[2018] NSWCATAP 186
NCAT Appeal Panel
2018-06-19
Ian Bailey AM
Original judgment source is linked above.
a) NiTma Project 1658S drawing 3 of 4 dated 13 October 2014 (the NiTmA Drawing), and
b) ADC Design Group Drawings S3A (FB4 Detail) and S2C for the Southern Wall (the ADC Drawings):
As to the scope of work: (The Rectification Works) (1) Excavate behind the western and southern retaining walls to the base of the concrete footings.
(2) Install compliant temporary shoring in the course of excavation and execution of work.
(3) Install waterproofing (tanking) to the internal face of the footing and retaining walls to the full height of the unexposed surface of the retaining walls.
(4) Install subsoil AG drainage behind the full length of retaining walls at the base of the excavation discharging at external ground level of the northern end of the western retaining wall and south-eastern corner of southern retaining wall, with connection to stormwater system in accordance with Clause 3.1.2.4 of the NCC.
(5) Install a compliant Kordon termite protection system at the granny flat level.
(6) Rectify all defects in the balcony balustrade to a workmanlike standard and in compliance with the NCC or BCA as appropriate.
(7) Back-fill behind all retaining walls and seal the external ground surface at the western wall as shown on the NiTmA Drawing.
(8) Install underfloor structural supports for the existing timber framed residence which comply with Clause P21.1 of the NCC.
(9) Clean up and remove all unused excavated material.
(10) Rectify all damage to the internal finishes caused by water damage in a proper and workmanlike manner including, replacing water damaged plasterboard and ceiling linings, replacing damage to internal trims and kitchen and laundry joinery and repaint all damaged painted surfaces and remove all debris and final clean.
As to the performance of the Rectification Work: (11) The Appellant is to pay for all costs associated with obtaining any relevant approval/s for the rectification work.
(12) The Respondent is to provide sufficient and appropriate access to the site to enable the Appellant to perform the Rectification Work.
(13) Before commencing work on site the Appellant is to provide copies of: (a) certificates of currency for insurance for: (i) Contract Works Insurance (ii) Public Liability Insurance (iii) Workers Compensation Insurance, and (b) Building and Trade licences for the Appellant and all subcontractors and trades undertaking the Rectification Work.
(14) The Rectification Work, the subject of subparagraphs 1 to 10, is to be inspected by Mark Brentnall Pty Ltd (certifier) at such times and in such manner as is necessary for the certifier to confirm in writing at the conclusion of the work that all work has been done in accordance with subparagraphs 1 to 10.
(15) The Appellant is to provide all certificates of compliance relating to the works performed under the contract and under this Order, required by the certifier to enable the certifier to confirm conformance of the work with the development approvals and other requirements applicable to that work and to issue an Occupancy Certificate.
(16) The costs of the certifier are to be paid by the Respondent.
(17) The performance of the Rectification Work is to commence within 30 days of the date of these Orders and shall be completed within 90 days of these Orders, subject to any agreement between the Appellant and the Respondent as to the amendment of the dates for either commencement or completion. Non-Compliance and Renewal of Proceedings
(18) Pursuant to Schedule 4 Clause 8 of the Civil and Administrative Tribunal Act, 2013 the Respondent has leave to renew the proceedings if these orders are not complied with by the Appellant.
(1) The Appellant is to file and serve submissions within 28 days of these Orders.
(2) The Respondent is to file and serve any submissions in addition to those dated 18 July 2018 within a further period of 21 days.
(3) The Appeal Panel will make Orders as to costs on the papers.
(1) Either party may make submissions as to any outstanding Order including any order as to the transfer of funds held in an account under an order of the Tribunal. Catchwords: APPEAL--Home Building Act - s 48O, terms of order to rectify" Legislation Cited: Home Building Act 1989 Category: Costs Parties: Catapult Constructions Pty Ltd (Appellant) Julia Anne Denison (Respondent) Representation: On the papers: File Number(s): AP 17/46569 Publication restriction: Unrestricted Decision under appeal Court or tribunal: NSW Civil and Administrative Tribunal Jurisdiction: Consumer and Commercial Division Citation: Not applicable Date of Decision: 03 October 2017 Before: G Meadows, Senior Member File Number(s): HB 15/52872 and HB 15/53181
Introduction
Submissions
Additional Contractual Drawing
AG Drainage
Termite protection.
Detail Drawings Waterproof membrane and backfilling
Water damage
Proof of Insurance - Licences
Certifier Identified
Compliance Certificates
Commencement and Completion Dates
Consideration
Orders
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales. Registrar DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 01 August 2018
Catapult Constructions Pty Ltd
Denison No 2