plan. You have hydronic heating, which is not in the plan. There’s an array of other things that are not in the plan. So – so whoever added this, added this after the fact… I signed a contract with Kiki. We lodged that with the broker and the broker came back to us and said you need an inclusions list and I believe that Kiki took this on his own back and did it himself and inserted this with the broker, because again there is no signature, there’s no initials, there’s nothing to say we both looked at 496 this.
494 T115.20-25. 495 T115.38. 496 T115.40-47 & T116.1-2. 497 T116.30-37.
The first plaintiff agreed that his version of the HIA Contract had no specifications. When it was put to the first plaintiff that the second plaintiff would have been unable to construct the property without an included allowance list, the first plaintiff maintained that he and the defendant were going to build and choose specifications as they went 498 on an ad hoc basis, given they were partners. The first plaintiff continued to maintain that no document entitled ‘inclusions list’ was ever agreed on between himself and the 499 defendant.
The first plaintiff was then referred to the defendant’s version of the HIA Contract to item 9 which is where the completion time is to be handwritten in. The first plaintiff’s version of the HIA Contract leaves item 9 blank whereas the defendant’s version of the HIA Contract has 180 days handwritten in. The first plaintiff agreed that in the 500 defendant’s version of the HIA Contract, 180 days had been entered in.
When asked whether he had entered the 180 days, the first plaintiff denied doing so. The first plaintiff further denied that the 180 days had been agreed upon with the 501 defendant.
In re-examination, the first plaintiff maintained that the purpose of the HIA Contract was to facilitate the provision of a loan from Westpac Bank so that the property could be 502 purchased. The first plaintiff gave evidence that no specifications as to inclusions and allowances were necessary in the HIA Contract, given the involvement of the defendant in the build. The first plaintiff confirmed that the predominant differences between his version of the HIA Contract and the defendant’s HIA Contract was the addition of 180 days handwritten into the defendant’s version and the annexure of the 503 inclusions list to the defendant’s version.
Elle Cobanov
Kiki Josifovski
In the first witness statement of the defendant, the defendant denied that he said to the first plaintiff he required a HIA contract in order to obtain finance. The defendant contended that after he received the original plans dated 4 June 2013, he gave the plans to the first plaintiff to facilitate the provision of an updated costing, an inclusions 505 list, and a timeframe for the build.
The defendant could not recall the specific date but agreed that the first plaintiff had handed him a blank standard HIA Contract to consider. The defendant’s best recollection was that on that occasion, the first plaintiff said words to the effect of “it will cost about $380,000 to $385,000 to build the house according to Robert’s plans. I will
498 T117.31-35. 499 T121.17-18. 500 T130.22. 501 T130.24-26. 502 T179.4-5. 503 T179.16-18, 40-47. 504 T145.11-16. 505 The first witness statement of the defendant Tab 8 Exhibit 1 [20]-[21]. take about 180 days to build”. The defendant recalled that the conversation took place 506 during a meeting at the work address of the second plaintiff.
The defendant stated that he and the first plaintiff met a couple of days thereafter at the work address of the second plaintiff. On this occasion, the defendant agreed to the build cost and to enter into the standard form HIA Contract stating it would cost $384,250 to build. The defendant stated that the HIA Contract was based on the original plans dated 4 June 2013 and an inclusions list dated June 2013 prepared by the first 507 plaintiff.
The defendant denied that there was no inclusions list attached to the HIA Contract and further denied preparing the inclusions list. The defendant noted that the inclusions list had the details of the second plaintiff on each page of the inclusions list in the 508 footer.
While denying authoring the inclusions list, the defendant stated that he had discussions with the first plaintiff prior to receiving the HIA Contract to discuss the plans 509 and the inclusions that the defendant wanted within the home.
The defendant also recalled that when he asked the first plaintiff why the HIA Contract had no prime cost or provisional sum items in attachments D and E, the first plaintiff referred to the allowances in the inclusions list as being prime costs/ provisional sums and said words to the effect of:
First Plaintiff: Those sections are covered in the attached inclusions list. It provides your allowances so you know how much you have to spend when dealing withs suppliers and selecting finishes. It also lists the specifications, so you 510 know what you’re getting.
On or about 12 June 2013, the defendant met with the first plaintiff and Patrick Bouquiaux at Tiffen & Co’s office in Kingston to execute the HIA Contract. The original HIA Contract was executed by the defendant and the first plaintiff on behalf of the second plaintiff. The original was copied twice by Patrick Bouquiaux and a copy was given to the first plaintiff and the defendant. Although the defendant had not yet exchanged the contract for the sale of the land, the defendant stated at this point in 511 time he was confident that exchange was imminent.
The defendant recalled that either on that occasion on 12 June 2013 or shortly thereafter, Patrick Bouquiaux advised him that Westpac Bank required a completion date. The defendant admitted that he inserted the build item at Item 9 of Attachment A 512 of the HIA Contract, being a period of 180 days. The version of the HIA Contract that the defendant says he entered into with the first plaintiff on behalf of the second plaintiff was exhibited to the first witness statement of the defendant and formed part of Exhibit 513 1.
506 The first witness statement of the defendant Tab 8 Exhibit 1 [23]. 507 The first witness statement of the defendant Tab 8 Exhibit 1 [24]. 508 The first witness statement of the defendant Tab 8 Exhibit 1 [25]. 509 The first witness statement of the defendant Tab 8 Exhibit 1 [25]. 510 The first witness statement of the defendant Tab 8 Exhibit 1 [25]. 511 The first witness statement of the defendant Tab 8 Exhibit 1 [26]. 512 The first witness statement of the defendant Tab 8 Exhibit 1 [27]. 513 Tab 80 Exhibit 1.
In the second witness statement of the defendant, the defendant responded to the portion of the second witness statement of the first plaintiff as to the HIA Contract. The defendant denied that the HIA Contract was not amended after it was signed on 12 June 2013. The defendant further denied that he and the first plaintiff had not discussed 514 the amendments.
The defendant was cross-examined in respect of the inclusions list by reference to the Campa project. As previously referenced, Exhibit 16 in the proceedings was an email forwarded by the defendant from Alfonso Campa to the email address of the second plaintiff dated 25 April 2013. That full email read:
John,
As discussed here are the final plans for crace. Call me when you review these so we can figure out how to go about it. I have done the numbers and it looks good.
Also when you can, get me the quote for the demountable. Remember to change the specs slightly.
Talk soon.
The defendant was then referred to a document title ‘Build Costing Schedule’. Underneath the title, it read ‘Block 8 Section 64 Crace | Client: Alphonso (sic) Campa’. On the second page of the Build Costing Schedule was a heading ‘Included Allowances’. When asked if he authored the Build Costing Schedule, the defendant 515 stated he did not recall doing so.
The defendant was then asked to refer to the inclusions list he said was included as part of the HIA Contract in reference to the Build Costing Schedule. The inclusions list that the defendant claimed was annexed to the HIA Contract included a table under the heading Included Allowances. That table was in the following format and design:
Inclusion Total Allowance
Kitchen including appliances $40,000
Stairs as per client selection $10,000
Hydronic In-slab Heating $10,000
Exterior Rendering $18,500
Retaining Walls $6,000
Colorbond Fencing $5,000
Lighting $2,500
Tiling $30 per m²
Carpet $30 per m²
Wardrobes $3,000
Bathroom Vanity Units $3,000
514 The second witness statement of the defendant Tab 15 Exhibit 1 [4]. 515 T282.24-25. Bathroom Tapware $2,000
Toilets $2,000
Showers $1,200
Laundry $2,000
Front Door (including front door $1,500 furniture), internal door furniture
Inclusion Total Allowance
Kitchen Areas including appliances $46,000
Stairs as per client selection $10,000
Hydronic In-slab Heating $10,000
Exterior Rendering $18,500
Colorbond Fencing $5,000
Lighting $2,000
Tiling $30 per m²
Carpet $30 per m²
Wardrobes $3,000
Bathroom Vanity Units $3,000
Bathroom Tapware $2,000
Toilets $2,000
Shower per unit $500
Laundry $1,000
Front Door (including front door $1,500 furniture), internal door furniture
The defendant agreed that while there were some differences in the tables, there were 516 a number of similarities, such as:
The first inclusion in the Build Costing Schedule is ‘Kitchen areas, including appliances’ and the first inclusion on the inclusions list is 517 ‘Kitchen, including appliances’.
516 T284.13-14. 517 T285.5-9. 4. The second inclusion ‘Stairs as per client selection’ was identical in 518 both tables as to inclusion and amount.
The third inclusion ‘Hydronic In-slab Heating’ was identical in both 519 tables as to inclusion and amount.
The third inclusion ‘Exterior Rendering’ was identical in both tables 520 as to inclusion and amount.
While ‘Retaining Walls’ was included as the fourth inclusion on the inclusions lists but not the Build Costing Schedule, the entry for ‘Colorbond Fencing’ was identical in both tables as to inclusion and 521 amount.
The inclusion ‘Lighting’ is referenced in both tables, notwithstanding 522 the different quantum in each table.
The inclusions ‘Tiling’ and ‘Carpet’ were in both tables for the same 523 amount.
The inclusion ‘Wardrobe’ was identical in both tables as to inclusion 524 and amount.
The inclusion ‘Bathroom Vanity Units’ was identical in both tables as 525 to inclusion and amount.
The inclusion ‘Bathroom Tapware’ was identical in both tables as to 526 inclusion and amount.
The inclusion ‘Toilets’ was identical in both tables as to inclusion and 527 amount.
Underneath both of the tables were the words ‘In addition to the items listed above, the build will also include the following general specifications as per the plan provided:’ with further subheadings. The subheadings in both the inclusions list and the Build Costing Schedule were in the following order:
General;
Construction;
Insulation;
Internal Doors;
Skirting & Architraves;
518 T283.30-33. 519 T283.35-36. 520 T283.38. 521 T284.40-44. 522 T284.46-47. 523 T285.2-3. 524 T284.5. 525 T284.7. 526 T284.9. 527 T284.11. 6. Garage Door;
Plastering;
Plumbing;
Electrical;
Cabinetry;
Bathrooms and Ensuite;
Finishes;
Painting - Internal – External;
External.
The following is directly extracted from the general specifications in the inclusions list:
General Connection to services (not including final owner connection fees) Construction Site cut (+/- 300mm deviation) and fill. Excludes rock Engineered concrete stiffened raft or waffle slab (as per engineers report). Footings and slabs to AS2870 Termite resistant timber wall frames and roof trusses Bristille Concrete tiles roof, colorbond fascia, and 100x50mm downpipes Aluminium powder-coated windows, sliding doors, security screen doors and fire rated flyscreens as per plan Selected face brickwork $600 (inc. GST) p/1000 2700mm ceiling height lower floor as per plans 2400mm ceiling height upper floor as per plans Insulation to specifications (as per energy report) Insulation R2.0 Batts to external walls and R4.0 Batts to ceiling of living areas Internal Doors Oakfield or equivalent (including plastic door stops) -height as per plans Gainsborough or equivalent door contemporary furniture throughout- Standard height Skirting & Architraves 67x8mm MDF pre primed craftwood Garage Door Automatic dual sectional door Garage front , includes x2 remotes Upgrade to timber dual sectional Garage door Single roller door at rear (non-automatic) Plastering 10mm plasterboard to walls and ceilings, 6mm villaboard to wet areas Square set cornice (Downstairs living, kitchen and theatre) 75mm scotia cornice Plumbing Instantaneous gas unit Laundry – Single 45 litre flushline tub in laminated benchtop unit External garden taps (x4) on building Stormwater lines and pit lids Water point for fridge Electrical Metering connected to street, up to 10 metres allowed 40 x power points allowed (34 double, 6 single) 4 x TV points connected to one roof antenna 10 x Phone/data point 3 x External light points 2 x Smoke detectors (hardwired with battery back-up) Exhaust fans in bathrooms Cabinetry Full Height Robes– fixed shelf with hanging rail including open divided shelving and drawer. Dual sliding mirrored doors WIR–fixed shelf with hanging rail and open divided shelving and drawer Linen - open divided shelving with dual vinyl sliding doors Bathrooms and Ensuite Modern vanity basins with mixer tapware to all basins and sinks Mirror over vanity units (to length of unit) Builders range chrome double towel rails and toilet roll holders Floor to ceiling tiling (as per tiling allowance) in main bathroom and ensuite Four bulb tastic in main bathroom and ensuite/two bulb in additional bathrooms Obscure glass windows to WC’s, Bath and Ensuite as per plan requirements Finishes Glass Splashback to Kitchen Tiled splashbacks to Laundry and Vanity Basins Tiled skirting to Bathroom, En-suite, WC and Laundry Painting Internal 3 coats low sheen paint on walls throughout. 2 coats paint to ceiling throughout. Enamel acrylic paint to woodwork. Choice of one wall colour including woodwork and one ceiling colour. External 3 coats solarguard external paint to rendered areas External Cladding/surfacing as per plans Concrete driveway to street. Concrete to Entry and Alfresco Wall mounted clothesline Engineered stiffened raft or waffle slab design H2 termite resistant timber wall frames and roof trusses. Colorbond roofing, colorbond fascia, and 100x50mm downpipes.
