[2024] WASCA 142
General information, not legal advice.
Court of Appeal (WA)
2024-11-13
Buss P
Original judgment source is linked above.
It was not in dispute that Rexwells was a business with low capital and assets, and had a good revenue stream. In [the third respondent's] evidence, he confirmed that the sale of Rexwells was essentially the sale of a revenue stream together with a minimal amount of assets [390].
(a) Completion of the transactions contemplated by this agreement is subject to and conditional upon the Purchaser [ie the appellant] being satisfied at its sole discretion with its due diligence investigations relating to the Company, the Business, the Shares and the transactions occurring under this agreement.
(b) The duration of this due diligence process will be limited to 30 January 2019.
(c) If the Purchaser has not advised the Seller [ie the first respondent] by 30 January 2019 that this condition 2.1 has not been satisfied, this condition is deemed to be satisfied and cannot be used by the Purchaser to terminate this agreement.
2.2 Conditions - general
Completion of the transactions contemplated by this agreement is subject to and conditional upon:
(a) execution of employment agreements by all Employees on terms satisfactory to the Purchaser;
(b) no material breach of the Warranties;
(c) the Purchaser entering into the New Lease over the Premises on terms acceptable to Purchaser;
(d) consents being obtained to change in control in connection with each material Business Contracts identified during due diligence on terms acceptable to the Purchaser at its sole discretion; and
(e) the Purchaser being satisfied at its absolute discretion that a new contract has been entered into with Rio Tinto Limited on terms acceptable to the Purchaser; and that if the new contract has a change of control clause Rio Tinto Limited has provided to the Purchaser assurance to the satisfaction of the Purchaser at its absolute discretion that Rio Tinto Limited will not seek to terminate this new contract as a consequence of the change in control of the Company which will occur should the sale and purchase of the Shares under this agreement Complete.
2.3 Financial assistance condition
Completion of the transactions contemplated by this agreement is subject to and conditional upon that assistance being approved by Shareholders under section 260B in compliance with required advance notice to the ASIC.
2.4 Best endeavours
The parties must use their best endeavours to satisfy the conditions set out in clauses 2.2 through 2.3.
2.5 Notice
A party must promptly notify the other parties in writing if it becomes aware that any of the conditions in clauses 2.2 through 2.3 are satisfied or become incapable of being satisfied.
2.6 Waiver
(a) The conditions in clauses 2.2 [sic] may only be effectively waived if waived by the Purchaser.
(b) The condition in clauses 2.3 [sic] may only be effectively waived if waived by both of the Purchaser and the Seller.
2.7 Non-fulfilment of conditions
If the conditions in clauses 2.2 through 2.3 are not fulfilled before 30 January 2019 then, this agreement shall cease to have effect and thereafter no party shall have any claim of any nature against the other in relation to this agreement.
[B]anks and other financiers, traditionally concerned to avoid being involved in the contravention of the financial assistance prohibition, may not be comfortable in relying on the absence of material prejudice except in a very clear case, and may therefore insist upon a 'whitewashing' special resolution procedure under s 260B if there is doubt as to the application of the prohibition.[15]
51 Lark Lawyers' email emphasised that it was 'important' that the documents were completed and lodged with the ASIC by no later than 15 January 2019: [157].
[U]nless your client lodges the relevant documentation today and passes the resolution tomorrow (and otherwise complies with the requirements of section 260 [sic]) the provisions of condition 2.3 (ie the condition regarding financial assistance) will not have been satisfied prior to 31 January 2019.
Could you please confirm that the appropriate steps will now be taken and provide us with copies of the documents prepared and lodged and confirmation that the provisions of section 260 [sic] have been complied with [179].
Given that the deadline to lodge the necessary documents with ASIC is about to pass, our client proposes that the completion date be pushed back to 14 February 2019.
Please let us have the additional information that our client requires to allow it to give the necessary approval as well as whether we should proceed with preparing the indemnity and varying the completion date in the share purchase agreement [184].
We note that your client has refused to provide the information requested and, in the circumstances, our client has concluded that it has insufficient information to be able to resolve that the provision of the financial assistance (to the extent that the details of same are known to our client) will not materially prejudice Rexwells' ability to pay its creditors.
Accordingly, and in light of the fact that notice to ASIC had to be given by 15 January for settlement to occur on 31 January, our client hereby gives notice that the condition in clause 2.3 of the share purchase agreement has become incapable of being satisfied and, under clause 2.7 of the agreement, the agreement ceases to have effect [194]. (emphasis added)
It is plainly the case, in my opinion, that your client's conduct in purporting to rely upon clause 2.3 in the circumstances set out in the correspondence constitutes a wrongful repudiation of the contract. This is particularly the case where:
In the circumstances my client accepts your client's repudiatory breach and terminates the Deed [ie the SPA] [202].
(a) the respondents denied that they had repudiated the SPA;
>
> (b) the appellant was 'advantageously seizing' on the 17 January 2019 letter to 'manufacture an artificial legal position' to achieve more favourable terms than agreed in the SPA; and
>
> (c) the respondents offered to reduce the purchase price by $400,000 and for the parties to treat the SPA as if it were on foot with completion on 28 February 2019.
