IMPROVEMENTS TO LOT - where the respondents have removed internal kitchen walls from their lot
BY-LAWS -Where a by-law requires body corporate approval for structural alterations, and the body corporate approval not obtained
RES JUDICATA- whether same matter has been finally decided
Act, s 163, s 276 Standard Module, s 180(2)(b)
(i) The unit entry wall which has been totally removed must be rebuilt in its original location, length and state as a full-length masonry infill wall with no gap between the top course of bricks and the ceiling.
(ii) The bathroom wall, which has been totally removed and replaced with a partial nib stud and plasterboard wall, must be rebuilt in its original location, length and state as a full-length masonry infill wall with no gap between the top course of bricks and the ceiling.
(iii) The eastern kitchen wall, which has been shortened by approximately 60cm and had large sections replaced with stud plasterboard walls, must be rebuilt in its original location, length and state as a full-length masonry infill wall with no gap between the top course of bricks and the ceiling.
(iv) The northern kitchen wall, which has been totally removed must be rebuilt in its original location, length and state as a full-length masonry infill wall with no gap between the top course of bricks and the ceiling.
I HEREBY CERTIFY this is a true copy of the order and reasons for decision.
I HEREBY CERTIFY this is a true copy of the order and reasons for decision.
A declaratory order that the four walls modified by the respondents were loadbearing because of their method of construction as masonry infill walls built with no gap between the top of the wall and the ceiling slab.
A declaratory order that the respondents have breached Camden By-law 14 and the BCCM Act by not obtaining Body Corporate permission before making the changes to the four walls in question.
The applicant says the four walls form part of the 'essential supporting framework, including load-bearing walls' referred to in Section 180(2)(b)(iii) of the Body Corporate and Community Management (Standard) Regulations 2020. Consequently, the Body Corporate has an obligation under Section 180(2)(b)(iii) to ensure the structural integrity of these walls is restored.
An order that, within three months of the issuing of this order, the respondents must return all four walls to their original location, length and condition by rebuilding them, as brick infill walls with no gap between the top of the wall and the ceiling slab. More specifically, the remedial works are to be completed as follows:
(i) The unit entry wall which has been totally removed must be rebuilt in its original location, length and state as a full-length masonry infill wall with no gap between the top course of bricks and the ceiling.
(ii) The bathroom wall, which has been totally removed and replaced with a partial nib stud and plasterboard wall that does not extend to the ceiling slab, must be rebuilt in its original location, length and state as a full-length masonry infill wall with no gap between the top course of bricks and the ceiling.
(iii) The eastern kitchen wall, which has been shortened by approximately 60cm and had large sections replaced with stud plasterboard walls, must be rebuilt in its original location, length and state as a full-length masonry infill wall with no gap between the top course of bricks and the ceiling. The doorway must be rebuilt in its original location.
(iv) The northern kitchen wall, which has been totally removed must be rebuilt in its original location, length and state as a full-length masonry infill wall with no gap between the top course of bricks and the ceiling. The servery window must be rebuilt in its original location.
A declaratory order that the respondents must maintain in place all temporary ceiling slab supports ordered to be installed in interim orders until the work ordered to return the walls to their original state has been completed to the Body Corporate's satisfaction.
That until the respondents have completed the work ordered to the satisfaction of the Body Corporate, they must allow any persons authorised by the Body Corporate access to lot 2 upon receiving 7 days notice under Section 163.
This access is to allow the Body Corporate to verify that the remedial work is being carried out as ordered.
A declaratory order that the Body Corporate may recover from the respondents, as a debt, all reasonable costs incurred by it in this matter. This includes, but is not limited to, the costs of engineering advice that the Body Corporate has already had to procure or may have to procure. It also includes the cost of any work the Body Corporate may have to carry out to meet its obligation with respect to the walls under Section 180(2)(b)(iii) of the Body Corporate and Community Management (Standard) Regulations 2020.
A declaratory order that the respondents are responsible for reimbursing the owners of lots 5 and 11 for all reasonable expenses they incur in rectifying cracks in their internal walls caused by the unapproved changes the respondents have made to the four walls.
Furthermore, the respondents must reimburse the owners of lots 11 and 5 within 7 days of receiving a reimbursement request, otherwise they will be in breach of this order.
No internal Structural Changes to Units Without Committee Approval
An owner or occupier of a lot shall not make any internal structural changes to his or her lot without the consent in writing, of the body corporate. Such consent shall only be granted upon the receipt of a properly documented engineer's report attesting that the structural integrity of the building is maintained.
We undertake not to carry out any demolition works in Unit 2 that involve removal or modification of any walls or any of the five body corporate common property windows along the western wall. We shall be relieved of this undertaking only once we have received authorisation from the Body Corporate of Camden to perform these works.
