[2009] VCAT 1934
Victorian Civil and Administrative Tribunal
2009-09-18
Original judgment source is linked above.
Amendment to development, Section 173 Agreement, Modification of villa apartments to conventional apartments, Urban design response
Clara Mews Pty Ltd v Stonnington CC [2009] VCAT 1934
"Use and staged development of multi-unit residential development including multi storey townhouses, and apartments with associated dispensation from the requirements of Clause 52.06 (car parking) of the Stonnington Planning Scheme and associated landscaping generally in accordance with the endorsed plans and subject to the conditions listed below."
Amendment to permit to: Use and staged development of multi-unit residential development including multi storey townhouses, and apartments with associated dispensation from the requirements of Clause 52.06 (car parking) of the Stonnington Planning Scheme and associated landscaping.
Partly demolished recycling and refuse transfer station
Mr Stuart Morris QC, instructed by Mr Mark Naughton of Planning & Property Partners lawyers. They called evidence from:
Section 173 Agreement
Does the revised apartment building respond to its context?
Will the apartment building have a negative impact on the amenity experienced in the parkland?
.........from the public domain of Surrey Road, the proposed parkland or walkway to the south of the proposed apartment building, the apartment building's architectural form, its visual interest and its presence in the urban environment is comparable to and no less engaging, that the villa buildings
Does the amendment result in a development that is at odds with the prevailing neighbourhood character outside the site?
The important south elevation differs from that of the villa buildings due to the different layout of the apartments which are smaller but, like the villas, similar in layout. This results in a grid of windows, wall panels, balustrades and wall and slab edges which appear repetitious in elevational terms. As is nearly always the case, this building will be viewed obliquely rather than straight on, and mainly from the south-east.
As discussed above, the proposed landscaping in the adjacent part of the park will significantly screen broad vistas towards this building but, nonetheless, the building will be visible from the public domain.
The south elevation is articulated to read obliquely in three sectors, each made prominent by a projecting outer 'frame' comprising the eave, two vertical blades and the cantilevered floor slabs, all of which are finished in material and colours to accentuate them over the other structural elements of the building. These slab edges, the eave lines and the balustrades are angled slightly to reinforce the three sections of the building. This is an effective technique, when viewed obliquely, compared to the gaps between the three villa buildings. The three components are separated by a 'stack' of apartments which are recessed from the line of the adjacent facade elements. This reinforces the prominence of the three components.
Further details and articulation of the facade of the apartment tower building to soften its architectural expression to more appropriately reflect its park setting to the satisfaction of the Responsible Authority. This should include, but not be limited to, further architectural treatment, details and expressions to the podium element and the building form above the podium.
The development allowed by this permit and shown on the plans endorsed to accompany the permit shall not be amended for any reason without the consent of the Responsible Authority.
Prior to the completion of the development hereby approved detailed plans must be submitted to, approved and endorsed by the Responsible Authority showing a directional signage system in the basement car park and at ground level to all building entrances on the site to the satisfaction of the Responsible Authority.
Prior to the use commencing, the designs of any road works or traffic control devices required to be constructed or modified by the applicant as part of the development must have a Road Safety Audit undertaken by an independent Road Safety Auditor and the design response must be to the satisfaction of Council's Transport and Parking Unit.
Within 6 months of the commencement of the development hereby approved a detailed landscape plan generally in accordance with the Landscape Master Plans (prepared by Tract) submitted and date stamped by the Responsible Authority 24 May 2007 and 21 May 2008 must be submitted and approved by the Responsible Authority. The works shown on the endorsed landscape plan must be carried out and completed within 3 months of the completion of construction of any stage of development to the satisfaction of the Responsible Authority and then maintained to the satisfaction of the Responsible Authority. The Landscape Plan is to address the following:
The ongoing maintenance and responsibility of the garden and landscaped areas is to be undertaken by the body corporate to the satisfaction of the Responsible Authority.
The office uses at basement level 1 for townhouses 13 and 14 are to be used only in conjunction with, and ancillary to, the residential use of these tenancies.
All plant and equipment (including air-conditioning units) shall be located and screened so as to not be visible from any of the surrounding footpaths and shall be baffled so as to minimise the emission of unreasonable noise to the environment in accordance with Section 48A of the Environment Protection Act 1970 to the satisfaction of the Responsible Authority.
The emission of noise or any other emission to the environment derived from activities on the site must conform to standards contained in the appropriate State Environment Protection Policy or Policies.
All walls on or facing a boundary must be treated and cleaned to the satisfaction of the Responsible Authority prior to the approved development being occupied.
All privacy screening measures shown on the endorsed plans (including terraces and balconies) of the buildings must be fixed and permanent in line with Standard B22 of Clause 55.04-6 to the satisfaction of the Responsible Authority.
The specific details of the construction of the carriageway including the width, material type, grades, location and any other relevant detail must be submitted to Council's Infrastructure and Parking and Transport Units for approval.