General Connection to services (not including final owner connection fees) Construction Site cut (+/- 300mm deviation) and fill. Excludes rock Engineered concrete stiffened raft or waffle slab (as per engineers report). Footings and slabs to AS2870 Termite resistant timber wall frames and roof trusses Bristille Concrete tiles roof, colorbond fascia, and 100x50mm downpipes Aluminium powder-coated windows, sliding doors, security screen doors and fire rated flyscreens as per plan Selected face brickwork $600 (inc. GST) p/1000 2700mm ceiling height lower floor as per plans 2400mm ceiling height upper floor as per plans Insulation to specifications (as per energy report) Insulation R2.0 Batts to external walls and R4.0 Batts to ceiling of living areas Internal Doors Oakfield or equivalent (including plastic door stops) – Standard height Gainsborough or equivalent door contemporary furniture throughout- Standard height Skirting & Architraves 67x8mm MDF pre primed craftwood Garage Door Automatic dual sectional door Garage front , includes x2 remotes Upgrade to timber dual sectional Garage door Single roller door at rear (non-automatic) Plastering 10mm plasterboard to walls and ceilings, 6mm villaboard to wet areas Square set cornice (Downstairs living, kitchen and theatre) 75mm scotia cornice Plumbing Instantaneous gas unit Laundry – Single 45 litre flushline tub in laminated benchtop unit External garden taps (x4) on building Stormwater lines and pit lids Water point for fridge Electrical Metering connected to street, up to 10 metres allowed 40 x power points allowed (34 double, 6 single) 4 x TV points connected to one roof antenna 10 x Phone/data point 3 x External light points 2 x Smoke detectors (hardwired with battery back-up) Exhaust fans in bathrooms Cabinetry Full Height Robes– fixed shelf with hanging rail including open divided shelving and drawer. Dual sliding mirrored doors WIR–fixed shelf with hanging rail and open divided shelving and drawer Linen - open divided shelving with dual vinyl sliding doors Bathrooms and Ensuite Modern vanity basins with mixer tapware to all basins and sinks Mirror over vanity units (to length of unit) Builders range chrome double towel rails and toilet roll holders Floor to ceiling tiling (as per tiling allowance) in main bathroom and ensuite Four bulb tastic in main bathroom and ensuite/two bulb in additional bathrooms Obscure glass windows to WC’s, Bath and Ensuite as per plan requirements Finishes Tiled splashbacks to Laundry and Vanity Basins Tiled skirting to Bathroom, En-suite, WC and Laundry Painting Internal 3 coats low sheen paint on walls throughout. 2 coats paint to ceiling throughout. Enamel acrylic paint to woodwork. Choice of one wall colour including woodwork and one ceiling colour. External 3 coats solarguard external paint to rendered areas External Concrete driveway to street. Concrete to Entry and Alfresco Wall mounted clothesline Engineered stiffened raft or waffle slab design H2 termite resistant timber wall frames and roof trusses. Builders selection Concrete tiles roof, colorbond fascia, and 100x50mm downpipes Lintels with brickwork above
In cross examination, counsel for the plaintiffs’ questioned the defendant on the basis that Elle Cobanov had given evidence that she did not recognise the inclusions list. It was put to the defendant that the Building Costing Schedule for the Campa project was the only document similar to the inclusions list, both of which projects involved the 528 defendant. The defendant responded that he did not know if that was the case.
The Build Costing Schedule became Exhibit 17 in the proceedings. Counsel for the defendant submitted that the Build Costing Schedule ought to be admitted only for the limited purpose of the assertion that it was prepared by the defendant. Counsel for the 529 plaintiffs confirmed that was the purpose it was sought to be tendered.
It was put to the defendant that he had prepared the inclusions list. The defendant denied doing so. The defendant further denied that he had added to the inclusions list 530 to the HIA Contract after it had been executed.
The defendant also confirmed that he had handwritten ‘180’ days into Item 9 of the HIA 531 Contract. When asked whether he still maintained that Westpac Bank required the completion time to have an allocated timeframe, the defendant gave evidence that it was both the requirement of the bank and a requirement of his agreement with the first plaintiff to build the property within the time period that he had promised he would do it 532 in.
Counsel for the plaintiffs noted that in the first witness statement of the defendant, the defendant refers to the insertion of 180 days solely being a requirement of the bank. The defendant said that the reference to the conversation whereby the first plaintiff provided the defendant with the blank HIA Contract to consider and said words to the effect of “it will cost about $380,000 to $385,000 to build the house according to Robert’s plans. I will take about 180 days to build” was a reference to the 180 days 533 being a requirement of the agreement with the first plaintiff.
When referred to the conversation the defendant had with Patrick Bouquiaux where Patrick Bouquiaux informed him that Wesptac Bank required a completion timeframe, the defendant gave evidence that he had spoken to the first plaintiff before he wrote in 534 180 days and that the first plaintiff had agreed to this timeframe. The defendant was queried as to whether he had asked the first plaintiff if the first plaintiff thought 180 days
528 T285.10-14. 529 T287.6. 530 T286.22-23. 531 T294.36-37. 532 T294.39-44. 533 T295.44. 534 T296.23-28. was a realistic timeframe. The defendant responded that 180 days had been the time 535 period the first plaintiff had said he would build within all along.
It was put to the defendant that he did not discuss the unilateral insertion of 180 days with the first plaintiff, nor did he confirm with the first plaintiff if 180 days was agreed. The defendant maintained that he did discuss and receive confirmation from the first 536 plaintiff.
When queried as to when he had handwritten 180 days into Item 9 of the HIA Contract, the defendant gave evidence that his recollection was that it would have been on the same occasion it was executed at Tiffen & Co, shortly after it was signed by the first 537 plaintiff and the defendant.
The defendant was reminded that the HIA Contract relied upon by the first plaintiff did not contain the 180 days in Item 9. It was put to the defendant that the HIA Contract was executed by the parties and Item 9 had not been completed, copies were made by Patrick Bouquiaux and thereafter the defendant made the hand amendment. The defendant said he could not recall the timeline of events as to the order of the copying 538 and that he did not know if it had been copied prior to the insertion of 180 days.
Consideration
The plaintiffs’ submitted that the court ought to prefer the evidence of the first plaintiff over the evidence of the defendant as to the execution of the HIA Contract at Tiffen & Co on 12 June 2013. It was submitted that the HIA Contract was prepared in order to facilitate finance from the Westpac Bank and that the contract itself was not intended to govern the relationship between the parties. The plaintiffs’ reiterated that it would not have been prudent for the defendant to execute the HIA Contract in circumstances when exchange of the property had not occurred nor had he fully secured the finance 539 upon which to develop the property.
The plaintiffs’ drew upon Exhibit 17, being the Build Costing Schedule for the Campa Project. It was submitted that the Build Costing Schedule provided a documentary link 540 between the defendant and the inclusions list. The plaintiffs’ referred to the evidence of Elle Cobanov that she did not recognise the inclusions list as a document which the 541 second plaintiff used or had used during her time working for the second plaintiff. I have no reason not to accept the evidence of Elle Cobanov in this regard.
It was submitted that the Build Costing Schedule and the inclusions list were in a strikingly similar template and that each of the documents arise in relation to jobs where the defendant was involved. The plaintiffs asserted that the court ought to infer the defendant had prepared both the Build Costing Schedule and the inclusions list.
The plaintiffs further reiterated that explanatory note 2, which is on the HIA Contract template, sets out that plans and specifications must be signed and dated. It was submitted that there was no evidence of a signed inclusions list nor signed plans
535 T296.30-31. 536 T296.36-42. 537 T297.32-34. 538 T298.36-47. 539 Plaintiffs’ submissions in chief 4 December 2019 [30]. 540 Plaintiffs’ submissions in chief 4 December 2019 [20(b)]. 541 Plaintiffs’ submissions in chief 4 December 2019 [32]. adduced in the proceeding. The plaintiffs asserted that there is no proof that those 542 items formed part of the HIA Contract.
The plaintiffs’ also pointed to the fact that both the first plaintiff and the defendant denied preparing the inclusions list. Further reference was made to the evidence of Elle Cobanov not recognising the document, as well as the unchallenged evidence that the first plaintiff did not have the computer skills to use word processing software. The plaintiffs submitted that if the defendant’s version of the HIA Contract was to be accepted, the court would have to infer the creation of a contractual document out of 543 nowhere.
It was submitted that the better explanation of the discrepancies between the versions of the HIA Contract was that the defendant had prepared the inclusions list and added it to his copy of the HIA Contract unilaterally. The plaintiffs asserted that this was not a valid incorporation on the terms of the building contract and furthermore, that it did not represent a meeting of the minds for the purposes of forming an enforceable contract. The plaintiffs ultimately urged the determination that the plans and inclusions list did 544 not form part of the HIA Contract. I note at this juncture that the state of the evidence concerning the inclusions list is unsatisfactory.
In oral submissions at the further hearing, counsel for the plaintiffs reiterated that if the defendant’s version of the inclusions list was to be accepted, the court would have to conclude that it was unclear where the inclusions list had originated from. Counsel for the plaintiffs submitted that the court ought to prefer the version proffered by the first 545 plaintiff that the inclusions list was not part of the HIA Contract. In view of the unsatisfactory state of the evidence concerning the inclusions list, I am not satisfied on the balance of probabilities that this inclusions list was part of the HIA Contract.
In oral submissions in reply, counsel for the plaintiffs claimed that the inclusions list tritely ought to be referred to as the “immaculate inclusions list” in circumstances where 546 both the first plaintiff and the defendant denied preparing the document. It was submitted that as the inclusions list remained of unknown and unknowable origin, the court ought to have serious pause as to whether it was capable of representing a meeting of the minds of the parties. As indicated above, I am not satisfied on this matter on the balance of probabilities on all of the evidence.
The plaintiffs conceded that there may have been valid incorporation of the inclusions list if the defendant had admitted to preparing it, as the first plaintiff had given evidence that he expected the defendant was going to prepare an inclusions list. The plaintiffs submitted that in circumstances where the defendant repeatedly denied preparing the inclusions list, the first plaintiff’s mere expectation bore no relevance to the 547 determination of incorporation. Again as stated above, the evidence in relation to the inclusions list is entirely unsatisfactory.
The defendant submitted that determining which version of the HIA Contract was agreed is a question of fact: Toll (FGCT) Pty Limited v Alphapharm Pty Limited [2004]
542 Plaintiffs’ submissions in reply 16 March 2020 [37]. 543 Plaintiffs’ submissions in reply 16 March 2020 [38]. 544 Plaintiffs’ submissions in reply 16 March 2020 [39]. 545 T381.37-45. 546 T431.34-42. 547 Plaintiffs’ submissions in reply 16 March 2020 [41]. HCA 52; 219 CLR 165 at [40]. While this is correct, the state of the evidence as to that fact is unsatisfactory.
The defendant referred to the standard HIA Contract providing in explanatory note 2 that plans and specifications are part of the contract. It was submitted that explanatory 548 note 2 not being contractual in nature was of no moment.
The evidence of the first plaintiff that he understood the defendant would prepare an inclusions list was relied upon by the defendant to assert that the inclusions list formed part of the HIA Contract. It was submitted that if the court accepted the evidence of the first plaintiff that the inclusions list was not part of the HIA Contract when it was executed, it must still follow the first plaintiff agreed an inclusion list would be part of 549 the terms. In my view, it does appear on the balance of probabilities on the evidence that the inclusions list was not part of the HIA Contract when it was executed.
The defendant submitted that the evidence of the first plaintiff that specifications were determined by consultation with the defendant on an ad hoc basis ought to be rejected. The defendant submitted that this evidence was implausible for the following reasons:
The defendant was a first homeowner in his mid-twenties who worked a s a public servant. There had not been evidence that he had experience in building and construction.
It would have been either highly impractical or impossible for the first plaintiff to continually liaise with the defendant as to specifications and inclusions when the defendant was offsite due to his fulltime employment.
It would have been a strange commercial arrangement if the defendant was required to pay the contract price and then participate in the works.
There was no adequate evidence of the defendant giving instructions of the kind to be expected in lieu of an inclusions list. Although there was email correspondence as to some specifications, they were sparce and not sufficient to canvass the extent of the development.
While the original plans dated 4 June 2013 contain some specifications, they do not contain the information that would be borne out by an inclusions list.
As the first plaintiff had calculated the contract price on 12 June 2013, it must follow that the quantum was based on something more than the original plans. It must be that the quantum was informed by the inclusions list.
I agree that an arrangement that entailed the specifications on an ad hoc basis does not on the evidence appear realistic. That of itself is not enough to conclude that this particular inclusions list formed part of the HIA Contract.
The defendant submitted that the cross examination in relation to the similarities between the Build Costing Schedule for the Campa project and the inclusions list did not yield any relevant evidence. It was asserted that even if the evidence supported a conclusion that the defendant had prepared the Build Costing Schedule, it would not
548 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [121]-[122]. 549 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [123]. support a conclusion that the defendant created the inclusions list. It was submitted that the assertion of the plaintiffs’ that the Build Costing Schedule informed the genesis 551 of the inclusions list was groundless. I do not agree that it was groundless.