The walls were 'observed to be clay masonry construction and MPN observed no gap between the walls and at the ceiling slab'. Our observation onsite indicates there may be a redistribution of load after demolition and therefore the walls can be considered to support building load. Therefore, MPN cannot state that there will be no movement after wall removal. Any structural movement after demolition of the walls could reflect as cracking to walls or finishes in units above unless structural remediation is provided.'
As per our initial letter, we confirm the original structural drawings, combined with our site inspection, were the key components on which we based our structural assessment of the proposed works. We also confirm that page 48 of the PDF copy of the original structural drawings outlines the type and location of the loadbearing walls and the proposed works does not include or require the removal of any loadbearing walls.
ongoing stability of the Unit 2 ceiling/ Unit 5 floor has been certified by CMG Engineers.
(a) the walls, due to their method of construction, are loadbearing/structural;
(b) the changes to the walls required the Applicant's approval under by-law 14;
(c) the changes to the walls have adversely impacted upon the structural integrity of the building and caused damage to other lots;
(d) that continued propping, until rectification, is required;
(e) that access to Lot 2 was improperly refused; and
(f) that remedial works to the walls is required.
180 Duties of body corporate about common property - Act, s 152
(1) The body corporate must maintain common property in good condition, including, to the extent that common property is structural in nature, in a structurally sound condition.
(2) To the extent that lots included in the community titles scheme are created under a building format plan of subdivision, the body corporate must -
(i) railings, parapets and balustrades on, whether precisely, or for all practical purposes, the boundary of a lot and common property; and
(ii) doors, windows and associated fittings situated in a boundary wall separating a lot from common property; and
(iii) roofing membranes that are not common property but that provide protection for lots or common property; and
(b) maintain in a structurally sound condition the following elements of scheme land that are not common property -
(iii) essential supporting framework, including load-bearing walls.
(3) Despite anything in subsections (1) and (2) , the body corporate is not responsible for maintaining fixtures or fittings installed by the occupier of a lot if they were installed for the occupier's own benefit.
(5) To avoid any doubt, it is declared that, despite an obligation the body corporate may have under subsection (2) , the body corporate may recover the prescribed costs, as a debt, from a person, whether or not the owner of the lot, whose actions cause or contribute to the damage or deterioration of the part of the lot.
"prescribed costs" , recoverable from a person, means the proportion of the reasonable cost to the body corporate of carrying out the maintenance that the body corporate reasonably considers can be fairly attributed to the person's actions.
(a) We have inspected both the building and Unit 2 at 108 Macquarie Street to determine if the proposed renovation works will impact the structural integrity of the building.
(b) The original structural drawings were made available and were a key component in our investigation.
(c) We can confirm that the proposed renovation works, which include the non-load bearing walls to be removed, as well as the balcony works, will not impact the structural integrity of the unit or the building.
(a) Further to our letter (Our Ref: 45317L1) dated 23 August 2022, we have reviewed and certified the construction drawings provided by TPG Architects and reassessed the structural considerations of the proposed works.
(b) As per our initial letter, we confirm the original structural drawings, combined with our site inspection, were the key components on which we based our structural assessment of the proposed works.
(c) We also confirm that page 48 of the PDF copy of the original structural drawings outlines the type and location of the loadbearing walls and the proposed works does not include or require the removal of any loadbearing walls.
(d) The slab thickness and reinforcement are provided on page 49 of the PDF copy of the original structural drawings and these correspond structurally with the location of the loadbearing walls. The proposed balcony works involves lightweight construction and will not compromise the structural adequacy of the balcony slab.
(e) We certify the proposed renovation works will not affect the structural integrity/adequacy of the existing building.
(a) I've attached copies of those two drawings that CMG references, ie Pages 48 and 49 .
(b) I've also attached pg 17 of the same set of PDFs that indicate the original architectural setout of the First floor units. The non loadbearing walls nominated as typically 110mmm and the loadbearing as nominally 150mm. It is clear that what we measured on site last year and documented in our plan drawing (attached) is consistent to what is shown in the original architectural layout. The Structural drawings pages 48 and 49 do not (as is industry practice typically would not) indicate dimensioned locations of walls, these are always indicated on Architectural floor plans as is the case here. The fact that the non loadbearing wall do not necessarily align with that drawn on the architectural plans is not relevant as both the loadbearing and nonloadbearing walls are dimensioned on the architectural plans.