The plaintiff [ie the appellant] has lost the opportunity to acquire all of the issued shares [sic] in Rexwells and thereby [the] benefit thereof [sic] of owning Rexwells.[21]
3, The appellant failed to mitigate its loss by not accepting the offer from the respondents to treat the SPA as if it were on foot with a discount to the purchase price of $400,000: [44].
The share in Rexwells was not transferred nor did [the appellant] pay the purchase price to [the respondents]. As a result, I do not consider that [the appellant] is entitled to damages for the loss in not receiving the share in Rexwells, as well as the profit it would have earned from operating Rexwells. [The appellant] is, in my view, only entitled to the loss in not receiving the share [424].
[The appellant] has not adduced any evidence of the market value of the share in Rexwells as at 22 January 2019 or on 31 January 2019 when Completion was due to occur. None of the expert evidence that has been adduced in this case assists the determination of this issue. The evidence adduced by [the appellant] went solely to the issue of what profits [it] may have earned from the purchase of Rexwells. This might have been relevant if the purchase price had been paid and the benefit not received, however that is not what occurred.
In these circumstances, having not proved the market value of the share in Rexwells as at 22 January 2019, or any alternative amount, [the appellant] is only entitled to nominal damages [430] - [431].
Grounds of appeal, notice of contention and grounds of cross-appeal
[T]he primary judge erred in fact and law by concluding that the appropriate measure of damages in the present case was the difference between the purchase price contained in the Agreement and the market value of the share in Rexwells.
The primary judge ought to have found that the appellant's claim required a more sophisticated approach to the assessment of the proper measure of damages and concluded that the proper measure of damages in the present case was:
16.1 the difference between the purchase price and what has variously been described as the 'true value', 'fair value', 'real value', 'actual value', or ' intrinsic value' of the share in Rexwells' at the date of termination; alternatively
16.2 the discounted net present value of Rexwells' future profits over a term of 10 years plus its residual value, less expenses (including the purchase price contained in the Agreement) that would have been incurred by the appellant had the Agreement been performed.[36] (citations omitted)
Disposition: cross-appeal ground 1 - whether there was repudiation of the SPA
Objectively viewed, the words 'the agreement ceases to have effect' conveyed that [the respondents] considered [the SPA] had come to an end and [the respondents] did not intend to continue to perform any obligations under it. In this regard, I do not consider it is relevant whether [the respondents] believed this action was justified by the terms of the contract. As summarised above, the test of whether conduct is repudiatory or a renunciation of [the SPA] is an objective test.
While I do not consider [the respondents] had complied with their obligations under cl 2.3 [sic - meaning cl 2.4] of [the SPA], I accept that as at 4.47 pm on 17 January 2019, it was not possible for the financial assistance provision to be complied with to enable Completion to occur on 31 January 2019. For this reason, I accept that at or about the time the 17 January Notice was sent, the parties were obliged under cl 2.5 of [the SPA] to give notice that they believed cl 2.3 was incapable of being satisfied prior to Completion. However, this is not what the 17 January 2019 [sic] does or purports to do.
The 17 January Notice did not seek to discuss what is required by cl 2.3 of [the SPA]. It is not limited in its terms to an assertion of [the respondents'] view as to the effect on [the SPA] of the inability to comply with cl 2.3. The 17 January Notice went further and stated unilaterally, as a matter of fact and not opinion, that [the SPA] had ceased to have effect. Nothing in this letter suggests [the respondents] were prepared to perform their obligations under [the SPA], even if they were wrong in their construction of cl 2.3 [sic - meaning cl 2.7].
In any event, it is my view that there is no tenable basis upon which [the respondents] could have formed a view that they were entitled prior to 30 January 2019 to give this notice. Even if [the respondents] believed they were not in breach of their obligations in cl 2.3 [sic - meaning cl 2.4] of [the SPA], what was required was to give a notice under cl 2.5 and then, if the matter had not been resolved or the parties had not agreed to an extension of the Completion Date, to give notice after 30 January 2019 that the Agreement ceased to have effect. This is not what occurred. [334] - [337].