In oral submissions, counsel for the defendant again referred to the evidence of the first plaintiff that he understood the defendant would prepare an inclusions list and it would be added to the contract in due course.
Counsel for the defendant submitted that the court would be alarmed at the prospect that the parties would have been able to proceed to develop the property in the absence of an inclusions list in the HIA Contract. It was submitted that the contract was 552 meaningless without an inclusions list. I agree that an inclusions list must have been contemplated.
When queried about the plaintiffs’ submission that the inclusion list relied upon by the defendant was not on the stationery of the second plaintiff, counsel for the defendant submitted that it was said that it was the plaintiffs’ who created the inclusions list and referred to the evidence of the defendant that he did not prepare the inclusions list. Counsel for the defendant submitted that it of no moment that the first plaintiff denied 553 the inclusions list was not on the stationery used by the second plaintiff. As stated earlier, the state of the evidence is unsatisfactory and consequently the submissions concerning the evidence are self-evidently based on unsatisfactory evidence.
Counsel for the defendant submitted that there was nothing to be achieved in determination of this issue by querying who in fact prepared the inclusions list, in light of the first plaintiff’s evidence that he understood the defendant was going to prepare 554 the inclusions list. This is difficult to reconcile with the defendant’s submission that the first plaintiff authored the inclusions list.
It was submitted that there was no evidence that the defendant had the skillset to author the inclusions list. Notwithstanding this, even if the defendant did author the inclusions 555 list this was what the first plaintiff expected.
In relation to the query of whether the parties intended to incorporate the inclusions list and building plans, the defendant submitted that the objective evidence established 556 that the parties did intend to incorporate those documents. The defendant submitted that if the court was to conclude that the inclusions list did not eventuate until after the HIA Contract was executed rather than concluding that it formed part of the HIA Contract when it was executed on 12 June 2013, such a determination would not bar 557 incorporation of the documents.
The defendant submitted that as the first plaintiff’s evidence was that he expected an inclusions list to be prepared by the defendant, the inclusions list was intended to be incorporated: Hollier v Rambler Motors (A.M.C) Ltd [1972] 2 QB 71 at 77-78 (Salmon
550 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [131]. 551 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [132]. 552 T414.44-49. 553 T414.38-43. 554 T416.13-16. 555 T437.30-37. 556 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [133]. 557 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [134]. LJ). As stated above, I note at this juncture it is clear an inclusions list was contemplated.
The defendant also submitted that it did not matter that the inclusions list and the plans had not been signed and dated by the parties. The absence of signatures did not bar their incorporation in the absence of an express term in the contract saying that 558 unsigned plans and inclusions lists are excluded. I agree that incorporation is thereby not excluded.
In submissions in reply, the defendant further submitted that absent the inclusions list, there was no way that the plaintiffs’ could have built the house as the detail and 559 specifications in the original plans was not sufficient. This of course begs the question of whether this is the inclusions list contemplated by the parties.
I note in passing that the “immaculate inclusions list” includes items that are not apparently referable to the original plans dated 4 June 2013. The first plaintiff claimed 560 in cross examination that there was “an array of things that [were] not in the plan” but this point remained undeveloped and I include it only for completeness.
In conclusion, in my view it is not established on the balance of probabilities that this inclusions list formed part of the HIA Contract.
Did the first plaintiff fail to adequately supervise the works undertaken by the second plaintiff?
Evidence
John Cobanov
Kiki Josifovski
558 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [135]. 559 Defendant submissions in reply on the counterclaim 9 April 2020 [12], [15]. 560 T115.43-44. 561 Defence to amended statement of claim and counterclaim 24 October 2019 [66]. 562 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [40], [43]. 563 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [41]-[42]. 564 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [92].
The defendant asserted that during construction in 2014, the first plaintiff was often absent from the site, including in or around the following periods:
April 2014 to June 2014;
Various periods from August to October 2014; and
From December 2014 onwards.
Defendant Submissions
The defendant noted that in both versions of the HIA Contract, the second plaintiff’s information is inserted as the builder. It was not disputed that as the sole director, secretary and shareholder of the second plaintiff, the first plaintiff was the sole controller 565 of the second plaintiff.
By way of establishing a timeline in respect of this issue for determination, reference was made by the defendant to the fact that settlement of the property occurred on 26 July 2013. It was also noted that approval to commence building works and the commencement notice were issued on or around 15 August 2013. Construction 566 commenced on the property in around September 2013.
The defendant noted that the first plaintiff’s evidence was that he was away for most of September 2013. It was submitted that the plaintiffs were absent at the commencement of the construction process. The defendant claimed that the second plaintiff could not have meaningfully commenced the construction in the absence of the first plaintiff, even if subcontractors were present. The defendant stated that subcontractors presumably 567 would have required guidance and supervision from the second plaintiff.
In oral submissions, counsel for the defendant noted that the court had not received evidence that the second plaintiff had any other employees apart from Elle Cobanov, who was only involved in office administration as opposed to the construction focus of 568 the second plaintiff’s business.
It was submitted that if the court found that the inclusions list was not part of the HIA Contract, it would have been even more difficult for subcontractors to have meaningfully commenced construction by reference to the plans only when the first plaintiff was 569 overseas.
Plaintiff Submissions
The plaintiffs contended that the defendant only pressed this issue in relation to the commencement of the build in September 2013, when the first plaintiff admitted he was overseas for a period of two weeks.
It was submitted by the plaintiffs that there was no basis for the court to infer that the first plaintiff inadequately supervised the second plaintiff. Further, the plaintiff claimed that the defendant did not press this finding, nor would such a finding be of any utility 570 to the determination of the counterclaim.
565 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [136]. 566 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [137]-[138]. 567 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [138]. 568 T417.42-46. 569 T417.48-51. 570 Plaintiffs’ submissions in reply 16 March 2020 [42]-[43]. Consideration
Did the second plaintiff fail to complete the works?
Evidence
George Pudja
An affidavit of George Pudja affirmed 22 February 2019, which annexed a copy of a report prepared at the request of the defendant dated 22 February 2019 and the curriculum vitae of the deponent (the George Pudja report), was part of the Index to Court Book jointly filed by the parties.
George Pudja is a licensed Builder and a licensed Building Consultant. George Pudja attended the property for the purpose of inspecting and reporting on alleged defective, non-compliant and incomplete works relating to the property.
George Pudja did not give evidence at the hearing. Counsel for the defendant formally read the affidavit of George Pudja. Counsel for the plaintiffs objected to the affidavit on the basis that the affidavit and the George Pudja report were prepared at a time when the defendant still owned the property. It was submitted that the George Pudja report was created to establish what the defects were in the construction and the setting out the costs of repairing said defects. Counsel for the plaintiffs claimed that the report ought to be admitted only to establish any liability for breach of the HIA Contract and to establish a ceiling as to the reasonable costs of rectification. The George Pudja 571 report was received by the court subject to weight.
John Cobanov
In the first witness statement of the first plaintiff, the first plaintiff stated that progress payment 8, being the final progress payment, was received on 24 November 2014 from Westpac Bank. Progress payment 8 was for $24,434. The first plaintiff noted that the 572 construction was not completed when this payment was received.
In the second witness statement of the first plaintiff, the first plaintiff clarified that he did not ring the defendant to tell him practical completion had been reached. The first plaintiff stated that nevertheless, the final progress payment was released by Westpac Bank. The first plaintiff had not taken part of any conversation with the defendant nor with Patrick Bouquiaux as to the final progress payment being released in error by 573 Westpac Bank.
571 T339.44-47 & T340.1-2. 572 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [58]. 573 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [21]-[22].
The first plaintiff stated that by late November 2014, the development was near completion. At this time there were several suppliers and subcontractors that were chasing the first plaintiff for payment of their invoices and accounts. The first plaintiff asserted that there were heated discussions between the defendant and himself on 574 this issue.
The first plaintiff asserted that on 28 November 2014, the first plaintiff received $22,400 575 from the defendant to go towards unpaid expenses associated with the construction.
On 5 December 2014, the first plaintiff claimed that there was to be a meeting with the defendant and himself at the office of the second plaintiff to discuss the unpaid invoices and accounts. The defendant said words to the effect of “you have the final payment, 576 you need to pay people so it can be finished”.
The discussion between the first plaintiff and the defendant became heated. The defendant said to the first plaintiff “I don’t trust you to use that money to make the right payments”. The first plaintiff felt there was no utility to continue the discussions and 577 said to the defendant “fine I’ll give you a cheque for the $28,000 and you can do it”. The first plaintiff then drew a cheque for $28,000 in the name of the defendant and provided the cheque to the defendant.
In the second witness statement of the first plaintiff, the first plaintiff stated that the cheque for $28,000 drawn on 5 December 2014 was not referable to any error by 578 Westpac Bank in releasing the $28,434 final progress payment.
On 24 December 2014 the first plaintiff received a phone call from the defendant who was angry. The first plaintiff asserted that words to the effect of the following conversation ensued:
Defendant: I am in the home and the sewerage is blocked.
First Plaintiff: What are you doing in there, there is no final yet. It’s Christmas eve, there is nothing I can do and you shouldn’t be in there.
The defendant then terminated the phone call with the first plaintiff. The first witness statement of the first plaintiff does not allege that the first plaintiff ever returned to the 579 property thereafter.
In cross examination, the first plaintiff was referred to the George Pudja report. The first plaintiff had confirmed that he had previously received the George Pudja report, but did 580 not look at it nor read it as the property had been sold by the defendant.
The following exchange took place in cross examination:
Counsel for the Defendant: Sir, I am going to be asking you a number of questions as to whether or not you performed the
574 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [59]. 575 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [60]. 576 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [62]. 577 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [62]-[63]. 578 The second witness statement of the first plaintiff Tab 14 Exhibit 1 [23]. 579 The first witness statement of the first plaintiff Tab 6 Exhibit 1 [64]. 580 T119.16-22. works that are the subject of that report. Do you agree that you did? 581 First Plaintiff: Yes, I did.
First Plaintiff: I think I’ve seen enough of this document. I mean, pretty much I stand by my product and my trades stand by my products. If it was necessary for us to come back and repair, we would have done repairs.
…
So, this documentation by a consultant – we should have had the chance to go and have a look at the complaints.
…
And if there were any complaints, we would have 582 addressed them…
Kiki Josifovski
In the first witness statement of the defendant, the defendant agreed that Westpac Bank had released the sum of $28,434 to the second plaintiff but that it had actually occurred on or around 4 December 2014 and not on 24 November 2014. The defendant confirmed it was the outstanding amount of the construction finance, being the final 583 progress payment.
The defendant stated that Patrick Bouquiaux had informed him that the final progress payment had been released to the second plaintiff in error. The defendant recalled that Patrick Bouquiaux had called him to advise the funds had been transferred. The defendant intended to only pay the second plaintiff $22,400, with the balance to be paid 584 directly by the defendant to Scott Dickason.
The defendant recalled that he then called the first plaintiff and words to the effect of the following were exchanged before the first plaintiff terminated the call:
Defendant: Patrick has hold me that the money has been paid to you in error. You are not entitled to that money, as you have not paid trades, I still do not have a certificate of occupancy and the house is incomplete. You need to pay it back. 585 First Plaintiff: Bad luck. I’m not going to.
581 T119.24-26. 582 T120.26-36. 583 The first witness statement of the defendant Tab 8 Exhibit 1 [122]. 584 The first witness statement of the defendant Tab 8 Exhibit 1 [123]. 585 The first witness statement of the defendant Tab 8 Exhibit 1 [124].
Defendant: Patrick has told me that the money has been paid to you in error. You are not entitled to that money, as you have not paid trades, I still do not have a certificate of occupancy and the house is incomplete.
First Plaintiff: No way, I have bills to pay, I need it.
Defendant: You’re not entitled to that money give it to me to pay the trades – I don’t have a certificate of occupancy I haven’t seen you for ages. You better pay that money back or else. 586 First Plaintiff: Okay, I’ll do it.
The first plaintiff then proceeded to draw a cheque for the defendant for $28,000. The defendant banked the cheque and deposited it into a Commonwealth Bank account in 587 his name. The defendant maintained that the $28,000 was an approximate refund of 588 the payment the second plaintiff had received in error from Westpac Bank.
The defendant denied that he had paid the second plaintiff $22,400 to go towards 589 unpaid expenses or that such an amount had been paid on 28 November 2014. Instead, the defendant stated that a payment of $22,400 was made to the second 590 plaintiff on 12 December 2014 and $7,200 was paid to Scott Dickason.
The defendant stated that on or around 6 December 2014, he and the first plaintiff attended the premises of CRT Building Products (CRT) to discuss the issue of non- 591 payment of CRT’s invoice.
The defendant stated he had to give assurances to CRT employees that upon issue of the CRT roof frame certificate and the subsequent issue of the certificate of occupancy, he would release the final progress payment to the second plaintiff. CRT agreed to issue the roof frame certificate on this basis and on a further proviso that the second plaintiff would promise in writing to use the monies he would be paid from the final 592 progress payment to pay the overdue account with CRT.
