[2026] NSWLEC 1188
General information, not legal advice.
Land and Environment Court (NSW)
2026-04-09
Walsh C
Original judgment source is linked above.
Zoe will write a short plain-English brief of this judgment and email it to you: what it was about, what the court decided and why. It can take up to a minute.
General information, not legal advice.
Or create a free account to save it and ask Zoe follow-up questions.
Source: NSW Caselaw (www.caselaw.nsw.gov.au). Converted to plain text by ZoeLaw. Not the official version.
Medium Neutral Citation: Castle 38 Pty Ltd v Ku-ring-gai Council [2026] NSWLEC 1188
Hearing dates: Conciliation conference on 27 March 2026
Date of orders: 09 April 2026
Decision date: 09 April 2026
Jurisdiction: Class 1
Before: Walsh C
Decision: The Court orders:
(1) The appeal is upheld.
(2) Development Application No. eDA1082/25 seeking consent for the demolition of existing structures and buildings, amalgamation of lots, and erection of a 7 storey residential flat building with 3 levels of basement parking and associated landscaping to build 51 new apartments at Lots 4 and 5 in Deposited Plan 4665, otherwise described as 5 -7 Middle Harbour Road, Lindfield is determined by the grant of consent subject to the conditions in Annexure B.
(3) Pursuant to s 8.15(3) of the Environmental Planning and Assessment Act 1979 (NSW), the Applicant is to pay the Respondent's costs thrown away in the sum of $20,000 (excl. GST) within 28 days.
Catchwords: DEVELOPMENT APPLICATION – conciliation conference – agreement between the parties – orders
Legislation Cited: Environmental Planning and Assessment Act 1979 (NSW), ss 4.15, 4.16, 8.15, 8.7
Land and Environment Court Act 1979 (NSW), s 34
Environmental Planning and Assessment Regulation 2021 (NSW), s 38
Ku-ring-gai Local Environmental Plan 2015, cl 6.5
State Environmental Planning Policy (Biodiversity and Conservation) 2021, Ch 6, ss 6.6, 6.7, 6.8, 6.9, 6.10
State Environmental Planning Policy (Housing) 2021, Chs 2, 5, ss 16, 18, 151, 152, 154, 155, 156, 159
State Environmental Planning Policy (Resilience and Hazards) 2021, s 4.6
Cases Cited: McMillan v Taylor (2023) 111 NSWLR 634; [2023] NSWCA 183
Texts Cited: NSW Government, Apartment Design Guide, July 2015
Category: Principal judgment
Parties: Castle 38 Pty Ltd (Applicant)
Ku-ring-gai Council (Respondent)
Representation: Counsel:
J Reed (Applicant)
C Morton (Solicitor) (Respondent)
Solicitors:
Thomas Greer (Applicant)
Sparke Helmore Lawyers (Respondent)
File Number(s): 2025/232954
Publication restriction: Nil
COMMISSIONER: These proceedings, brought by Castle 38 Pty Ltd (applicant) under Class 1 of the Court’s jurisdiction, are an appeal pursuant to s 8.7 of the Environmental Planning and Assessment Act 1979 (NSW) (EPA Act) against the deemed refusal of Development Application No. eDA0182/25 (DA) by Ku-ring-gai Council (Council). The DA seeks consent for demolition of existing buildings and structures, amalgamation of lots and the construction of a seven storey residential flat building with 51 apartments over three levels of basement parking and associated works including landscaping at Lots 4 and 5 in Deposited Plan 4665, otherwise described as 5-7 Middle Harbour Road, Lindfield (site).
The Court arranged a conciliation conference between the parties under s 34 of the Land and Environment Court Act 1979 (NSW) (LEC Act), which was held on 27 March 2026. I presided over the conference. The parties indicated they had come to an agreement in relation to the terms of a decision in the proceedings that would be acceptable to the parties.