The test is whether the conduct of one party is such as to convey to a reasonable person, in the situation of the other party, renunciation either of the contract as a whole or of a fundamental obligation under it.[66]
(a) the party evinces an intention no longer to be bound by the contract; or
>
> (b) the party shows that it intends to perform the contract only in a manner substantially inconsistent with its obligations and not in any other way.[67]
In the present case, without taking [the purchasers'] conduct generally into account, [the vendors'] contention, that [the purchasers] had repudiated, would be a difficult one. So far from repudiating the contract, [the purchasers] were relying on it and invoking one of its provisions, to which both parties had given their consent. And unless the invocation of that provision were totally abusive, or lacking in good faith, (neither of which is contended for), the fact that it has proved to be wrong in law cannot turn it into a repudiation.[89]
[I]t would be a regrettable development of the law of contract to hold that a party who bona fide relies upon an express stipulation in a contract in order to rescind or terminate a contract should, by that fact alone, be treated as having repudiated his contractual obligations if he turns out to be mistaken as to his rights. Repudiation is a drastic conclusion which should only be held to arise in clear cases of a refusal, in a matter going to the root of the contract, to perform contractual obligations. To uphold [the vendors'] contentions in this case would represent an undesirable extension of the doctrine.[92]
Where one party, honestly but erroneously, intimates to the other reliance upon a term of the contract which, if properly applicable, would entitle him lawfully to rescind the contract, in circumstances which do not and are not reasonably understood to infer that he will refuse to perform his obligations even if it should be established that he is not so entitled, legal proceedings to decide that issue being in contemplation, I do not consider it in accordance with ordinary concepts of justice that the other party should be allowed to treat such conduct as a repudiation. Nor, in my opinion, are there any considerations of convenience which favour that course.[95]
No doubt there are cases in which a party, by insisting on an incorrect interpretation of a contract, evinces an intention that he will not perform the contract according to its terms. But there are other cases in which a party, though asserting a wrong view of a contract because he believes it to be correct, is willing to perform the contract according to its tenor. He may be willing to recognise his heresy once the true doctrine is enunciated or he may be willing to accept an authoritative exposition of the correct interpretation. In either event an intention to repudiate the contract could not be attributed to him.[101]
In this case [the vendor] acted on its view of the contract without realising that [the purchasers] were insisting upon a different view until such time as they purported to rescind. It was not a case in which any attempt was made to persuade [the vendor] of the error of its ways or indeed to give it any opportunity to reconsider its position in the light of an assertion of the correct interpretation. There is therefore no basis on which one can infer that [the vendor] was persisting in its interpretation willy nilly in the face of a clear enunciation of the true agreement.[103]
The distinctions drawn in the cases may be summarised as follows:
(a) acts (or threatens to act) unilaterally on the basis of the interpretation; or
(b) persists in the interpretation in the face of communications from party B pointing out the error.[109] (citations omitted)
(a) the construction adopted by the defaulting party is clearly or obviously 'untenable'[112] - conduct or threatened conduct which cannot reasonably be justified by the terms of the contract may be such as to convey to a reasonable person in the position of the other party a renunciation of the contract or of a fundamental obligation under the contract; or
>
> (b) the erroneous construction adopted by the defaulting party is maintained steadfastly despite correction.[113] In other words the defaulting party is not 'open to correction'.[114]
A party must promptly notify the other parties in writing if it becomes aware that any of the conditions in clauses 2.2 through 2.3 are satisfied or become incapable of being satisfied [cl 2.5].
If the conditions in clauses 2.2 through 2.3 are not fulfilled before 30 January 2019 then, this agreement shall cease to have effect and thereafter no party shall have any claim of any nature against the other in relation to this agreement [cl 2.7].
Zilkens Lawyers, on behalf of [the respondents], relied upon the statements made to them by Larks [sic] Lawyers, pleaded in sub-paragraphs 19.3(a) to 19.3(d) above, and gave [the appellant] the notice, by their letter, dated 17 January 2019, in the bona fide belief that Larks [sic] Lawyers' statements were correct and reflected the view of [the appellant] and that it followed therefrom, that clauses 2.5 and 2.7 of [the SPA] applied.[125] (emphasis added)
Disposition: cross-appeal ground 2 - whether appellant also in breach of the cl 2.4 'best endeavours' obligation
Objectively viewed, I consider that the information provided by [the appellant] by 2.01 pm on 15 January 2019 was sufficient information for [the respondents] to finalise the notice of meeting and explanatory statement. This information was to the effect that the financial assistance being provided by Rexwells was a guarantee and security over all of its assets, the total of the loan was $4 million, and that the security included not only the assets of Rexwells but a property to the value of $4 million (although details of the specific property were not provided) together with a term deposit of $1 million. On the face of this information, these securities were more than sufficient to secure repayment of the loan.
While I accept that this information was provided at a relatively late stage, there was still sufficient time between the provision of this information and the deadline for the lodgement of documents with ASIC for [the respondents], using their best endeavours, to consider this material and finalise the necessary documents. Had [the respondents] finalised the notice of meeting and explanatory statement on the afternoon of 15 January 2019 and lodged these documents with ASIC either that day or the following morning, the financial assistance clause could have been complied with to enable completion to occur on 31 January 2019.
For these reasons, I am not satisfied on the balance of probabilities that [the appellant] failed to use their [sic] best endeavours to satisfy cl 2.3 of the Agreement [293] - [295].