An email dated 5 December 2014 from an email address of the second plaintiff was 593 annexed to the first witness statement of the defendant. That email read:
To whom it may concern,
I John Cobanov of ASHELL HOMES Pty Ltd, hereby certify that upon successful issue of the Certificate of Occupancy for 1/104 Casey ACT 2913, I am due a practical completion progress payment from the owner. Upon receipt of this payment, I hereby agree to make a payment to CRT in order to rectify the issue with the account: ASHELL
586 The first witness statement of the defendant Tab 8 Exhibit 1 [126]. 587 The first witness statement of the defendant Tab 8 Exhibit 1 [128]. 588 The first witness statement of the defendant Tab 8 Exhibit 1 [132]. 589 The first witness statement of the defendant Tab 8 Exhibit 1 [129]. 590 The first witness statement of the defendant Tab 8 Exhibit 1 [130]. 591 The first witness statement of the defendant Tab 8 Exhibit 1 [133]. 592 The first witness statement of the defendant Tab 8 Exhibit 1 [134]. 593 Tab 60 Exhibit 1. HOMES. To attain the Certificate of Occupancy, CRT needs to issue the relevant clearances/certificates for the roof frame and truss work undertaken at 1/104 Casey ACT 2913.
The defendant admitted that he contacted the first plaintiff to indicate the sewerage was 594 blocked but denied that he had any conversation about being in the house. The defendant received the certificate of occupancy on 12 January 2015. The defendant 595 submitted that he did not move into the house with his wife until early February 2015.
The defendant stated that shortly after moving into the house, he had called the first plaintiff regarding defects in the construction. The first plaintiff retorted with words to 596 the effect of “if you want me to fix them, I’ll need more money”.
In the first witness statement of the defendant, the defendant claimed he had a number of concerns over the second plaintiff’s workmanship and as a result, the George Pudja 597 report was obtained in the course of the litigation.
In the evidence in chief of the defendant, a document titled ‘Defendant’s/Counter Claimant’s Summary of Expert Defect Evidence – George Pudja’ was tendered through the defendant and became Exhibit 9 in the proceedings. Exhibit 9 was prepared on behalf of the defendant as a shorthand reference document to the George Pudja report.
The defendant was cross examined on his compliance with the HIA Contract. The defendant admitted he could not recall where he had followed the defects liability 598 regime as stipulated in Clause 23 of the HIA Contract.
The defendant was also cross examined on the release of the final progress payment by Westpac Bank. The defendant maintained that the money was released to the 599 second plaintiff in error. The defendant was taken to a document that was on the letter header of Tiffen & Co dated 28 November 2014 and signed on behalf of Patrick Bouquiaux.
This letter dated 28 November 2014 became Exhibit 12 in the proceedings. It was addressed to Westpac Bank and the contents of the letter said, “please find attached progress payment invoice for $28,434 for the practical completion stage authorised by the client for payment to the builder ASAP”. Attached to the letter was the invoice dated 28 November 2014 for the final progress payment and it was signed by the defendant.
The defendant gave evidence that he was advised by Patrick Bouquiaux that the funds had been released in error. The defendant stated that the final progress payment was 600 to be released to himself directly in order to facilitate the payment for subcontractors.
The defendant confirmed that he had signed the invoice as approved and provided it to Patrick Bouquiaux so that Westpac Bank would release the funds. The defendant 601 denied that the error was his own.
594 The first witness statement of the defendant Tab 8 Exhibit 1 [138]. 595 The first witness statement of the defendant Tab 8 Exhibit 1 [135]-[136]. 596 The first witness statement of the defendant Tab 8 Exhibit 1 [139]. 597 The first witness statement of the defendant Tab 8 Exhibit 1 [145]. 598 T292.13-14. 599 T242.5-6. 600 T244.24-30. 601 T245.5-21. Consideration
The plaintiffs conceded that the second plaintiff failed to complete the works. This failure was a result of the defendant preventing the second plaintiff from performing any further work from 24 December 2014, as a result of the defendant taking early possession of the site on this date without the knowledge or consent of the second 602 plaintiff.
The plaintiffs submitted that the defendant took possession prior to the second plaintiff issuing a notice of practical completion and that the defendant did not follow the defects rectification procedure that is established in Clause 23 of the HIA Contract. Pursuant to Clause 14 of the HIA Contract, the defendant was not entitled to take exclusive possession of the property until completion of the contract. The plaintiffs submitted that as the defendant had breached the HIA Contract in this way, the second plaintiff had 603 been denied the opportunity and ability to complete the construction works.
In relation to the HIA Contract itself, the plaintiffs submitted that neither party insisted upon compliance with the HIA Contract and that the court should find that it was not 604 intended to strictly govern the relationship between the parties.
The plaintiffs submitted that if the HIA Contract had truly governed the relationship between the parties, then the defendant would have refused to authorise the release of progress payments prior to the relevant work being completed. The actions of the defendant in causing progress payments to be released prior to the relevant stage being reached is evidence that neither party gave any real regard to their rights under 605 the HIA Contract. This does in my view regrettably appear to be the case.
It was submitted that despite there being no issuing of a notice of practical completion by the second plaintiff nor any orderly ending to the works, the defendant prematurely caused the final progress claim for practical completion to be paid. The plaintiffs noted that the invoice, which was submitted by the plaintiffs to have been prepared by the defendant, bore the defendant’s signature authorising payment.
The plaintiffs also noted that Patrick Bouquiaux could have been called by the defendant to give evidence as to how the final progress payment was to be released 606 by Westpac Bank to the second plaintiff in error. I note that Patrick Bouquiaux was not called to give evidence. In my view, the drawing or otherwise of this inference does not assist to any significant degree in the resolution of this matter.
The defendant referred to portions of the HIA Contract (which is not controversial in 607 that the terms are the same on both parties versions of the HIA Contract). The defendant made reference to Clause 3 of the HIA Contract which relevantly reads:
The building works
602 Plaintiffs’ submissions in reply 16 March 2020 [44]. 603 Plaintiffs’ submissions in reply 16 March 2020 [45]. 604 Plaintiffs’ submissions in chief 4 December 2019 [34]. 605 Plaintiffs’ submissions in chief 4 December 2019 [34]. 606 Plaintiffs’ submissions in chief 4 December 2019 [66]. 607 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [139]-[144]. …
The defendant noted that ‘the contract’ is defined in Clause 2 to mean the agreement set out in the conditions of the contract (including Attachments A-D) and in the signed plans and specifications attached to the contract, signed by both the builder and the owner. ‘Building works’ is defined in Clause 2 as the work to be done on the site by the builder pursuant to the contract.
Clause 2 also provides the following definition of ‘practical completion’:
Practical completion means that the building works have reached the stage where the builder certifies that they have been completed in accordance with the contract, except for minor omissions and, where applicable, has done all that the builder is required to do under the contract to enable a certificate of occupancy to be obtained.
Practical completion
When the building works have reached the stage of practical completion, the builder must give the owner a notice of practical completion and the final progress claim.
Within 5 days, the owner and the builder must meet together to inspect the building works. The owner must give the builder a written and signed list of any work required by the contract which the owner claims is defective or unfinished. If the owner fails to do so within 5 days, the owner must immediately pay the amount of the final progress claim.
The builder must promptly rectify the defective or unfinished work in accordance with the contract.
Handing over the keys
When the owner pays the final progress payment, the builder must hand any keys for the building works to the owner.
Possession without consent
Damages for late completion of building works
Maintenance services period
Within 65 days after the date of practical completion, the owner must provide the builder with a written list of the claimed defects if any, in the building works. The builder must within 15 days after the expiry of the 65 day period rectify the defects resulting from work or materials not being in accordance with the contract.
Item 13, which is the detailing of the progress payments, was extracted by the defendant. The works required to be performed to reach a certain progress payment is part of the HIA Contract, whereas the first plaintiff wrote in the quantum for each progress payment:
Deposit on signing of contract (should not exceed $10,000)
5% $10,000
Footings poured. Stumps, piers or columns complete. Bearers and joists complete, based brickwork complete. Internal and external drainage complete. Internal and external drainage complete. Electrical, gas, and plumbing rough in below the floor complete. Floor slab poured.
10% $48,425
Wall frame complete and braced. Roof frame complete and braced. Fascia installed. Windows installed. All structural supports installed. Wall framing complete.
15% $57,638
All frames straightened. Windows nil off. Electrical, gas and plumbing rough in complete. Bath installed. Front and back door complete with locks. Eaves, barge, external wall cladding and roof covering is fixed.
35% $134,478
All internal architraves, skirtings, doors, cupboards and detailed joinery installed. Plasterboard finished, sanded and cornices fixed. Exterior downpipes fitted and penetrations complete. Decks and landings complete.
15% $57,637
All ceramic tiling installed. Prime cost items installed. Interior and exterior painting completed.
15% $57,638
$
Practical completion:
All interior fit-off items installed including door furniture, robe rails, bathroom accessories. Electrical, plumbing and gas fit-off installed. House cleaned internally and externally. Site cleaned and all excess items removed from site.
5% $28,434
TOTAL 100% $384,250
The defendant relied upon the evidence contained within the George Pudja report and noted that this evidence was unchallenged by the plaintiffs. The qualifications, experience or ability of George Pudja to give the expert opinion was not scrutinised by 608 the plaintiffs.
The George Pudja report listed 24 items of works which the second plaintiff was required to complete pursuant to the HIA Contract which were defective. It was submitted that defective works are deemed incomplete works: Maples Winterview Pty Ltd v Liu & Anor [2015] ACTSC 58 at [80]-[84] (Maples Winterview).
The defendant referred to the evidence that the first plaintiff gave under cross examination where he confirmed he performed the works which the George Pudja report said were defective. The defendant also referred to the first plaintiff’s evidence that he had received a copy of the George Pudja report but did not respond to it.
The defendant also referred to Exhibit 9, which was the summary table of the George Pudja report prepared on behalf of the defendant. The centre column of the summary table was titled ‘source of obligation’ and specified where in the HIA Contract the obligation was drawn from, as well as the consequential provisions in ss 42 and 88 Building Act 2004 (ACT) (Building Act).
Item 23 of the George Pudja report noted that the second plaintiff failed to install hydronic heating in the slab. The defendant submitted that if the court was to accept that the inclusions list was duly incorporated in the HIA Contract, it must follow that the second plaintiff failed to complete this particular work. I am not satisfied that this inclusions list that contemplated hydronic heating was duly incorporated into the HIA Contract.
The defendant also referred to Item 24 in the George Pudja Report which highlighted that the stone feature wall at the front of the residence was not built, despite being shown in original plans dated 4 June 2013. The defendant submitted that as Clause 3 of the HIA Contract provided that the builder must completed the works in, amongst other things, the signed approved plans, the second plaintiff was obliged to complete 609 this item. The defendant noted that the second plaintiff failed to complete this item. I note that this was not completed.
In submissions in reply, the defendant noted that not even in the face of the litigation nor of the George Pudja report had the plaintiffs offered to fix the defects with the property. The defendant submitted that if the defendant had not taken possession of the property, on the balance of probabilities the defendant would still be waiting for practical completion, a certificate of occupation, and for the defects to be fixed.
Again the evidence is in an unsatisfactory state in this regard and I am not satisfied on the balance of probabilities of the defendant’s claim.
608 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [145]. 609 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [145]-[150]. Did the second plaintiff breach the HIA Contract, and his duty of care (owed to the defendant) (breaches) by failing to build the house in a proper and skilful way, with proper materials and with reasonable promptness?
Evidence
Defendant Submissions
Breach
The defendant again relied upon the evidence of the first plaintiff in cross examination that he performed the works that the George Pudja report stated were defective. The defendant submitted that the second plaintiff was obliged to perform those works pursuant to the HIA Contract and the logical conclusion from that was that the second 610 plaintiff breached the contract as he did not complete the works.
The defendant referred to Clause 12 of the HIA Contract which provides that the builder must give the owner a written claim for each progress payment on completion of each stage set out in Item 12 of Attachment A, which is the various progress payment stages 611 and corresponding percentages of the total build price extrapolated above.
Further reference was made to the decision of Mossop J in Maples Winterview at [84] where it was stated that in interpreting the HIA Contract in that matter, the meaning of completion of each stage is a condition precedent to a builder’s entitlement to make progress payment claims.
The defendant claimed that following this observation made by Mossop J in Maples Winterview, the second plaintiff was not entitled to make a claim for a progress payment until all the matters for that stage were completed, save for minor defects. The defendant submitted that if the court was to conclude the second plaintiff failed to attend to complete a stage, it must follow that the second plaintiff was not entitled to make the claim or any subsequent claims. Further, any payments ought to be refunded or an adjustment be made to take into account the cost of rectifying the defect relevant to the 612 completion of each progress stage.
It was noted that the defendant’s version of the HIA Contract encompassed the 180 days completion time. If the court was to accept this version of the HIA Contract, it would follow that the second plaintiff was required to achieve practical completion by approximately January or February 2014 – to March or April 2014, depending on when 613 the court determined construction commenced.