The parties' decision involves the Court exercising the function, under s 4.16 of the EPA Act, to grant consent to the DA, as amended, subject to agreed conditions. Under s 34(3) of the LEC Act, I must dispose of the proceedings in accordance with the parties’ decision if it is a decision that the Court could have made in the proper exercise of its functions. The question here is whether preconditions to the exercise of the power to grant consent are satisfied. The parties advise and I accept that relevant documentary and procedural preconditions have already been met. What has not as yet occurred is the making of findings on certain factual preconditions which enable jurisdiction to, in this case, the Court’s exercise of consent powers (McMillan v Taylor (2023) 111 NSWLR 634; [2023] NSWCA 183 at [57]-[65]). Commonly these factual preconditions include a requirement for a finding of satisfaction with respect to applicable provisions in relevant environmental planning instruments. This judgement is intended to address these factual preconditions.
The parties outlined matters of relevance through an agreed statement of jurisdictional preconditions provided to the Court on 27 March 2026, explaining how they believed relevant preconditions to the exercise of consent power have or could be satisfied. Mindful of their advice, I ultimately concur with the parties’ and believe there is power available to the Court to exercise the function of granting development consent in accordance with the parties' agreement. This is contingent on the findings which follow, which are made mindful of the advice of the parties.
Certain provisions of State Environmental Planning Policy (Housing) 2021 (Housing SEPP) apply. According to the parties, Ch 5 (concerned with Transport Oriented Development) applies as the site falls within a Transport Oriented Development Area (as identified on the Transport Oriented Development Sites Map) pursuant to s 152. Further, residential flat buildings are permitted with development consent on the site as it sits in a relevant residential zone, pursuant to ss 151 and 154.
The proposal seeks to take up the provisions of Ch 2 (concerned with affordable housing) as it proposes the dedication of eight apartments or 12.8% of the total gross floor area (GFA) of the building as affordable housing for a period of 15 years (the parties advise the baseline provisions of Ch 5 and s 156(2) requiring 2% of the GFA of the building to be used for affordable housing in perpetuity is also satisfied). Meeting Ch 2’s threshold brings into play s 16 which provides a mechanism for uplift in GFA and building height, proportionate to the affordable housing component of the development.
The parties advise that the proposal does not call upon the uplift in GFA under Ch 2 and that the proposed GFA meets the baseline requirements of 2.5:1 under s 155(4)(a). The proposed building height of 27.63m exceeds the 22m control under s 155(2), however is permissible under the affordable housing uplift provisions at s 18.
The parties do not direct me to any requirement for a jurisdictional finding with respect to the Housing SEPP but the advice in regard to compliance with these development standards is accepted and noted. It is further noted that the requirement on site width (s 159) and the requirement for the consent authority to consider the Apartment Design Guide have also been met.
With the above factual findings, there is no jurisdictional bar and the parties’ decision is one that the Court could have made in the proper exercise of its functions. Therefore, I am required under s 34(3) of the LEC Act to dispose of the proceedings in accordance with the parties’ decision.
In making the orders to give effect to the agreement between the parties, I was not required to make, and have not made, any merit assessment of the issues that were originally in dispute between the parties. The LEC Act also required me to “set out in writing the terms of the decision” (s 34(3)(b)). The final orders have this effect.
The Court orders:
The appeal is upheld.
Development Application No. eDA1082/25 seeking consent for the demolition of existing structures and buildings, amalgamation of lots, and erection of a 7 storey residential flat building with 3 levels of basement parking and associated landscaping to build 51 new apartments at Lots 4 and 5 in Deposited Plan 4665, otherwise described as 5 -7 Middle Harbour Road, Lindfield is determined by the grant of consent subject to the conditions in Annexure B.
Pursuant to s 8.15(3) of the Environmental Planning and Assessment Act 1979 (NSW), the Applicant is to pay the Respondent's costs thrown away in the sum of $20,000 (excl. GST) within 28 days.
**********