The sequence for consideration of the remaining issues before the court
Disposition: grounds 1 - 13 - the appellant's measure of damage
The appellant's measure of damage - the expert evidence
For practical purposes, I assume that [the appellant] holds its investment in Rexwells for a period of ten years at which time the investment will be sold at a price using the same implied earnings multiple that applied to [the appellant's] purchase of Rexwells. This is a convenience recognising that the discount applying after ten years in the net present value calculation results in variations in this assumption not being material for the purpose of this report.[157] (emphasis added)
The appellant's measure of damage - the parties' submissions
The appellant's measure of damage - an initial observation
The appellant's measure of damage - the general compensatory principle
[W]here a party sustains loss by reason of a breach of contract, he is, so far as money can do it, to be placed in the same situation, with respect to damages, as if the contract had been performed.[175]
[S]tatements of subsidiary principle framed in the context of working out the ruling principle in standard categories of case must be approached with circumspection. There is, as has often been pointed out, 'a danger in elevating into general principles what are in truth mere applications to particular facts or situations of the overriding general principle'. The measure appropriate in a particular case 'cannot be divorced from the [claimant's] personal position and obligations, both legal and moral, or from what the [claimant] ought reasonably to do by way of mitigation', and a rigid distinction cannot always be drawn between measure and mitigation.[193] (citations omitted)
In the case of non-delivery, where the purchaser does not get the goods he purchased, it is assumed that these would be worth to him, if he had them, what they would fetch in the open market; and that, if he wanted to get others in their stead, he could obtain them in that market at that price.[195]
One key qualification of the rule which prevents it from being inflexible is that the test depends not on the difference between price and 'market value', but price and 'real value' or 'fair value' or 'fair or real value' or 'intrinsic' value or 'true value' or 'actual value' or what the asset was 'truly worth' or 'really worth' or 'what would have been a fair price to be paid ... in the circumstances ... at the time of the purchase'. This distinction is sometimes difficult to draw, but it is old and fundamental.[198] (citations omitted)
The difference between the price paid and the actual value at the time of purchase should reflect the future profitability or unprofitability of the business because the actual value of the business at the time of purchase must depend upon its potential as well as its present returns ... If, as prima facie it is, the subsequent profitability or unprofitability of the business is to be taken into account in the calculation of its actual value at the time of purchase, then care must be exercised in the calculation of consequential losses to ensure that the same ground is not covered twice.[200]
[T]here is substituted by implication of law for the primary obligations of the party in default which remain unperformed a secondary obligation to pay monetary compensation to the other party for the loss sustained by him in consequence of their non-performance in the future.[203]
Rules which operate satisfactorily in cases where purchasers have not paid money, cannot be applied automatically to cases where purchasers have paid money for what has not been delivered to them.[214]
But, in my opinion, there could be circumstances which would require that the purchaser be held entitled to some loss of profits in addition to an amount measured by the difference between the contract price and the value ... at the date of breach, if those circumstances were capable of being regarded as within the contemplation of the parties.
In my opinion the error that is contained in the argument for the appellant consists in treating rules which constitute useful guidance in the ascertainment of damages as rigid rules of universal application, instead of treating them as prima facie rules which may be displaced or modified whenever it is necessary to do so in order to achieve a result which provides reasonable compensation for a breach of contract without imposing a liability upon the other party exceeding that which he could fairly be regarded as having contemplated and been willing to accept.[216]
The appellant's measure of damage - consideration and determination
[T]he proper measure of the appellant's damages, based on its loss in not receiving the share in the second respondent [sic - meaning Rexwells], was the difference between the purchase price and the 'true' value of the share, calculated or assessed on the basis of the discounted net present value of the second respondent's [sic - meaning Rexwells'] future profits over a term of 10 years plus its residual value.
[T]he quantum of the net profit, after tax, likely to have been generated by the business operated by Rexwells, from and including 1 February 2019, for a 10 year period.[227]
Disposition: grounds 14 - 17 - the alleged quantification errors
Ground 14: disallowance of adjustment to future profits by annual 5% growth
In providing your opinions ... please make the following assumptions:
...
Ground 15: disallowance of residual value of Rexwells' share after 10 years
While I accept that at the end of the 10-year period, there is a business which has a value, there was insufficient evidence before me on which I could be satisfied that the method by which Mr Honey calculated this value was correct. I also note that this assumption is inconsistent with the evidence of Mr Leaman that he intended to own the business indefinitely. On this basis, I do not consider that any allowance should be included in the calculation of [the appellant's] loss for its receipt of any amount from the potential sale of Rexwells.[260]
Ground 16: disallowance of future profits after 5 years
[COUNSEL FOR THE RESPONDENTS]: ... Now, Mr Hockley, you mentioned that the - I believe you mentioned the mining services industry is a volatile industry. In that industry, what time period do you consider you could make predictions for with any level of confidence?