The extent of cracking does not appear to be increasing in width or extent. However, it is recommended this is monitored (e.g. glass tile over crack and marking of extent)
It is recommended the engineer for Unit 2 works (CMG Engineers) inspect and comment on the reported distress in Unit 5
Furthermore, we recommend CMG Engineers confirm the structural adequacy of the Unit ceiling/ Unit 5 floor, and specify measures to ensure no further movement occurs. This may comprise a lintel beam or other remedial structural element.
The cracks are old, pre-existing cracks. New cracks appear fresh and sharp. These cracks are weathered and rounded with evidence of existing cracks under the paintwork.
The shape and location of the cracks in the filled in arched doorway of the eastern kitchen wall are due to the two different material types used and are also pre-existing. The wall immediately under this wall, in Unit 2, remains. The opening in the wall in Unit 2 was increased by 40mm. This is a very small increase and will not and did not affect the wall over in Unit 5.
The wall immediately under the living room/bathroom wall in Unit 2 remains and did not affect the wall over in Unit 5.
The cracks in Unit 8 establish a history of cracking in the rendered clay masonry walls of this building. The construction procedure and notes provided by the building contractor confirms that the works undertaken in Unit 2 had no impact on the existing structure.
The works undertaken in Unit 2 did not cause any cracking in the walls of Unit 5. The location, geometry and visual appearance of the cracks in Unit 5 indicates they pre-existed any works completed in Unit 2.
(a) Notwithstanding there was no gap between the walls and the ceiling slab, those walls remained non-structural and redundant with respect to the structural integrity of the slab above;
(b) Redistribution of load following removal of the subject walls had been considered in their assessment of how the load would be accommodated by the slab spans between the remaining walls;
(c) They did not believe that removal of those walls resulted in deflection of the slab and therefore did not believe it was necessary to install an underpinning beam where the northern kitchen wall had been removed;
(d) the contractor followed the engineer's procedure, including monitoring and measurement and at no time was there any visible or measured defection of the slab over;
(e) the cracking in lots 2, 5, 8 and 11 is not due to the wall works; and
(f) without further information, comment cannot be made about the underpinning beam in Lot 5 other than it appears it may be undersized or ineffective.
Engineering advice was received from both parties from independent engineers throughout the approval and building process. Both engineers accept the original walls appear as non-load bearing on the original plans, disputing only redistribution of load
the cracking identified approx. 0.25mm to 0.50mm wide in the living room and bathroom walls of unit 5 are within the acceptable limits detailed in AS3700-2018 (current standard applicable to masonry structures.
After reviewing the information available, the QBCC are unable to apportion liability for the cracking observed in unit 5 without unfair prejudice given it is not conclusive that the cracking is a result of defective construction practices by the respondent, pre-existing damage or settlement associated with the age of the property, or settlement of building elements associated with resting the unit 5 suspended slab on the non-load bearing masonry wall below.
Your complaint has been investigated and there was insufficient evidence to reveal any obvious defective construction practices by Simon Prosser at the time of the inspection. Therefore the QBCC is unable to provide you with any further assistance with the resolution of the item.
(a) the walls are structural;
(b) the removal and modification works on the walls have caused damage to other lots;
(c) there is risk of further damage;
(d) that propping is required;
(e) that access to lot 2 was improperly refused.
(a) The internal walls: > > > (i) do not form part of the fabric or framework of the building; and > > > > (ii) whilst they may have been attached to the building, are not integral to the building itself; and > > (b) The changes to the internal walls; > > > (i) are not a structural change, such that it is not a breach of by-law 14; > > > > (ii) did not withdraw support, such that it did not interfere with the easement for support; and > > > > (iii) did not cause any damage to the building and no remedial action is required; and
(a) the CMG engineering reports are based on original plans that do not reflect the Lot 2 "as built"; > > (b) the second kitchen wall is an extension, and the same width, of a load bearing wall labelled W40; and > > (c) the Wall labelled W35 runs the full length of the hallway, demonstrating the differences between the original plans and Lot 2 as built.
(a) The model with kitchen walls removed does not accurately account for the cumulative effect for load of the walls and floor slabs above Level 2.
(b) Given building movement has occurred and to whatever extent, it is more likely that cracking observed and reported has occurred as a result of this movement.
No internal Structural Changes to Units Without Committee Approval
An owner or occupier of a lot shall not make any internal structural changes to his or her lot without the consent in writing, of the body corporate. Such consent shall only be granted upon the receipt of a properly documented engineer's report attesting that the structural integrity of the building is maintained.
The walls were 'observed to be clay masonry construction and MPN observed no gap between the walls and at the ceiling slab'. Our observation onsite indicates there may be a redistribution of load after demolition and therefore the walls can be considered to support building load. Therefore, MPN cannot state that there will be no movement after wall removal. Any structural movement after demolition of the walls could reflect as cracking to walls or finishes in units above unless structural remediation is provided.
