austlii:vic/VBAB/2025/130
General information, not legal advice.
VBAB
2025-10-20
Original judgment source is linked above.
1.1. That the Owner and any other persons must vacate the building within 30 days from the date of this Injunction and are prohibited from occupying the building thereafter.
1.2. That the Owner is to demolish and or remove the Building located on the property in its entirety within 120 days from the date of this injunction.
(a) 'retrospectively',[3] development of the Dwelling; and
(b) use of the Subject Land for the purposes of 'caretaker's residence'.
The dwelling does not currently have planning approval and hence would require retrospective planning approval for it to be legalised
building work in the form of the construction of a dwelling has been carried out without a building permit being in force contrary to Section 16 of the Building Act 1993.
(a) providing:
(i) a report prepared by Mr Simon Flahavin of Keystone Building Surveyors dated 14 February 2025 (Keystone Report);
(ii) a bushfire attack level (BAL) assessment report prepared by Fire Risk Consultants;
(iii) a BAL Certificate issued 12 February 2025; and
(iv) the Structural Assessment; and
(b) saying:
As set out in the Keystone report, Mr Flahavin considers that the following works are required for the dwelling to be suitable for occupation:
We are instructed that our client would like to undertake these works as soon as possible and seek confirmation from the Municipal Building Surveyor as to what permissions are required for these works or if they can be undertaken in the current enforcement process.
We also request that Council confirm that subject to the rectification works identified being completed that Council will cancel or withdraw the building notice and take no further enforcement action in this matter.
building work in the form of the construction of a dwelling has been carried out without a building permit being in force contrary to Section 16 of the Building Act 1993.
insufficient cause has been shown by the Owner and that for the reasons set out in the building notice the making of this Order is warranted.
(a) the decision of the MBS to make the 2025 Order; and
(b) the decision of the MBS to refuse to cancel the 2025 Order.
it is unreasonable for the Respondent to issue the Building Order in light of its response to the Building Notice, especially as the Structural Assessment and Report prepared by Chris O'Brien & Company Pty Ltd confirms that the dwelling (including attached verandahs) is structurally adequate and safe for domestic occupation. Given the minor nature of the rectification works recommended by Keystone Building Surveyors, the Respondent ought to have either issued a building order under section 113 of the Act for minor work or action, or requested further response from the Applicant.
orders or relief from the Board that the Building Order be cancelled, conditional upon the completion of the following work as set out in the Inspection and Assessment of Suitability Report prepared by Keystone Building Surveyors dated 14 February 2025:
a) Rectification works so that the dwelling meets the BAL 12.5 requirements; and
b) Installation of additional smoke detectors, which are hardwired and adequately placed so that the sleeping rooms are separated from the living rooms.
a) The Keystone Building Surveyors report failed to address and provide solutions for multiple building non-compliances,
(1) ... the relevant building surveyor must not issue a building permit unless he or she is satisfied that -
(c) any relevant planning permit or other prescribed approval has been obtained; and
(d) the building permit will be consistent with that planning permit or other prescribed approval.
A building order under this section may direct the owner of a building, land or a place of public entertainment to carry out building work, protection work or other work required by the regulations in relation to the building, land or place.
Despite anything to the contrary in this Act or the building regulations, a person who carries out work in accordance with an emergency order or building order in force under this Part is not required to obtain a building permit or comply with the building regulations unless the relevant building surveyor so directs
(a) we have identified rectification work which we consider should be done promptly, and in relation to which we will not require a building permit to be issued before that work is done; and
(b) where we have decided that a building permit should be issued before rectification work is done, we have recognised that resolution of the dispute regarding the Planning Permit may take a considerable amount of time, and we have set the due date for compliance with that in mind.
(a) lack of smoke detection; and
(b) not constructed to appropriate bushfire attack level (BAL).
(a) the carrying out of all necessary building work to upgrade the Dwelling to the required BAL; and
(b) that work to be performed in accordance with a building permit.
(a) if the dispute regarding the planning permit is not resolved in the Applicant's favour, it will not be possible to obtain a building permit to bring the Dwelling into compliance with the Regulations; and
(b) the work required to bring the Dwelling into compliance with the Regulations might be too difficult or too expensive to undertake.
[1] Clause 17 of Schedule 3 to the Building Act 1993 provides: 'Unless the Building Appeals Board otherwise determines, a party to a proceeding before the Board must bear his, her or its own costs'.
[2] Somewhat unhelpfully, none of the notices or orders are identified by a unique reference number.
[3] While planning permits issued after development has been carried out do not have any retrospective effect (Planning and Environment Act 1987, s 67, Van Egmond v City of Knox, Bassett & Ors (1985) 3 PABR 249), the term 'retrospective' is widely used to refer to the grant of a planning permit after all development authorised by that planning permit has already been completed.
[4] There is some inconsistency in the MBS's contentions. On the one hand, the MBS said that the 2017 Order was 'withdrawn in 2020'. On the other hand, it was said (and appeared to be common ground between the parties) that the 2017 Order was 'withdrawn' (though, we conclude it was more likely cancelled) after the Planning Permit was issued. The Planning Permit (a copy of which was before us) was issued on 22 September 2021.
[5] Again, no record of this decision was before us. The MBS referred to cancellation of the 2017 Order, but s 116 of the Act gives the MBS the power to cancel a building order.
[6] The detail of which is not important here.
[7] The letter is dated 25 September 2022, however it refers to 'correspondence ... dated 26 July 2024 and ... follow up correspondence dated 29 August 2024', so cannot possibly have been sent in 2022. We therefore conclude that it was most likely sent in September 2024.
[8] The Applicant indicated that the time within which representations could be made in response to the 2024 Notice was, at the request of the Applicant, extended by the MBS, however this is not reflected in the 2025 Order.
[9] We have considered all of written and oral submissions made by the parties and (relevant) material filed with the BAB, however, we do not consider it necessary to refer to or cite all of the material put before us, instead focussing on the key points leading to our findings.
[10] A position ultimately supported by the MBS.
[11] Regardless of whether it is characterised as a 'Dwelling' or a 'caretaker's residence'.
�Canningvale Pty Ltd
Municipal Building Surveyor for the Shire of Wellington [2025] VBAB 130;