Prior to completion of the development a Parking Management Plan is to be submitted to the satisfaction of Council and shall:
b) Detail the signing and line marking of parking spaces;
c) Detail where and how loading and unloading will occur;
d) Detail any access controls to the parking and waste management area, such as boom gates which shall take into account the required queue length required as per section 3.4 of AS 2890.1; and
Any poles, service pits or other structures/features on the footpath required to be relocated to facilitate the development must be done at the cost of the owner and subject to the relevant authority's consent.
Any obsolete vehicle crossover/s (including the crossovers to Surrey Road) except those directly associated with the reserve lot (the Park) must be removed in conjunction with the development and the footpath, kerb and channel reinstated all at the cost of the owner and to the satisfaction of the Responsible Authority.
Air extraction fans, air conditioning and all other plant and equipment installed on the subject buildings shall be baffled in accordance with the requirements of the Environment Protection Authority. Ventilation systems shall be designed and installed in accordance with relevant Australian Standards to the satisfaction of the Responsible Authority.
Any external lighting must be designed, baffled and located to suitably manage any adverse effects on adjoining land to the satisfaction of the Responsible Authority.
Prior to the commencement of any buildings and works allowed by this permit the owner and/or developer must submit a Construction Management Plan for that stage of development to the satisfaction of the Responsible Authority. The Construction Management Plan must include details on how the construction will be undertaken so it has minimal impact on the environment. Details to be provided in the Construction Management Plan will include, but are not be limited to:
The Construction Management Plan must be approved and endorsed by the Responsible Authority prior to commencing construction of that stage and all buildings and works must be carried out in accordance with the approved Construction Management Plan.
All wastes generated from demolition, site preparation and construction stages shall be disposed of appropriately in accordance with the requirements of the EPA to the satisfaction of the Responsible Authority.
The drainage of the site shall be to the requirements of the Responsible Authority and the discharge of water from the land affected by this permit shall be controlled around its limits to prevent any discharge onto any adjacent property or street other than by means of an underground pipe discharged to a point nominated to the satisfaction of the Responsible Authority.
An engineer is to be engaged to evaluate the public drains with regard to accommodating these drains within the development. A formal application for consent to build over Council drains or easements must be made to Council's Building Control Unit prior to the commencement of any such works. Upon completion of the new drainage works, the owner must at its cost take all steps necessary to have the redundant drainage easements removed.
New 2.0m wide drainage easements are to be created in favour of Council over the new easement drains, at the permit holders cost, to the satisfaction of Council. The owner shall pay all costs associated with the provision of the easement drains, outfall drain and creation of the drainage easements.
Prior to the commencement of any works as part of stage 2 of the development, with respect to the 600mm diameter drain located to the south of the site, the following conditions shall apply:
The plan must be generally in accordance with the Draft Waste Management Plan dated 7 November 2007 submitted to the Responsible Authority and must specify:
When approved the plan will be endorsed and will then form part of the permit. Waste collection from the development must be in accordance with the plan, to the satisfaction of the Responsible Authority.
provided it is acknowledged that the certificate of environmental audit referred to in paragraph (a) above or the statement of environmental audit referred to in paragraph (b) can be obtained separately for stage 1 and stage 2 of the development allowing for commencement of the relevant stage.
The Responsible Authority may extend the times referred to if a request is made in writing before the Permit expires or within the three (3) months afterwards.
No polluted and / or sediment laden runoff is to be discharged directly or indirectly into Melbourne Water's drains or watercourses.
The building/structure including footings, eaves etc must be set outside any easement or a minimum 1.5 metre laterally clear of the outside edge of the main drain, whichever is greater.
Prior to the Building Permit being issued, the depth of the footings must be adequate to satisfy the angle of repose relative to the drain as per Melbourne Water's specification. See attached Standard Drawing: 'Angle of Repose - Footing Design' for details.
Prior to the commencement of works separate application, direct to Melbourne Water, must be made for any new or modified storm water connection to Melbourne Water's drains or watercourses. Prior to accepting an application, evidence must be provided demonstrating that Council considers that it is not feasible to connect to the local drainage system.
Contact Asset Services on telephone 9235 1414 for Melbourne Water's connection requirements, including payment of appropriate fees.
Prior to any works being undertaken, the applicant must submit to VicTrack detailed engineering design drawings and specifications of the proposed works on or near VicTrack land for its approval. VicTrack's costs in assessing the proposed works shall be paid for by the applicant.
No excavation, filling or construction shall take place on or near the common boundary without first obtaining the approval of the rail operator's maintenance contractor, MainCo, by contacting Andrew Irving on 9619 7174 or 0419 523 856.
No works shall result in any subsidence of or direct any stormwater into or over VicTrack land.
No waste, soil or other materials resulting from the works are to be stored or deposited on VicTrack land.
Railway facing exterior walls on or near the common boundary with VicTrack land must have graffiti resistant surfaces.
[1] Pursuant to Section 87A of the Planning and Environment Act 1987
[2] Amendment C94 to the Stonnington Planning Scheme gazetted on 19 March 2009
[3] That may shortly accommodate a three storey building
[4] Interstice means an intervening space
[5] No footnotes or notations are nominated by the Tribunal
Clara Mews Pty Ltd
Stonnington CC [2009] VCAT 1934