The defendant submitted that as the George Pudja report highlighted that the second plaintiff had not completed the construction works in accordance with the HIA Contract, including the inclusions list. Therefore, the second plaintiff was well and truly outside of the 180 day obligation.
610 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [151]. 611 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [152]. 612 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [155]. 613 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [156]-[158].
(1) By force of this section,… every contract to carry out residential building work to which the builder is a party is taken to contain a warranty under this section.
(2) The builder warrants the following in relation to residential building work:
…
(d) if the work has not been completed , and the contract does not state a date by which, or a period within which, the work is to be completed – that the work will be carried out with reasonable promptness.
(1) Building work must not be carried out except in accordance with the following requirements:
(a) the materials used in the building work must comply with the standards under the building code for the materials in buildings of the kind being built or altered;
(b) the way the materials are used in the building work must comply with their acceptable use under the building code for buildings of the kind being built or altered;
(c) the building work must be carried out in a proper and skilful way.
The defendant submitted that by virtue of ss 88(1), 88(2) and 42 of the Building Act, it was an implied term of the HIA Contract that the second plaintiff was to carry out the construction works in a proper and skilful way, in accordance with the approved plans, using good and proper materials and with reasonable promptness (if no time is 614 specified).
It was submitted that there were 24 defects in the construction works that the second plaintiff performed that was in breach of the statutory warranties implied into the building contract. The second plaintiff thereby breached the HIA Contract and the 615 Building Act.
Negligence
The defendant referenced the definition of negligence contained within s 40 of the Civil Law (Wrongs) Act 2002 (ACT) (Civil Law (Wrongs) Act), meaning the failure to exercise reasonable care and skill.
The defendant also drew attention to the standard of care that is set out within s 42 of the Civil Law (Wrongs) Act:
For deciding whether a person (namely here, the second plaintiff) was negligent, the standard of care required by the second plaintiff is that of a reasonable person in the second plaintiff’s position who was in possession of all the information that the second plaintiff either had, or ought reasonably to have had, at the time of the incident out of which the harm arose.
614 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [165], [167]. 615 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [168]. 616 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [172]-[175].
Consideration
The plaintiffs submitted that the second plaintiff did not breach the HIA Contract nor his duty of care owed to the defendant. The defendant denied the second plaintiff the opportunity to complete the works by effectively ending the contract prior to the date of practical completion. It is not established that the second plaintiff breached the HIA Contract or his duty of care with respect to the construction when the defendant unilaterally ended the contract.
The defendant did not issue the second plaintiff with a dispute notice nor present a defect list to the second plaintiff, both of which are contemplated by the HIA Contract. By denying the second plaintiff the opportunity to finish the works, the defendant denied the second plaintiff the opportunity to fulfil the terms of the HIA Contract and his duty of care.
In relation to s 88(2)(d) of the Building Act as to reasonable promptness, I am not satisfied that the 180 day clause formed part of the HIA Contract. This is in light of the defendant’s concession that he had added 180 days after execution. There was not in my view sufficient evidence for the court to determine reasonableness or otherwise as to the time taken to carry out the building works.
The defendant urged the court to reject the suggestion that the defendant was not entitled to damages because he took possession of the property before practical 618 completion. I am not persuaded that an entitlement to damages has been established. I am not persuaded s 42 has been breached.
It was submitted that there was no evidence that the plaintiffs attempted to rectify the defects from late November 2014, not even after receipt of the George Pudja report 619 which explicitly identified defects.
The defendant submitted that it was of no moment that the defendant did not follow the regimes laid out in the HIA Contract as to disputes and the rectification of defects. It was asserted that the counterclaim and the George Pudja report amounted to such 620 notices. I am not persuaded on the evidence to this view.
If the second plaintiff committed part or all of the Breaches, did those Breaches cause the defendant to suffer the loss claimed (including the amounts the defendant paid to contractors as set out at paragraph 63 of the first/ second witness statement of the defendant)?
Evidence
John Cobanov
617 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [175]. 618 Defendant submissions in reply on the counterclaim 9 April 2020 [26]. 619 Defendant submissions in reply on the counterclaim 9 April 2020 [29]. 620 Defendant submissions in reply on the counterclaim 9 April 2020 [30].
Kiki Josifovski
In the second witness statement of the defendant, the exhibit Schedule B sets out the subcontractors that the defendant paid directly. Payment was made to subcontractors either prior to the certificate of occupancy being issued or thereafter tin order to rectify 621 defects and finalise the incomplete works.
In reference to the George Pudja report, the defendant caused the following works to be rectified either by himself or with further subcontractors:
Item 1: sealing works on the roof – which was undertaken directly by the defendant.
Item 16: draining works – the defendant engaged a plumber to undertake 622 these works.
Plumbing
In relation to the conversation between the first plaintiff and the defendant on 24 December 2014 in relation to the sewerage system, the defendant stated that the ACT Government Environment and Planning authority had inspected the plumbing on the 623 property on that date. A copy of the inspection report was exhibited to the first witness 624 statement of the defendant and formed part of Exhibit 1. The report stated that the plumbing inspection had failed as it was unsatisfactory, and the sewer drain was blocked.
After the failed inspection, the defendant called the first plaintiff and said words to the effect of “you need to send your plumbers to fix this”. The first plaintiff responded saying “it’s now Xmas and I’m not going to”. The defendant then engaged his own plumber to facilitate the provision of the final plumbing certificate as he did not have faith in the 625 second plaintiff.
The defendant paid Nathan Jarvie, another plumber, $4,650 in total on 1 January 2015 626 and 27 January 2015 which formed part of Schedule B.
Tiling
621 The first witness statement of the defendant Tab 8 Exhibit 1 [144]. 622 The first witness statement of the defendant Tab 8 Exhibit 1 [147]. 623 The first witness statement of the defendant Tab 8 Exhibit 1 [148]. 624 Tab 64 Exhibit 1. 625 The first witness statement of the defendant Tab 8 Exhibit 1 [149]. 626 The first witness statement of the defendant Tab 8 Exhibit 1 [150]. 627 The first witness statement of the defendant Tab 8 Exhibit 1 [151]-[152].
Progressively from 2015 onwards, the defendant engaged tiling contractors to undertake the following rectification works:
Replacing the ensuite tiles that fell and were broken;
Removing unstable tiles in the ensuite and main bathroom and resecuring them;
Re-grouting two of the ensuite walls and re-grouting parts of the main bathroom where tiles were removed and reattached;
Reattaching tiles and regrouting the porch and alfresco area where tiles had 628 become detached.
The defendant noted that Schedule B did not set out all of the costs incurred for 629 defective tiling, only $1,500 incurred to replace the tiles that had become detached.
Roofing
The defendant asserted that water leakage throughout the property had been a continuing issue. The defendant first noticed substantial water ingress in 2016 or 2017 630 when water began gushing into the theatre room whilst it was raining.
The defendant investigated the roof above and discovered there were multiple offcuts joined to form the corner of the roof instead of one piece. The offcuts were bound together with silicone. The defendant organised with his father Ratko Josifovski to apply a second layer of silicone to attempt to rectify the issue. The defendant stated that the second layer of silicone improved the situation but did not completely rectify the defect. 631 Schedule B did not encompass costs associated with the application of silicone.
Brick works
Incomplete works
The defendant made reference to the second plaintiff’s failure to install hydronic heating into the slab, which was an inclusion in the inclusions list. The defendant maintained that by the time he became aware that the hydronic heating had not been installed, the 633 works were too far advanced to facilitate the installation.
The defendant also asserted that the second plaintiff had failed to install the feature rock wall on the western face of the dwelling, which was specified in the inclusions list 634 and the original plans dated 4 June 2013.
628 The first witness statement of the defendant Tab 8 Exhibit 1 [152]. 629 The first witness statement of the defendant Tab 8 Exhibit 1 [153]. 630 The first witness statement of the defendant Tab 8 Exhibit 1 [154]-[155]. 631 The first witness statement of the defendant Tab 8 Exhibit 1 [155], [157]. 632 The first witness statement of the defendant Tab 8 Exhibit 1 [158]. 633 The first witness statement of the defendant Tab 8 Exhibit 1 [161]. 634 The first witness statement of the defendant Tab 8 Exhibit 1 [162].
The second plaintiff also failed to complete the sub-floor cellar area. The defendant claimed that the area was left without a door, with a bare dirt floor and with exposed brickwork footings as the walls. This had been contrary to what the defendant had 635 discussed with the first plaintiff about the sub-floor area.
To rectify and complete the sub-floor cellar area, the defendant engaged subcontractors to pour a concrete floor, render and seal the walls, install a vent to 636 attempt to reduce moisture, and install a door.
The defendant claimed that the second plaintiff failed to make adjustments or deductions to the HIA Contract sum for the items that the second plaintiff did not deliver. 637 The defendant stated that he had paid the HIA Contract in full.
The defendant stated that the second plaintiff failed to make a deduction to the HIA Contract sum for works that were the subject of allowances in the inclusions list where the items cost less than the allowances. This was dependent on the inclusions list being 638 found to have formed part of the HIA Contract.
Schedule B was exhibited to the first witness statement of the defendant set out various payments to subcontractors and suppliers. It detailed the date an amount was paid, the quantum and the type of work/ goods that were supplied. In total, it set out that the 639 defendant had paid various subcontractors and suppliers $88,661.20.
In examination in chief, the defendant was directed to Exhibit 9 and asked to confirm what items identified in the George Pudja report he had caused to be rectified prior to 640 selling the property.
The defendant gave the following evidence in respect of items in the George Pudja report and by reference to Exhibit 9:
The defendant had caused Item 4– the roof screws that had been incorrectly fitted in some areas of the home – to be rectified before he sold the 641 property.
The defendant had caused Item 5– the installation of the Foxtel cables that had resulted in gaps to the roof flashing – to be rectified before he sold the property.
The defendant had caused Item 8 – the excessive gaps and a lack of head flashing of the entry door to be partially rectified before he sold the property.
The defendant had caused Item 13 – the excessive cracking in the exterior rendered wall and the lack of articulation joints in the brickwork to be rectified before he sold the property.
The defendant had caused Item 14 – the location of the subfloor storage 642 area – to be rectified ‘in a way’ before he sold the property.
635 The first witness statement of the defendant Tab 8 Exhibit 1 [163]-[164]. 636 The first witness statement of the defendant Tab 8 Exhibit 1 [166]. 637 The first witness statement of the defendant Tab 8 Exhibit 1 [169]. 638 The first witness statement of the defendant Tab 8 Exhibit 1 [170]. 639 Tab 71 Exhibit 1. 640 T209.8-10. 641 T209.29-30. 642 T209.32-33. 6. The defendant had caused Item 19 – the defective paint work on all interior and exterior doors – to be rectified before he sold the property.
The defendant had caused Item 20 – the upstairs ensuite leaks and inadequate falls on the flooring – to be partially rectified before he sold the 643 property.
In the absence of the defendant, counsel for the plaintiffs objected to the court receiving Exhibit 9 as the evidence given by the defendant in examination in chief did not identify what rectification work was actually done to meet particular items. It would raise a question of whether the cost incurred in rectification was reasonable which was difficult to answer in circumstances where the defendant said some items were fixed and some 644 items were only partially remedied. It was submitted that the court did not know how ‘partial’ items were remedied and how much a partial rectification cost, nor what was 645 meant by ‘in a way’ to describe Item 14.
Counsel for the defendant confirmed that Exhibit 9 was only sought to be admitted for the limited purpose for the sake of it being a summary of the George Pudja report and what the defendant said he repaired, not for the price he paid to cause any 646 rectifications.
Defendant Submissions
By reference to Reg. Glass Pty Ltd v Rivers Locking Systems Pty Ltd (1968) 120 CLR 516 at 523, the defendant set out that for the defendant to succeed in the counterclaim for a breach of the HIA Contract and the relevant provisions of the Building Act, the court would need to be satisfied on the balance of probabilities that the damages the defendant claimed were a consequence of the second plaintiff’s breach of the HIA 647 Contract.
The defendant submitted that whether the damages were caused by the breaches or as a consequence of the breaches was to be determined through the application of the ‘but for’ test: March v Stramare (E and M H) Pty Ltd (1991) 171 CLR 506 at 522. That is, whether on the balance of probabilities a particular harm would not have occurred absent the conduct of the party in breach.
s 45 of the Civil Law (Wrongs) Act sets out causation as to negligence in this jurisdiction s the following:
(1) A decision that negligence caused particular harm comprises the following elements:
(a) that the negligence was a necessary condition of the happening of the harm (‘factual causation’)
(b) that it is appropriate for the scope of the negligent person’s liability to extend to the harm so caused (the scope of liability).
643 T209.35-36. 644 T211.6-26. 645 T24.17-19. 646 T214.33-42. 647 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [176].
The defendant noted that the ‘but for’ test is to be utilised as the test for causation pursuant to the Civil Law (Wrongs) Act: Blundell v Leighton [2013] ACTCA 1 at [49].
The defendant submitted that where the first plaintiff conceded in cross examination that he had performed the works which were listed as defective in the George Pudja report, there was no question that the second plaintiff’s caused the losses claimed.