[59] The term 'structural' is not defined in the by-laws or the legislation. The Cambridge Dictionary defines it as 'relating to the structure of a building or similar object'. The Oxford Dictionary defines it as 'forming a necessary part of the structure of a building or other construction, as distinct from its decoration or fittings'.
[60] In Granada Theatres Limited v Freehold Investments (Leytonstone) Ltd [9], the English Court of Appeal considered the meaning of the term 'structural' and upheld the interpretation adopted by the trial judge who stated as follows:
It appears, rather surprisingly that the expression 'structural repairs' has never been judicially defined, a fact to which attention is drawn in the 21st edition of Woodfall's Law of Landlord and Tenant at page 770, and Counsel in the present case have accepted that statement as correct. The writer of the textbook submits on the same page that 'structural repairs' are those which involve interference with, or alteration to, the framework of a building, and I would myself say that 'structural repairs' means repairs of, or to, a structure. It is sometimes said that repairs must be either structural or decorative, and if that is the simple criterion we are in this case certainly not dealing with decorative repairs.
[63] In Owners SP10701 v Segelov [13], the Strata Schemes Board of New South Wales considered the meaning of 'structural alterations' in the context of a by-law, as follows:
If the ordinary usage of the term "structural" is to be applied, the relevant definition in the Shorter Oxford Dictionary is "of or pertaining to the structure of a building as distinct from decoration or fittings".
In my view the word "structural" does not limit the kind of alterations to alterations of load-bearing walls for example. Structural alterations would certainly include alterations which involve the penetration of a common property floor slab.
[64] The New South Wales Supreme Court in Alamdo Holdings Pty Ltd v Australian Window
Furnishings (NSW) Pty Ltd[ 14] considered the meaning of the term 'structural' as follows:
The first thing to be said is that, as I view matters, maintenance, replacement or repair that is
"structural" can be undertaken only in relation to something that is a "structure" although, of course, not everything done by way of maintenance, replacement or repair in relation to a "structure" is properly classified as "structural". I regard as apposite, in this connection, a passage in the judgment of Brereton J in Hampson v Clyne (1967) 89 WN (NSW) 321:
'Structure' of course is a word of which the meaning varies considerably according to the context, and the phrase 'structural character' or 'defect of a structural character' varies correspondingly. Literally 'structure' means something which has been constructed and 'defect of a structural character' means either a fault in putting the structure together or some subsequent failure on the part of the structure to remain satisfactorily put together. With particular reference to buildings in common parlance we refer to the bare building as the structure. We refer to fixtures and fittings attached to the structure although these may themselves as individual units be technically 'structures'. We refer also to installations, such
as gas and water piping and electrical circuits. Each of these may, however, independently be in certain contexts regarded as a 'structure' in that it is something which has been constructed within another structure.
(a) the CMG engineering reports are based on original plans that do not reflect the Lot 2 "as built";
(b) the second kitchen wall is an extension, and the same width, of a load bearing wall labelled W40; and
(c) the Wall labelled W35 runs the full length of the hallway, demonstrating the differences between the original plans and Lot 2 as built.
(i) The unit entry wall which has been totally removed must be rebuilt in its original location, length and state as a full-length masonry infill wall with no gap between the top course of bricks and the ceiling.
(ii) The bathroom wall, which has been totally removed and replaced with a partial nib stud and plasterboard wall, must be rebuilt in its original location, length and state as a full-length masonry infill wall with no gap between the top course of bricks and the ceiling.
(iii) The eastern kitchen wall, which has been shortened by approximately 60cm and had large sections replaced with stud plasterboard walls, must be rebuilt in its original location, length and state as a full-length masonry infill wall with no gap between the top course of bricks and the ceiling.
(iv) The northern kitchen wall, which has been totally removed must be rebuilt in its original location, length and state as a full-length masonry infill wall with no gap between the top course of bricks and the ceiling.
[9] Annexure 2 to Application - Report dated 7 June 2023
[18] See Page 28 of attachments to Respondent's submissions
[19] See page 59 of attachments to Respondent's submissions
[22] Annexure 15 to Respondents' submission
[23] Exhibit 1 "Peters Report" dated 29 November 2024
[25] Camden [2023] QBCCMCmr 168
[26] See Annexure 27 to the Application
[31]Mr Pikusa confirmed this opinion in his report following a second inspection on 6 October 2023, after the respondents had removed the Northern kitchen wall, the Unit entry wall and sections of the Bathroom and Eastern kitchen wall - see Annexure 20.
[34] This is evident from photographs accompanying the application.
[35] Camden [2023] QBCCMCmr 168