WITNESS, HOCKLEY: I - I guess, forecasting for any business, regardless of whether it's the mining services industry, that the further you go out, the more - the more guess - you know, guess work, effectively, that is involved. Ordinarily, I think you couldn't look any more than, say, three - three to five years at the absolute maximum. And certainly, in mining services I think any more than three years would be very problematic, given the volatility of the business.[272]
In relation to the work that has been done, I haven't turned my mind to that issue for two reasons: (1) is, I wasn't asked to address that specific question, and, (2) if I was asked to address that specific question I wouldn't hold out that I have the expertise to talk about volatility in the mining industry - the mining services industry over a period of 10 years.[274]
Ground 17: expert evidence as to franking credits irrelevant to determination
Disposition: notice of contention points and cross-appeal ground 3
Notice of contention grounds 1 - 3: the contingency arising in relation to the Rio Tinto contract
It was certainly a clause that was put there to my benefit. And I had not actually finalised my opinion at that stage, because - if I may explain why, if that's okay - Mr Steele was in long negotiations with Rio about increasing the size of the agreement. From recollection, Rio were in the process, through India, of adding more than 750 new inventory lines to the agreement that they were going to be placing to make, potentially, future purchases for from Rexwells. My experience is that Rio don't start having those conversations with people unless they have an intention of keeping the relationship.[289] (emphasis added)
My answer was, 'Obviously I need to make that decision at the time but my inkling is, yes, I'm getting more comfort as days go by.' I think it's important to understand that what these contracts - which is the incorrect term - are and how they roll forward.[293] (emphasis added)
What I mean is that they are not actually a true contract as in a mutual obligation on - on each party. It is more an agreement to supply that is very one-sided whereby the document is not reissued as a new document on its anniversary. It merely has the expiration date changed in Rio's purchasing system in India or London, wherever the main system is at that time.[294]
The agreement is extended so that settlement shows 31st Jan, but final completion (payments, Rio etc) can be extended without penalty for 30 days. There is still the issue around the possible Rio delay, and we would like to get some advice/ideas on how best to accommodate for this.[299]
The Rio agreement isnt [sic] a problem its [sic] just time and I can show communication line with us moving towards an outcome.[300]
Lark's [sic] are expecting to get a modified contract, with tracked changes, to me today. The only change in it that you won't be expecting to see is that Larks are wanting to delete Rio being a condition of the sale. They felt that with everything that both side [sic] have been through so far the idea of putting more conditions around Rio would just put more undue pressure on yourself. Their idea is to delete that clause and then have us simply not put a signature on it [ie the replacement contract] until Rio have renewed the price agreement.[305] (emphasis added)
Are you saying they didn't give you that advice?---The words should read 'the idea is to delete the clause'. It was my idea, which, as I started, Mr Lark told me that, 'You don't get to do that'.
So they say, 'Their idea is to delete that clause and then have us simply not put a signature on it'. You're saying they didn't give you that advice?---Peter Lark did definitely not give me that advice.
Are you saying this is untruthful?---I've got a typo in there; yes.
Sorry. So explain to me what the typo is?---I believe the word 'their', t-h-e-i-r, being the ownership 'their', should read the word 'the'.
Should read 'the'?---The word 'the'.
Okay. So let's go back. 'The only changes that you won't be expecting to see is that Larks are wanting'. Now, did you want to change the word 'Lark' there at all? Should we write something else for 'Larks' there?---No, I don't believe you should.
Okay. So:
Larks are wanting to delete Rio being a condition of the sale. They -
should that be 'the' or is 'they' correct there?---'They felt'. That is correct.
That's correct. So:
They felt that everything that both sides had been through so far, the idea of putting more conditions around Rio would just put more undue pressure on yourself. Their idea -
it's clear you're saying it's Lark's idea, Mr Leaman?---It does read that way, yes.
Yes. And you saying now they didn't tell you to do that?---No, Mr Lark actually did the opposite of that.
So he said, 'Just take out the condition precedent. Rio is vital to you but that's fine. Just sign the agreement and pay the money and don't worry. If you don't get Rio, you don't get Rio'. Is that what - was that the advice?---No. That would be silly advice.
Well, he deleted it so what was going to happen there?---We had - already had conversations around it and the conversations were - - -[307]
Notice of contention ground 4: whether the appellant failed to mitigate
[I]t is clear that [the appellant] still wants to purchase the shares but:
(a) may require different payment terms in order to be able to settle under [the SPA]; and/or
(b) wants more favourable terms than what was agreed in [the SPA].
It appears to us that [the appellant] is advantageously seizing on the wording of Zilkens Lawyers' letter to manufacture an artificial legal position in order to achieve this.[315]
Accordingly, [the respondents] make the following open offer to [the appellant]:
(a) the parties treat [the SPA] as on foot with the variations referred to in (b) and (c) below (or execute a further agreement on the same terms and conditions except as provided in paragraph (b) and (c) below);
(b) the purchase price payable at completion is reduced by $400,000.00; and
(c) the parties proceed to completion on 28 February 2019.
We note that if [the appellant] requires further time to complete (beyond the extended completion date of 28 February 2019 proposed above), [the respondents] will entertain reasonable offers for such an extension.
This offer is open for acceptance by [the appellant] until 4pm on 22 February 2019. If it is not accepted by that time it is automatically withdrawn.[317] (original emphasis)
We have concerns around handover and performance of obligations. We need a tangible and real retention to support this. Please provide your retention offer. Please understand we are not asking to change the purchase price with this concern, but that we need a retention value for a period of time.[339]
Ground 17 and notice of contention ground 5: the dividend distribution and franking credit issue
[A]s was submitted by [the respondents], the calculation that was undertaken by the experts considered the net present value of the likely net profits of Rexwells. Neither of the experts expressed an opinion of [sic] the calculation of the loss of [the appellant]. Counsel for [the appellant] accepted this was the case but disputed the assessment was materially different. This was because [the appellant] intended that Rexwells would distribute its profit by way of franked dividends to [the appellant], a corporation. While I accept this may be the case, there was no evidence of the extent of any franking credits or whether it was possible or likely for Rexwells to pay all dividends as fully franked dividends [441]. (original emphasis)
Cross-appeal ground 3: the amount of the deduction on account of Mr Steele's replacement
While I accept, consistent with the views expressed by both experts, that it would be standard valuation practice to include an allowance for a salary of the business owner in the valuation of the business, this was not the task that the experts were asked to do. Neither of the experts purported to give an opinion as to the valuation of Rexwells as at 31 January 2019 (or 22 January 2019). Mr Hockley ultimately accepted that this was irrelevant to the task they had been asked to perform.