It was conceded that if the court found that the inclusions list was not incorporated as part of the HIA Contract, the negligence claim would not extend to the inclusion of 648 hydronic heating in the slab of the construction.
The defendant claimed that due to the various breaches by the second plaintiff, the defendant was forced to pay $89,572.07 to different subcontractors. The $89,572.07 was in addition to the progress payments made to the second plaintiff pursuant to the 649 HIA Contract.
It was submitted that schedule B of the first witness statement of the defendant established which invoices he had paid by reference to Commonwealth Bank statements. The defendant noted that this evidence was not challenged by the 650 plaintiffs.
The defendant noted that the unchallenged evidence from schedule B established that the defendant paid for the following defects identified in the George Pudja report and the summary of that report in Exhibit 9:
Items 1 and 16: parapet capping and plumbing/ drainage;
Item 4: roof screws (partially rectified);
Item 5: Foxtel cables;
Item 8: entry door excessive gaps (partially rectified);
Item 13: cracking on exterior wall;
Item 14: subfloor storage alteration (partially rectified);
Item 19: defective paint (partially rectified); and 651 8. Item 20: ensuite to the master bedroom leaks (partially rectified).
The defendant highlighted that the George Pudja report had concluded that the cost 652 the defendant incurred to rectify the defects was reasonable.
Consideration
648 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [179]. 649 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [180]. 650 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [181]. 651 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [182]. 652 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [183]. Was the second plaintiff entitled to be paid for each of the progress payments? Does the defendant’s authorisation of payment of each of the progress payments affect the defendant’s right to claim those payments back?
Evidence
Defendant Submissions
Relying on Maples Winterview, defendant submitted that the second plaintiff was not entitled to be paid for any stage it did not complete nor any later stages thereafter 653 pursuant to the HIA Contract. The defendant referred back to Exhibit 9 as containing the ‘source of obligation’ that corresponded with the George Pudja report conclusion that the second plaintiff did not properly complete any stage after the first stage associated with the first progress payment.
The defendant referred to the stages as specified in Item 13 of the HIA Contract, which is set out previously in the judgment at paragraph [698]. On the assumption that the inclusions list formed part of the HIA Contract, the George Pudja report opined that the second plaintiff failed to complete the second stage ‘floor slab complete’ by failing to install hydronic heating into the slab. The defendant submitted that on this basis, the second plaintiff was not entitled to issue a payment claim for the second progress 654 payment for the second stage, being an amount of $38,425.
The defendant also referred to the George Pudja report that concluded the installation of the windows was defective. The second plaintiff was required to install the windows in a proper and skilful way. It was submitted that the second plaintiff failed to complete the third stage of the HIA Contract being the ‘roof frame complete’ and was therefore 655 not entitled to be paid the $57,638 as the third progress payment.
It was submitted that the second plaintiff was not entitled to the final progress payment for practical completion. Reference was made to the George Pudja report to assert that the second plaintiff was not entitled to be paid any of the progress payments as the defects together and separately revealed that the second plaintiff had not completed 656 the final stage which disavowed the second plaintiff the entitlement to be paid for it.
The defendant asserted that the second plaintiff was not entitled to claim any progress payment beyond the payment made for completion of the first stage due to Maples Winterview. It was submitted that the second plaintiff ought to be ordered to repay all 657 progress payments it received save for the first progress payment.
As to whether the defendant’s authorisation of payment affected the right to claim the payments back, it was submitted that the plaintiffs had not expressly pleaded this nor had they conducted the case on the basis of such a defence. It was submitted that the plaintiffs were bound by the HIA Contract in that the second plaintiff was only
653 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [184]. 654 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [185]. 655 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [185]. 656 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [186]. 657 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [187]. contractually entitled to be paid a progress payment if the associated works were 658 completed in accordance with the HIA Contract itself.
Consideration
The second plaintiff was paid the progress payments as set out in the HIA Contract. The defendant authorised the payments. As stated previously, I am not satisfied that the inclusions list was part of the HIA Contract. Further, consistent with Maples Winterview, the second plaintiff was entitled to the progress payments.
Even if the inclusions list was part of the HIA Contract, the evidence is that the defendant signed the progress payment invoices. The defendant controlled the release of payments from one stage to the next.
The plaintiffs submitted that the progress payment invoices were referrable to a 2011 invoice that the defendant had sent to the plaintiffs in relation to the Phyllis Ashton Circuit project. The invoice was dated 17 June 2011 and the plaintiffs submitted that invoice bore a number of key similarities to the invoices purportedly issued by the 660 second plaintiff for progress payments.
The plaintiffs referred to the evidence of the first plaintiff that he did not have the technical nous to generate an invoice in a word processing program and the evidence of Elle Cobanov that she did not recognise the template that was used for the progress payment invoices. It was submitted that the available inference from this evidence was that the defendant had prepared the progress payment invoices himself, using a template he had from 2011. After drafting the invoice, printing it and signing it, the defendant would provide the invoice to Patrick Bouquiaux who would forward it to 661 Westpac Bank to facilitate the release of funds to the second plaintiff. Again the evidence in this regard is unsatisfactory.
As to the final eighth progress payment of the HIA Contract for $28,434, the plaintiffs submitted that the court ought not to accept that the funds were released by Westpac 662 Bank in error. The plaintiffs referred to Exhibit 12 which showed the defendant signed the invoice and that it was provided to Tiffen & Co to be forwarded to Westpac Bank.
The plaintiffs highlighted that the defendant had admitted he had signed the invoice for the final progress payment and the handwritten date immediately below the defendant’s signature was 28 November 2014. It was submitted that the court ought to infer that the final progress payment invoice was signed by the defendant and submitted for payment on 28 November 2014. This inference was supported by Exhibit 12 which showed that the invoice was then promptly sent to Westpac Bank with a cover letter saying the client had authorised payment. I am not satisfied on the evidence on the
658 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [188]. 659 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [189]. 660 Plaintiffs’ submissions in chief 4 December 2019 [59]. 661 Plaintiffs’ submissions in chief 4 December 2019 [63]. 662 Plaintiffs’ submissions in chief 4 December 2019 [64]. balance of probabilities that the funds for the final progress payment were released in error.
In reference to the hydronic heating system, the plaintiffs submitted that this alleged inclusion had not been raised as integer of the counterclaim until the defendant amended his pleadings in 2019. It was submitted that the evidence did not establish that the defendant had raised the absence of the hydronic heating with the second 663 plaintiff. I accept this submission on the evidence.
The plaintiffs submitted that the defendant was obliged under the HIA Contract to pay the contract sum subject to an adjustment to take into account the costs of rectification of any unremedied defects. It was submitted that a failure to complete a stage may have disentitled the second plaintiff from making a progress claim but the defendant was not relieved from his obligation to pay the contract sum. The plaintiffs reiterated that the defendant did not suffer a diminution in the sale price of the property and the defendant was not eligible to claim the cost of unrectified defects against the contract 664 sum nor the individual progress payments. On the evidence before me, I accept the submission of the plaintiffs on this issue in this regard.
The defendant asserted that even if the inclusions list was not incorporated, the plaintiffs could not then say the second plaintiff was entitled to the progress payments for the following reasons:
The George Pudja report concluded the works were defective;
The first plaintiff gave evidence that the second plaintiff performed the works that were the subject of the George Pudja report;
It was possible to determine which progress claim the defective items were attributable to by reference to the George Pudja report and the summary in Exhibit 9, even if the inclusions list was not part of the HIA 665 Contract;
The defendant submitted that the plaintiffs were incorrect in the characterisation of Maples Winterview in suggesting that the defendant must still pay the contract price, subject to an adjustment to take into account the costs of rectification of any 666 unremedied defects. In my view on the basis of Maples Winterview, the defendant must pay the contract price subject to adjustment, if called for.
Mossop J stated in Maples Winterview at [81]:
…although a builder may have failed to complete the requirements of a stage so as to become entitled to a progress payment that failure will not preclude payment of the overall contract price so long as the defects are ultimately remedied pursuant to clause 23 or, if they are not so remedied, subject to an adjustment to take into account the cost of rectification, or if that is not reasonable in the sense referred to in Bellgrove v Eldridge (1954) 90 CLR 613 at 618-619, the loss in value (see also Tabcorp Holdings Ltd v Bowen Investments Pty Ltd (2009) 236 CLR 272 at 300 [17]).
663 Plaintiffs’ submissions in reply 16 March 2020 [55]. 664 Plaintiffs’ submissions in reply 16 March 2020 [56]. 665 Defendant submissions in reply on the counterclaim 9 April 2020 [39]-[42]. 666 Defendant submissions in reply on the counterclaim 9 April 2020 [43].
Is the defendant entitled to compensation for losses caused by the Breaches, in circumstances where he sold the property on or about 24 July 2019?
Evidence
Kiki Josifovski
Marcus Hon
Marcus Hon prepared a valuation report (the Marcus Hon report) dated 20 November 2019 at the request of the plaintiffs. The Marcus Hon report had been obtained after the hearing of all of the evidence in the matter and the plaintiffs were granted leave to 668 obtain it solely for the specific purpose of addressing diminution of the sale price. At the further hearing on 16 June 2020, the plaintiffs formally tendered the Marcus Hon report and it became Exhibit 20 in the proceedings.
The Marcus Hon report noted that after reviewing the building inspection report, that report had concluded that there were no maintenance or defective items requiring attention. That is, the building report did not make reference to any defective/ sub standard works.
The Marcus Hon Report also opined that the property was offered for sale and purchased by the incoming owners without taking into consideration of the 24 rectification defects as identified in the George Pudja report. It was claimed that the sale price of property at $1,125,000 would have been adversely affected by the total sum of the rectifications, if potential buyers had been made aware of the unrepaired defects. It concluded that the sale price of the property being $1,125,000 was fair and reasonable and reflects the value of the subject property, not including any unrepaired defects that were not disclosed on the purchaser.
The defendant was given leave to obtain evidence in reply, if such a course of action 669 was necessary. No evidence in reply was obtained in respect of the Marcus Hon report.
Submissions
Defendant Submissions
667 T206.19-22. 668 T368.20-24 & T369.6-8. 669 T369.23-26. v Eldridge) which set out the award of damages is usually to order the cost to rectify the defective works, so long as this amount is necessary and reasonable in the 670 circumstances.
The defendant referred to the High Court’s ruling in Bellgrove v Eldridge at 620 that it is immaterial to such an award whether the owner actually uses the damages to demolish the house and re-erect it, if the relevant breach of contract related to a 671 fundamental error in the foundation of the house. Thus the unreasonableness will only be satisfied in exceptional circumstances and the test of necessity is an award of damages that achieves conformity with the plans and specifications: Tabcorp Holdings Ltd v Bowen Investments Pty Ltd [2009] HCA 8; 236 CLR 272 at [17] (Tabcorp).
The defendant noted that the George Pudja report concluded that the $221,740 or $224,665 or if the hydronic slab was included, $470,451. The defendant asserted that if the court found that the inclusions list was incorporated, it would follow that it was reasonable and necessary to order rectification on the basis that the defendant receives what he bargained for, that is hydronic heating in the slab and the $470,451 in 672 damages.
As to the claim for negligence, the defendant noted that damages are awarded to compensate the defendant for the losses, so the defendant is put in the position it would have been had the negligence not occurred: Haines v Bendall (1991) 172 CLR 60 at 63.
The defendant also referred to the New South Wales Court of Appeal case of Hyder Consulting (Australia) Pty Ltd v Wilhelmsen Agency Pty Ltd & Anor [2001] NSWCA 313 (Hyder Consulting) where it was held at [99]:
If the rectification work has not been carried out, then a theoretical reasonable cost must be found and, because damages must be assessed once and for all, must be awarded even thought the rectification work might not be carried out. (I have held that if it is found tha the rectification work will never be carried out, no damages should be awarded: see Central Coast Leagues Club Limited v Gosford City Council 9 June 1998 unreported). But if the rectification work has been carried out and the actual cost is known, that provides sound evidence of the reasonable cost and should ordinarily provide the basis for damages.
The defendant noted that in Central Coast Leagues Club Limited v Gosford City Council (Unreported, Supreme Court of New South Wales, Giles CJ, 9 June 1998) there was no evidence that the Leagues Club was to be sold. It was a case where the owners instead were not proposing to rectify and thus there was no loss. The defendant submitted that this was a decision of first instance and that the Judge was also apart of the Court of Appeal in Hyder Consulting. As a result, it submitted the court would not 673 follow Central Coast Leagues Club Limited.
The defendant cited the cases of Director of War Services Home v Harris (1986) QdR 275 at 278-279 (Harris) and Cesare v Deluxe Motors Pty Ltd (1996) 13 BCL 136 (Cesare) as cases where the owner had undertaken some rectification but did not attend to all defects prior to selling the properties. The defendant noted that in both
670 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [191]. 671 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [192]. 672 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [193]-[195]. 673 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [199]. cases the court had held that the reasonable cost of rectification could still be the 674 measure of the former owner’s losses.
