[2025] QCAT 119
General information, not legal advice.
Queensland Civil and Administrative Tribunal
2025-03-20
Original judgment source is linked above.
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)
1 Extensive waterproofing issues with the construction of the basement.
2 Extensive waterproofing issues to the construction of the foundations and basement structure. Which we understand this is the subject of a prior QBCC investigation.
3 Consequential damage to wall linings, ceilings, timber wall panelling cellar and lift, lift metalwork in the base of the lift shaft and tiling of the basement due to water ingress, corrosion, and mould.
4 Water builds up behind the aqua check plasterboard wall linings of the basement.
21 August 2017 Master Builders Commercial Building Contract executed between Crosland Constructions and Rockwell.
18 January 2018 Rockwell issued a breach notice with respect to basement waterproofing.
23 February 2018 Rockwell claimed to have re -waterproofed the basement.
28 March 2018 first quantity surveying report by Accurate Estimating Services (AES) (Mr Ray).
5 June 2018 contract between Crosland Constructions and Rockwell terminated.
13 June 2018 second quantity surveying report by Accurate Estimating Services (AES) (Mr Ray).
18 June 2018 second contract between Crosland Constructions and Steve P Carpentry Pty Ltd (SPC) (Mr Purcell) to complete construction
2 July 2018 preparation for start of works under second contract between Crosland Constructions and Steve P Carpentry Pty Ltd (SPC) (Mr Purcell) to complete construction.
4 July 2018 SPC commence construction works.
27 November 2018 Rockwell's progress claim number seven for final accounting.
12 February 2019 Form 21 final inspection certificate.
14 February 2019 adjudication decision between Crosland Constructions and Rockwell assessing sum owed for works partially completed by Rockwell.
10 June 2019 Deed of settlement between Crosland Constructions and Rockwell agreeing on/acceptance of sum owed.
9 December 2019 Mr Castro purchases the subject property.
19 December 2021 Crosland Constructions Pty Ltd deregistered.
8 August 2022 Mr Castro lodges a complaint with the Commission.
March and April 2023 Commission's inspector conducts inspections.
24 July 2023 initial inspection report produced by Commission.
26 July 2023 Commission issues its review decision declining to issue a direction to rectify to Rockwell.
22 August 2023 Mr Castro applies to the Tribunal for review of the Commission's decision.
11 December 2023 Commission's statement of reasons.
a) Rockwell Group was originally contracted to complete the dwelling, but the contract was terminated during construction. > > b) Two quantity surveying reports completed by Accurate Estimating Services earlier in the course of construction and then at contract termination identified that approximately, respectively 70% and 85% of the waterproofing to the basement was completed, at those points in time. > > c) An adjudication decision (No 468849), that concluded that the percentages shown in the Construction Progress Valuation Report (AES) were agreed between the original contracting parties. and > > d) The adjudication decision awarded Rockwell Group $247,835.20 for monies owed by the original owner/developer, which remained unpaid.
The short point is that the Respondent (Crosland) must be deemed to have fully understood the content of the May 2018 progress claim (effectively 5 June 2018 because no works were undertaken in the period 31 May 2018 to 5 June 2018) in relation to both the contract works and the claims for variations because its quantity surveyor had agreed those quantities, percentages and amounts with the claimant (Rockwell) and that agreement was recorded in the document entitled progress report dated 13 June 2018 (second AES report), which was relevantly identical to the progress claims of 31 May 2018.......because I have concluded the claimant (Rockwell) and the banks quantity surveyor (Crosland Constructions) have agreed upon the scheduled percentages of work completed on or about 31 May 2018, and that the claimant did no further work between that date and its termination. I will assume prima facie that the percentages shown in the construction progress report (of 13 June 2018) were agreed and should be preferred.
[1] Wright v Duke Building Pty Ltd [2017] QCATA 35 at [62].
[2] Section 71I(1)(i) states that for the purposes of section 71 that a person who carries out building work is taken to include "a person who, for profit or reward, carried out the building work".
[3] J M Kelly (Project Builders) Pty Ltd [2015] QCAT 66.
[4] Waddell v Queensland Building and Construction Commission [2023] QCAT 159.
[5] Taouk v Queensland Building Services Authority [2013] QCAT 508.
[6] Maldes v Queensland Building and Construction Commission [2022] QCAT 359
Castro
Queensland Building and Construction Commission [2025] QCAT 119
J M Kelly (Project Builders) Pty Ltd v Queensland Building Services Authority [2015] QCAT 66
Waddell v Queensland Building and Construction Commission [2023] QCAT 159
Taouk v Queensland Building Services Authority [2013] QCAT 508
Maldes v Queensland Building and Construction Commission [2022] QCAT 359
Wright v Duke Building Pty Ltd [2017] QCATA 35