I accept Mr Leaman's evidence that he did not intend to employ anyone to replace Mr Steele. I also accept, consistent with Mr Hockley's [sic] evidence, that Mr Leaman would have taken any payments from the business in dividends as opposed to salary. For these reasons, I consider that a deduction of only $50,000 should be made from the gross profit for the costs associated with Mr Steele and that a further deduction of a full salary of $200,000 should not be made.[352]
(a) The appeal is allowed in part.
>
> (b) The cross-appeal is allowed in part.
>
> (c) Paragraphs 1 - 3 of the order of the Supreme Court of Western Australia made 16 December 2022 in action CIV/1323/2019 are set aside.
>
> (d) The proceedings in action CIV/1323/2019 are remitted to Hill J in the General Division of the Supreme Court of Western Australia for a rehearing and final determination in accordance with the reasons of this court.
>
> (e) The rehearing before Hill J proceed on the evidence adduced at the trial of the proceedings before her Honour on 24, 27 - 31 July 2020 and 20 August 2020 together with such further evidence as her Honour may admit limited to the outstanding issues for determination as described in the reasons of this court.
>
> (f) The appellant's application in an appeal dated 20 September 2024 is dismissed.
(a) The appellant has leave to appeal against the orders of the Supreme Court of Western Australia made 23 March 2023 in action CIV/1323/2019 if and to the extent that leave to appeal is required.
>
> (b) The appeal is allowed.
>
> (c) The orders of the Supreme Court of Western Australia made 23 March 2023 in action CIV/1323/2019 are set aside.
Annexure: grounds of appeal, notice of contention and grounds of cross‑appeal Grounds of cross-appeal
1.1 the primary judge accepted that, as at 4.47 pm on 17 January 2019, when the Letter was sent[364], it was not possible for cl 2.3 of the Agreement[365] to be complied with to enable completion to occur on 31 January 2019;
1.2 the primary judge accepted that, at or about the time the Letter was sent, the parties were obliged under cl 2.5 of the Agreement[366] to give notice that they believed cl 2.3 was incapable of being satisfied prior to completion.[367]
1.3 the primary judge placed reliance on the Letter asserting the respondents' view as a fact and not seeking to discuss what was required by cl 2.3 of the Agreement,[368] instead of the primary judge asking and determining:
1.3.1 whether there was an honest apprehension by the respondents as to the terms of the Agreement;
1.3.2 whether the respondents had acted otherwise than in accordance with a bona fide belief as to the correctness of the interpretation which they sought to place upon the Agreement;
1.3.3 whether the respondents' apprehension as to the terms of the Agreement were open to correction; and
1.3.4 whether any attempt was made by the appellant, CH Leaman Investments Pty Ltd, (CH Leaman) to persuade the respondents of the error of their ways or give them any opportunity to reconsider their position in the light of an assertion of the correct interpretation.
1.4 the primary judge relied, in error, upon there being nothing in the Letter which suggested the respondents were prepared to perform their obligations under the Agreement, even if they were wrong in their construction of its terms;[369] and
1.5 the primary judge found, in error, that whether the respondents believed that their action in giving notice of termination under the Letter was justified by the terms of the Agreement was not relevant because the test of whether conduct is repudiatory or a renunciation is objective.[370]
The primary judge ought to have found that the respondents did not, by the Letter, renunciate the Agreement, in that:
1.6 there was an honest apprehension by the respondents as to the terms of the Agreement;
1.7 the respondents had not acted otherwise than in accordance with a bona fide belief as to the correctness of the interpretation which they sought to place upon the Agreement;
1.8 the respondents' apprehension as to the terms of the Agreement were open to correction;
1.9 no attempt was made by CH Leaman to persuade the respondents of the error of their ways or give them any opportunity to reconsider their position in the light of an assertion of the correct interpretation; and
1.10 the contents of the Letter did not, in the circumstances, evince an intention, which would convey to a reasonable person, in the situation of CH Leaman, no longer to be bound by the terms of the Agreement.