It is true that in Bellgrove v Eldridge the High Court was not a case in which the building owner had sold the building before bringing the action but I am unable to see any reason why there should be a different measure of damages in such a case and nothing is said in Bellgrove v Eldridge to support any such distinction. When the builder, in breach of his contract, delivered to the building owner a building that did not conform to the specifications, the owner became entitled to recover damages according to the measure approved in Bellgrove v Eldridge. If the owner subsequently sold the building, or gave it away, to a third person, that would not affect his accrued right against the builder to damages according to the same measure. The fact that the building had been sold might be one of the circumstances that would have to be considered in relation to the question whether it would be reasonable to effect the remedial work, but assuming that it would be reasonable to do the work the owner would still be entitled to recover as damages the cost of remedying the defects or deviations from the contract (assuming of course that the contract price had been paid). In assessing thos damages it would not be relevant whether the owner was under a legal liability to remedy the defects, or whether he had made a profit or a loss on the sale of the building, for the builder has no concern with the details of any contract that the owner might make with a third party…
….
The owner of a defective building may decide to remedy the defects before he sells it so that he may obtain the highest possible price on the sale; he may sell subject to a condition that he will remedy the defects; or he may resolve to put the building in order after it has been sold because he feels morally although he is not legally, bound to do so. These matters are nothing to do with the builder, whose liability to pay damages has already accrued.
The defendant submitted that the court was bound not only by the High Court authority in Bellgrove v Eldridge, but also the decision of Harris bound the court as a decision of 675 an interstate appellate court.
In respect of the Marcus Hon report, the defendant submitted that it was of no utility 676 whatsoever. The defendant noted that many of the defects identified in the George Pudja report were the result of a detailed inspection of the internal and external parts of the property. Conversely, the Marcus Hon report noted that there had been an inspection of the exterior, and where possible the interior, but that no inspection of the 677 roof had been undertaken.
The defendant submitted that upon determination of liability of the second plaintiff and that the breaches caused the loss, the authorities provided that the court would be required to determine whether the costs claimed for rectification were reasonable. The
674 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [200]-[201]. 675 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [201]. 676 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [204]. 677 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [202]. defendant relied upon the George Pudja report to assert that the reasonable cost to 678 rectify were the amounts as set out in the report.
Consideration
In my view the defendant is not entitled to damages for the losses caused by the second plaintiff’s breaches as the defendant has sold the property. If the defects outlined in the George Pudja report were not disclosed to potential purchasers, then the defendant did not suffer a diminution of the sale price due to the defects. This is clear in my view from the Marcus Hon report.
There was no evidence to suggest that the George Pudja report was disclosed to the purchaser, notwithstanding the defendant had been granted leave to reply to the Marcus Hon report.
I am satisfied on the evidence that the value realised by the defendant on the sale of the property is the same as if the defects had been rectified. Consequently, the defendant failed to prove loss and the negligence claim fails. I note the plaintiffs conceded that the defendant would be entitled to nominal damages only for breach of 680 the HIA Contract.
The plaintiffs made reference to the judgment of Keane JA (as his Honour then was) in UI International Pty Ltd v Interworks Architects Pty Ltd [2007] QCA 402 at [55]-[75] (UI International). It was asserted that this matter was akin to UI International where the purpose of the building contract was to produce a marketable product. The measure of damages is the difference in value between what the property would have been worth had the contract been performed and what it was in fact worth. In UI International, 681 Keane JA had held that the damages were nil. I have formed the same view with respect to this case.
By reference to the decision of Kourakis CJ in Stone v Chappel [2017] SASCFC 72 at [55]-[75] (Stone v Chappel), the plaintiffs submitted that if it is not practically feasible for rectification work to be carried out, damages cannot be awarded in relation to that work. In Stone v Chappel, an award of rectification costs had to be weighed against the likelihood that such rectifications would take place, and the effect of those works on third parties. It was held by Kourakis CJ that rectification was unlikely and thus an 682 award of rectification costs was a not a reasonable course for the court to adopt. On the evidence in this case, I am persuaded to a similar course.
In the current matter, the defendant first entered into the contract to sell the property on 24 July 2019. The plaintiffs submitted that as such it was not practically feasible to rectify the 24 defects outlined in the George Pudja report in circumstances where the defendant now has no right to access the property. It was asserted that the defendant is not entitled to damages for rectification for the following reasons:
678 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [205]. 679 Defendant submissions in reply and in chief on the counterclaim 18 February 2020 [207]. 680 Plaintiffs’ submissions in reply 16 March 2020 [59]. 681 Plaintiffs’ submissions in reply 16 March 2020 [61]. 682 Plaintiffs’ submissions in reply 16 March 2020 [62]. 1. An award for damages is not reasonable in circumstances where ethe rectification is unlikely to occur; 683 2. The defendant did not incur a loss on the sale of the property.
I accept these submissions as they accord with my view of the evidence.
The incoming owners of the property succeeded the defendant’s rights to bring an action for breach of statutory warranty, pursuant to s 88(3) of the Building Act. That subsection explicitly establishes that each of the owner’s successors in title succeeds to the rights of the owner in relation to the statutory warranties. The plaintiffs claimed that as a result, from the date of transfer the defendant no longer had any rights to claim for breach of s 88 of the Building Act. The plaintiffs stated that any claim for breaches of s 88 relied upon by the defendant for unrectified defects had to fail for want 684 of standing. In my view there is force in this submission.
The rectification works carried out by the defendant prior to the sale of the property were undertaken and paid for by the defendant after he took possession of the property 685 and excluded the second plaintiff in breach of the HIA Contract.
The defendant submitted that the decision of UI International was not applicable in this matter for the following reasons from that case at [45]-[87]:
UI International was a decision in respect of an application to strike out certain parts of an unusually pleaded statement of claim. There had been three attempts at amending the statement of claim.
The case centred on a building dispute brought by a developer (who developed the land for residential, retail and office purposes) against, amongst others, the builder with whom it contracted to design and construct the building on the land;
After completion of the construction, the developer subdivided the land and sold some of the lots. The developer was then not able to unilaterally carry out any rectification works on the building as that course required the consent of persons who were not parties to the matter;
In the third proposed amended statement of claim, the developer alleged it was entitled to damages for the demolition and rebuilding of the development for $31,099,490. This claim for damages were based on the following three bases:
(a) The defects caused the developer to lose the contractual entitlement to achieve the development objective;
(b) The builder ought reasonably to have known that ownership of the development might be transferred by the developer to third parties so that defects would cause losses claimed by the developer in addition to losses suffered by the third parties as the new owners;
683 Plaintiffs’ submissions in reply 16 March 2020 [63]. 684 Plaintiffs’ submissions in reply 16 March 2020 [64]. 685 Plaintiffs’ submissions in reply 16 March 2020 [65]. (c) That the developer would undertake such steps as necessary to facilitate the building and rebuilding of the development, including by applying to the District Court for approval.
The developer could not rely on Bellgrove v Eldridge due to the way it had pleaded its statement of claim on the basis that the losses were based on the reduced marketability of the development resulting from the defects, as 686 opposed to the actual cost to rectify.
I do not accept that UI International is not applicable in this case.
The defendant also made reference to Stone v Chappel where at [55], Kourakis CJ had asserted that rectification damages are to be awarded unless there is ‘good reason’ to adopt another measure as rectification would be manifestly disproportionate to the attaining of the contractual benefit. His Honour then referred to 8 considerations derived from the authorities to determine whether good reason exists:
The degree of departure from the contractual stipulation;
The adverse effect of the departure on the functional utility, amenity and aesthetic appearance of the building;
The reasons, objectively ascertained and commonly known, for which the innocent party made the stipulation which was breached;
The practical feasibility of rectifying the work, including the effects on third parties of attempting to do so;
Whether or not the innocent party intends to carry out the rectification work;
The absolute cost of the rectification work and the disproportion between that cost and
(a) The value of the building and contract price;
(b) The diminution in commercial value of the building;
(c) The effect of the departure on the functional utility, amenity and aesthetic appearance of the building;
The nature of the wrongdoer’s fault for the defect; and
The public interest in reducing economic waste.
The defendant was critical of these considerations from Stone v Chappel and claimed that despite Kourakis CJ stating the considerations had been distilled from the authorities, there had not been a reference to an authority for each consideration, apart 687 from an earlier citing of Bellgrove v Eldridge in the preceding paragraph at [54].
The defendant took particular issue with consideration 5 and again asserted that there was no authority offered for this consideration nor was it explained in reference to 688 Bellgrove v Eldridge or any other appellate court decision in Australia.
686 Defendant submissions in reply on the counterclaim 9 April 2020 [45]. 687 Defendant submissions in reply on the counterclaim 9 April 2020 [51]. 688 Defendant submissions in reply on the counterclaim 9 April 2020 [52].
The defendant noted that reference had been made in Stone v Chappel to the House of Lords decision of Ruxley Electronics and Construction Ltd v Forsyth (1996) 1 AC 344 (Ruxley) and Hinton J in Stone v Chappel at [429] had noted that ‘in Ruxley all of their Lordships assumed that rectification damages as a remedy was subject to the 689 qualification of reasonableness.
Ruxley concerned a building dispute over a swimming pool where the diving area was to be 7 feet 6 inches deep. On completion the pool was suitable for diving but the designated area was only 5 feet deep. There was no adverse effect on the value of the property yet the estimated cost of rebuilding the pool to the specified depth in the contract was £21,560. The House of Lords determined that where the expenditure was out of all proportion to the benefit to be obtained, the appropriate measure of damages was not the cost of reinstatement but the diminution in the value of the work occasioned by the breach. Even if this would result in a nominal award only.
In Ruxley at 353-354, Lord Bridge observed the following:
The circumstances giving rise to the present appeal exemplify a situation which one might suppose to be of not infrequent occurrence. A landowner contracts for building works to be executed on his land. When the work is complete it serves the practical purpose for which it was required perfectly satisfactorily. But in some minor respect the finished work falls short of the contract specification. The difference in commercial value between the work as built and the work as specified is nil. But the owner can honestly say “this work does not please me as well as would that for which I expressly stipulated. It does not satisfy my personal preference. In terms of amenity, convenience or aesthetic satisfaction I have lost something”. Nevertheless the contractual defect could only be remedied by demolishing the work and starting again from scratch. The cost of doing so would be so great in proportion to any benefit it would confer on the owner that no reasonable owner would think of incurring it. What is the measure of the loss which the owner has sustained in these circumstances?...
… To hold in a case such as this that the measure of the build owner’s loss is the cost of reinstatement, however unreasonable it would be to incur that cost, seems to me to fly in the face of common sense.
The defendant submitted that the court was not bound by Ruxley nor by Stone v Chappel as the decisions were plainly wrong and in the latter, the Supreme Court of South Australia had failed to adopt the ratio from Bellgrove v Eldridge. It was submitted 690 that the court ought to adopt the course taken in Bellgrove v Eldridge.
In my view this required some further analysis.
Further Submissions on Bellgrove v Eldridge and Ruxley
Defendant Submissions on Bellgrove v Eldridge and Ruxley
689 Defendant submissions in reply on the counterclaim 9 April 2020 [54]. 690 Defendant submissions in reply on the counterclaim 9 April 2020 [55]-[57]. was inconsistent with Hyder Consulting, Harris and Cesare. Cordon Investments 691 overlooked and requalified the ruling principle in Bellgrove v Eldridge.
The defendant submitted that Cordon Investments was outside the ratio of Bellgrove v Eldridge and the court was obliged to follow the other authorities it had referenced in 692 place of Cordon Investments.
The defendant referred to the following factors in the current matter:
The first plaintiff admitted the second plaintiff performed the defective works as defined by the George Pudja report;
The defendant’s unchallenged evidence that he paid various third parties to finish some of the incomplete works in the sum of $88,661.20 (as referenced in the first witness statement of the defendant);
The defendant paid a plumber $4,650 to repair defective drainage work attributable to the second plaintiff;
If the court did not order the second plaintiff to pay for the reasonable costs of the defects, the second plaintiff will make a windfall through being paid regardless of whether the works were completed at all or to the requisite 693 standard.
The defendant submitted that if the court was inclined to the notion of common sense that was alluded to in Cordon Investments, that enquiry ought not be limited to the sale of the property. It should also include consideration of the second plaintiff’s breaches of the HIA Contract and the defendant’s payment to correct some of the defective 694 items.
Consideration
Both Bell v Eldridge and Ruxley are discussed in Tabcorp. The following propositions emerge from Tabcorp at [18]-[19]:
The House of Lords referred to passages in Bellgrove v Eldridge without dissent.
The High Court in Tabcorp referred to the result in Ruxley and the particular facts in that case. Ruxley itself is not inconsistent with the Australian line of authority.
Both Tabcorp and Bellgrove v Eldridge had been applied in Cordon Investments at [214]. It was noted that in Cordon Investments, Bathurst CJ on behalf of the court held at [229]-[230]:
While I accept that a possibility that rectification work will not be carried out does not preclude a claim for damages: Bellgrove v Eldridge, and that unreasonableness will only be established in exceptional circumstances: Tabcorp Holdings, in the present case the carrying out of the work would be unreasonable in the sense described by Giles JA in Westpoint Management Ltd v Chocolate Factory Apartments Ltd (McColl
691 Defendant’s response to plaintiffs’ note on Bellgrove and Ruxley 1 July 2020 [11]. 692 Defendant’s response to plaintiffs’ note on Bellgrove and Ruxley 1 July 2020 [11]. 693 Defendant’s response to plaintiffs’ note on Bellgrove and Ruxley 1 July 2020 [12]. 694 Defendant’s response to plaintiffs’ note on Bellgrove and Ruxley 1 July 2020 [14]. and Campbell JJA agreeing). His Honour dealt with the issue in the following manner (at [59]-[61]):
[59] Relevance of the plaintiff’s intention to carry out the rectification work to reasonableness is accepted in, for example, Chitty on Contracts… and Hudson’s Building and Engineering Contracts… It appears to have been accepted in De Cesare v Deluxe Motors Pty Ltd – indeed, sale of the building may have relevance through whether or not the rectification work will be carried out. If truly going to reasonableness, I do not think consideration of whether or not the plaintiff will carry out the rectification work is inconsistent with Bellgrove v Eldridge, since the regard to it is part of arriving at the plaintiff’s compensable loss. Once there is compensable loss, the court is not concerned with the plaintiff’s use of the compensation.
[60] But the plaintiff’s intention to carry out the rectification work, it seems to me, is not of significance in itself. The plaintiff may intend to carry out rectification work which is not necessary and reasonable, or may intend not to carry out rectification work which is necessary and reasonable. The significance will lie in why the plaintiff intends or does not intend to carry out the rectification work, for the light it sheds on whether the rectification is necessary and reasonable. Putting the same point not in terms of intention, but of whether or not the plaintiff will carry out the rectification work, whether the plaintiff will do so has significance for the same reason, and not through the bald question of whether or not the plaintiff will carry out the rectification work. That question is immaterial, see Bellgrove v Eldridge.
[61] So if supervening events mean that the rectification work can not be carried out, it can hardly be found that the rectification work is reasonable in order to achieve the contractual objective: achievement of the contractual objective is no longer relevant. If the sale of the property to a contended purchaser means that the plaintiff did not think and the purchaser does not think the rectification work needs to be carried out, it may well be found to be unreasonable to carry out the rectification work. An intention not to carry out the rectification work will not of itself make carrying out the work unreasonable, but it may be evidentiary of unreasonableness; if the reason for the intention is that the property is perfectly functional and aesthetically pleasing despite the non-complying work, for example, it may well be found that rectification is out of all proportion to achievement of the contractual objective or to the benefit to be thereby obtained.
The combination of the lack of intention to carry out the rectification work, the transfer of the property…and the absence of any evidence that the defects were affecting the use and occupation of the building or the common property leads, in my opinion, to the conclusion that it would be unreasonable to carry out the work and that damages for the cost of rectification should therefore not be awarded.
Conclusion on the Defendant’s Counterclaim
In the defence to amended statement of claim and counterclaim, the defendant sought the following relief: 1. damages and or compensation for breach of the HIA Contract including rectification costs;
damages and or compensation for negligence in undertaking the construction works; and
damages and or compensation for contravening s 42 of the Building Act.
For the reasons outlined above, the counterclaim is not made out on the balance of probabilities and the defendant is not entitled to the relief sought.
Application for Interim Injunction
At the commencement of the hearing on 21 October 2019, counsel for the plaintiffs moved on an application in proceeding dated 17 October 2019. That application sought to restrain the defendant from disposing of, dealing with, or diminishing the proceeds from the sale of the property and was supported by an affidavit of the plaintiffs’ solicitor Gavin Mansfield affirmed on 17 October 2019 (the Gavin Mansfield affidavit).
The Gavin Mansfield affidavit detailed that he had received instructions from the first plaintiff on 10 October 2019 that the defendant had been observed moving out of the property. The plaintiffs’ solicitor proceeded to conduct Google searches to ascertain information as to the status of title of the property which indicated that the property had been sold on 11 July 2019 for $1,125,000.
Email correspondence between the plaintiffs’ solicitor and the defendant’s solicitor was annexed to the Gavin Mansfield affidavit. In the first email dated 11 October 2019 sent by the plaintiffs’ solicitor to the defendant’s solicitor, the plaintiffs’ solicitor attached links to websites that indicated that the property had been sold. An urgent request was made for confirmation that the property had been sold, for disclosure of all discoverable documents in relation to the sale and for advice as to what the defendant had done or intended to do with the proceeds of sale.
On 15 October 2019, the plaintiffs’ solicitor wrote to the defendant’s solicitor requesting a substantive and full response to their first letter, noting that no response had been received. The plaintiff’s solicitor put the defendant’s solicitor on notice that if they were not provided with a substantive and full response including the provision of all discoverable documents by 16 October 2019, it was anticipated an urgent interlocutory application would be made pursuant to Parts 2.8 and 2.9 of the Court Procedure Rules 2006 (ACT).
On 16 October 2019, the defendant’s solicitor responded to the plaintiffs’ solicitor and attached a letter to their email in response. In the letter, the defendant’s solicitor denied that there was any basis for the plaintiffs’ request for information and documents. The letter confirmed that exchange of contracts for the sale of the property occurred on 24 July 2019 and that settlement occurred on 10 October 2019. A copy of the front page for sale was enclosed with the letter.
The Gavin Mansfield affidavit also annexed a copy of the defendant’s most recent balance Westpac Bank Investment Loan account, which was dated 23 January 2015. The loan was secured by a mortgage over the property and as at 23 January 2015, the balance was $563,674.
At the commencement of the hearing, counsel for the defendant opposed the granting of an interim injunction. Counsel for the defendant stated that “quite a bit of the money 695 has been dissipated to satisfy debts that the defendant owed”. Counsel for the plaintiffs noted that this was the first instance that he had been notified that monies had been dissipated and put the defendant on notice that the statement of claim may need 696 to be amended.
After a short adjournment, counsel for the plaintiffs’ notified that court that he had been informed by counsel for the defendant that only $126.11 remained from the sale of 697 $1,125,000. Counsel for the defendant confirmed that $126.11 was the amount 698 remaining. Counsel for the plaintiffs indicated that had this information been forthcoming prior to the hearing when it was requested, the application for an interim injunction would not have been prepared nor would have it been formally moved upon 699 at the outset of the hearing.
After hearing from the parties, I reserved the question of costs in relation to the 700 application for an interim injunction. As the true amount of the remaining funds was late breaking, it is appropriate to also set out the relevant evidence of the parties and witnesses as to how $126.11 came to be the remaining quantum.
Evidence
Kiki Josifovski
In cross examination, the defendant was questioned about the sale of the property. The defendant agreed that he had entered into a contract to sell the property on 24 July 701 2019 and that he did not tell the first plaintiff he had entered into that contract. The defendant gave evidence that he did not tell his solicitors in this matter that he had sold 702 the property on or about 24 July 2019.
The defendant recalled that that there had been a mediation in this matter on 8 August 2019. When asked whether he had informed his solicitors prior to the mediation that he had entered into a contract to sell the property, the defendant responded that he did 703 not recall.
The defendant was shown the Gavin Mansfield affidavit and referred to the annexure that contained the letter from the defendant’s solicitor to the plaintiffs’ solicitor. The defendant confirmed that he instructed his solicitor to send that letter and that he had refused to provide the information to the first plaintiff, despite the request to do so from 704 the plaintiffs’ solicitor.
The defendant confirmed that from the sale there was only $126.11 and that the 705 Westpac Loan was for $563,000. The defendant gave evidence that between
695 T12.23-25. 696 T14.33-35 & T14.39-45. 697 T21.41-43. 698 T22.19-20. 699 T23.1-6. 700 T24.43. 701 T317.9-12. 702 T317.38-39. 703 T317.41-42. 704 T318.38-45 & T319.1-2. 705 T319.7-8, 9-20. February 2015 and October 2019, he had increased the load on the property by roughly 706 $500,000. The defendant stated that the Westpac Loan was approximately $920,000 707 as at 10 October 2019.
As to the approximate remaining $205,000 after $920,000 is deducted from the sale amount of $1,125,000, the defendant gave evidence that the remaining funds from the sale were paid out to individuals that had loaned him money, being his father Ratko 708 Josifovski and his brother Goran Josifovski.
The defendant stated that it was his understanding that he gave both Ratko Josifovski and his father a mortgage over the property and that he had formally signed a document 709 confirming this arrangement.
It was put to the defendant that the mortgage arrangements with Ratko Josifovski and Goran Josifovski were made so that there would be no funds left over from the sale of the property and so the first plaintiff would not have to be paid anything from the 710 proceeds of the sale. The defendant denied this assertion.
Later in the cross examination, documents had been produced on behalf of the defendant that provided information about the sale of the property. The first page of the bundle was the first page of the contract for sale of the property. Also included in the bundle of documents on the second page was the settlement adjustment sheet for the sale of the property dated 10 October 2019. Under the heading ‘Bank Cheque Details’, a cheque for $913,681.30 was payable to Westpac Bank. The defendant confirmed that the $913,681.30 was owed to Westpac Bank solely for the loan for the property and that the amount owed to Westpac Bank had increased between 2015 and 2019 711 from $563,000 to $913,681.30.
Contained within the third page of the bundle was a handwritten document dated 24 April 2017. The defendant confirmed that the document was not written in English and 712 that it was written in Macedonian. The defendant confirmed that the document said that his father Ratko Josifovski would lend him $100,000 and that it was agreed that the defendant would return that amount upon the sale of his home, being the property 713 that is the subject of these proceedings. The defendant gave evidence that he received the $100,000 loan from Ratko Josifovski by a deposit in his bank account on 714 approximately 24 April 2017.
The defendant was referred to the final page of the bundle which was a handwritten letter dated 20 September 2018. It read as follows:
I Goran Josifovski have agreed to assist my brother Kiki Josifovski financially.
I have committed to give him a sum upto (sic) $75,000 which must be repaid within 14 days upon sale of his home (being [address of the property]).
706 T319.45-46 & T320.1-2. 707 T320.15-16. 708 T321.25-30. 709 T321.39-41. 710 T322.23-39. 711 T350.8-15. 712 T350.17-20. 713 T350.28-34. 714 T352.5-9. I accept his offer of security & guarantee against [address of the property].
The letter was signed by Goran Josifovski and Kiki Josifovski. The defendant gave evidence that Goran Josifovski wrote the document and that it was written in the 715 presence of the defendant on 20 September 2018. The defendant stated that Goran Josifovski did not give him the $75,000 on that occasion, instead that he received the 716 money over a period of time in varying amounts and methods of payment. The defendant claimed that he received some of the money in cash but that he could not recall how much cash in total Goran Josifovski had given him. The defendant also stated that Goran Josifovski would give him money by paying for things on the 717 defendant’s behalf or by transferring amounts to him.
The bundle of documents containing the contract for sale of the property, the settlement adjustment sheet, the handwritten document in Macedonian recording the loan of $100,000 from Ratko Josifovski to the defendant and the handwritten document recording the loan of up to $75,000 from Goran Josifovski to the defendant collectively 718 became Exhibit 19 in the proceedings.
Ratko Josifovski
Ratko Josifovski was referred to the third page of Exhibit 19, being the handwritten document in Macedonian dated 24 April 2017. Ratko Josifovski confirmed that he wrote 719 the document and that it recorded a loan of $100,000 to the defendant.
When asked why the $100,000 loan had been recorded in writing but not the $76,850 gift, Ratko Josifovski gave evidence that the funds were for different purposes and that 720 the $100,000 was to be repaid.
Goran Josifovski
Consideration
Orders
The orders of the court are:
On the plaintiffs’ claim, judgment be entered for the defendant.
On the defendant’s (as counterclaimant) claim, judgment be entered for the first and second plaintiff (as the first counter defendant and the second counter defendant).
715 T351.1-3. 716 T351.5-9. 717 T351.17-20, 42-44. 718 T352.19. 719 T363.20-27. 720 T262.36-40. 3. The defendant pay the plaintiffs’ costs of the application dated 17 October 2019 for an interim injunction.
Each party is to pay its own costs for the remainder of the proceedings.
If an alternative costs order is sought, parties have liberty to notify the court in writing that a party wishes to be heard further in relation to costs within 7 days of these reasons being published.
I certify that the preceding eight hundred and fifty-three [853] numbered paragraphs are a true copy of the Reasons for Judgment of her Honour Justice Loukas-Karlsson
Associate: Rhiannon McGlinn
Date: 4 June 2021
Cobanov
Josifovski
(1954) 90 CLR 613
(1981) 189 CLR 390
(1984) 155 CLR 242
(1956) 95 CLR 353
(1993) 179 CLR 101
(1996) 141 ALR 92
(1988) 166 CLR 18
(1991) 172 CLR 60
(1959) 101 CLR 298
(1991) 171 CLR 506
(1978) 18 ALR 1
(1968) 120 CLR 516
(1970) 119 CLR 397
(1985) 157 CLR 1
(1995) 182 CLR 544
(2009) 236 CLR 272