2.1 The primary judge failed to take into account, or give sufficient weight to, the following circumstances:
2.1.1 on 7 November 2018 and 13 November 2018, Peter Lark, of Lark Lawyers, CH Leaman's then solicitors, said to Sidd Jain and Alex Zilkens, respectively, of Zilkens Lawyers, the respondents' then solicitors, that he, or his firm, would draft the financial assistance documents;
2.1.2 by 9 January 2019, Mr Lark and Lark Lawyers had taken no steps to prepare the financial assistance documents;
2.1.3 on 9 January 2019, Lark Lawyers notified Zilkens Lawyers, as if Zilkens Lawyers were to draft the financial assistance documents, that CH Leaman expects to be able to service and repay the borrowings, referring to the $4m loan from NAB which CH Leaman was using to fund the purchase price for the share in Rexwells under the Agreement;[373]
2.1.4 after a telephone conversation and email correspondence between Lark Lawyers and Zilkens Lawyers, it was agreed, as originally arranged, that Lark Lawyers would prepare the financial assistance documents;[374]
2.1.5 on 11 January 2019, Zilkens Lawyers sent draft financial assistance documents to Zilkens Lawyers;[375]
2.1.6 Lark Lawyer's [sic] email of 11 January 2019 warned that the requisite documents had to be duly completed and lodged with ASIC by no later than 15 January 2019;[376]
2.1.7 the draft resolution of the third respondent, Mr Steele, as the sole director of the first respondent, Tuesday Enterprises Pty Ltd (Tuesday Ents), prepared by Lark Lawyers, to approve it resolving to approve the provision by Rexwells Corporations Pty Ltd (Rexwells) of financial assistance to CH Leaman, provided that the financial assistance transaction did not lead to any solvency concerns for Rexwells;[377]
2.1.8 the draft resolution of the sole shareholder of Rexwells, Tuesday Ents, to approve the provision of financial assistance by Rexwells to CH Leaman, prepared by Lark Lawyers, provided that the financial assistance transaction did not lead to any solvency concerns for Rexwells and for it to be passed in accordance with s 260B(1)(a) of the Corporations Act 2001 (Cth) (Act) as a special resolution;[378]
2.1.9 the draft disclosure statement, in accordance with s 260B(4) of the Act, prepared by Lark Lawyers, provided that the transactions did not lead to any solvency concerns for Rexwells and [t]o the best of the knowledge and belief of Tuesday Enterprises, the proposed financial assistance to be provided by Rexwells would not materially prejudice Rexwell's [sic] ability to pay its creditors;[379]
2.1.10 the condition in clause 2.3 of the Agreement[380] required approval by the shareholders under s 260B of the Act and s 260B(1)(b) did not require a special resolution or any issues as to solvency or prejudice to creditors to be resolved and the primary judge found that the requisite documents had to be duly completed and lodged with ASIC by no later than 17 January 2019, rather than 15 January 2019;[381]
2.1.11 on 14 January 2019, Zilkens Lawyers sought financial information from CH Leaman in order for the respondents and Rexwells to determine whether the provision of financial assistance by Rexwells would materially prejudice the ability of Rexwells to pay its creditors, as they were enjoined to do by Lark Lawyers' draft documents;[382]
2.1.12 on 15 January 2019, the date Lark Lawyers had previously said was the deadline for completing and lodging the documents with ASIC, Lark Lawyers told Zilkens Lawyers that CH Leaman expected NAB to be flexible with regard to repayments under their $4m loan until Rexwells' income reached a sustainable level; the security which NAB was taking; if additional funds were required, they would be sourced from CH Leaman's other resources; and the documents had to be lodged with ASIC that day and the resolution passed the next day;[383]
2.1.13 in relation to the finding at J [293], the explanation, on 16 January 2019, provided by Zilkens Lawyers, of the continuing concerns of the respondents and why the financial information provided by CH Leaman was inadequate; and the request for further information from CH Leaman to enable the respondents and Rexwells to form the requisite view (required according to Lark Lawyers) as to the absence of prejudice to Rexwells' ability to pay its creditors;[384]
2.1.14 on 17 January 2019, in lieu of providing further information, which it was said would take too long,[385] despite CH Leaman having just secured a $4m loan from NAB, Lark Lawyers sent to Zilkens Lawyers an indemnity from CH Leaman and Mr Leaman for Mr Steele. The recitals to the draft indemnity deed provided that the Act required that, before financial assistance was provided, it had to be approved by the members of the company on the basis that the proposed financial assistance would not materially prejudice the company's ability to pay its creditors and that Mr Steele was so satisfied on the information provided to him;[386]
2.1.15 Mr Pocock, of Lark Lawyers, gave evidence that his understanding, when he drafted the recitals to the draft indemnity deed, was that it would be inappropriate for Tuesday Ents to pass a resolution approving the provision of financial assistance, unless Mr Steele was satisfied that the proposed financial assistance would not materially prejudice Rexwells' ability to pay its creditors;[387] and
2.1.16 Mr Leaman and Lark Lawyers knew that Zilkens Lawyers and Mr Steele were relying on Lark Lawyers to guide them through the s 260B process.[388]
1.1 the difference between the purchase price and the 'true' value of the asset the subject of the contract;
1.2 alternatively, on the facts as found by the primary judge, the discounted net present value of future profits of the second respondent over a term of 10 years plus its residual value, less expenses (including the purchase price contained in the Agreement) that would have been incurred by the appellant had the Agreement been performed.
3.1 in determining the proper measure of damages, the Court was required to be flexible and identify an appropriate amount to place the injured party in the position it would have been in had the contract been fully performed and thus the Court was required to identify the actual loss suffered by the innocent party; and
3.2 the proper measure of damages in the present case was the difference between the purchase price and the 'true' value of the share at the date of termination;
3.3 in the alternative to paragraph 3.2 above, the appropriate measure of damages was the discounted net present value of the second respondent's future profits over a term of 10 years plus its residual value, less expenses (including the purchase price contained in the Agreement) that would have been incurred by the appellant had the Agreement been performed.
4.1 the proper measure of the appellant's damages, based on its loss in not receiving the share in the second respondent, was the difference between the purchase price and the 'true' value of the share, calculated or assessed on the basis of the discounted net present value of the second respondent's future profits over a term of 10 years plus its residual value; alternatively
4.2 the proper measure of the appellant's damages was the discounted net present value of the second respondent's future profits over a term of 10 years plus its residual value, less expenses (including the purchase price contained in the Agreement) that would have been incurred by the appellant had the Agreement been performed.
6.1 consistent with her Honour's observations in [425], that a loss of profits was an appropriate measure of damages; and
6.2 in the absence of any evidence as to an alternate use of the purchase funds (for which the primary judge should have held the defendants bore an evidential onus to adduce), there should be no reduction to the calculation of the appellant's losses.
9.1 as the share in the second respondent was not fungible and there was no market for the share, the appropriate measure of damages was the difference between the purchase price and the 'true' value of the business, valued by a discounted net present value of future profits of the second respondent over a 10 year period, plus its residual value;
9.2 in the alternative to 9.1 above, as the share in the second respondent was not fungible and there was no market for the share, the appropriate measure of damages was the discounted net present value of future profits of the second respondent over 10 years plus its residual value, less expenses (including the purchase price contained in the Agreement) that would have been incurred by the appellant had the Agreement been performed.
9.3 as there was no evidence of an alternative business purchased by the appellant, no deduction should be made from the true value of the second respondent; alternatively no deduction should be made from the discounted net present value of future profits of the second respondent;
9.4 the Court was satisfied by the evidence before it that the appellant had discharged its onus to prove its damages (on the basis of either the measure of damages outlined in 9.1, alternatively 9.2) beyond nominal damages;
9.5 the appellant correctly sought and proved its damages on the basis set out in 9.1, alternatively 9.2 above, to the exclusion of claiming any wasted expenditure, as it would not be entitled to recover both.
12.1 a determination of market value of the share in the second respondent was neither possible on the facts, nor a relevant consideration in determining the proper measure of damages; and
12.2 the expert evidence was relevant to determining either the true value of the share of the second respondent, alternatively the discounted net present value of the second respondent's future profits over a term of 10 years plus its residual value, less expenses (including the purchase price contained in the Agreement) that would have been incurred by the appellant had the Agreement been performed.
13.1 a determination of market value of the share in the second respondent was neither possible on the facts, nor a relevant consideration in determining the proper measure of damages;
13.2 the proper measure of damages was the difference between the purchase price and the 'true' value of the share in the second respondent;
13.3 in the alternative to paragraph 13.2 above, the proper measure of damages was the discounted net present value of the second respondent's future profits over a term of 10 years plus its residual value, less expenses (including the purchase price contained in the Agreement) that would have been incurred by the appellant had the Agreement been performed;
13.4 the expert evidence adduced by both parties was sufficient to determine the appellant's damages based on the measures outlined in either paragraph 13.2 or 13.3 above.
(a) The appellant provided particulars of the loss and damage it pleaded it had suffered, as a result of the termination of the Agreement, namely, that it had lost the opportunity to acquire all of the issued shares in Rexwells and thereby the benefit of owning the shares.[389]
(b) The appellant further particularised the value of the loss and damage it alleged it suffered, as a result of the termination of the Agreement, in the following respects:
(i) it lost the likely net present value, as at 22 January 2019, (the date of notice of termination)[390] of the likely future profit of Rexwells from 1 February 2019 (the completion date under the Agreement was 31 January 2019)[391] for a period of 10 years, 'if the sale had been completed in accordance with the' (emphasis added) Agreement;[392]
(ii) plus the residual capital value of Rexwells at the end of the 10[-]year period;
(iii) less the purchase price under the Agreement;
(iv) less bank financing and financing costs; and
(v) less the appellant's investment.
(c) Completion of the Agreement was subject to and conditional upon, inter alia, the appellant being satisfied, at its absolute discretion, that a new contract had been entered into by Rexwells with Rio Tinto Ltd (Rio Tinto) on terms acceptable to the appellant, at its sole discretion (Condition Precedent).[393]
(d) The respondents raised in opening address,[394] in cross‑examination[395] and in their written[396] and oral[397] closing submissions, for determination the issue of whether or not the sale of the share in Rexwells pursuant to the Agreement would have completed, but for the appellant's termination of the Agreement.[398] The appellant itself, in its opening address, stressed the importance of the fact that Rexwells had not entered into the Rio Tinto contract when the parties were trying to resurrect the Agreement after the notice of termination had been issued by the appellant.[399]
(e) The primary judge found, in effect, that an issue for determination was whether the appellant had lost the opportunity it relied upon and that such opportunity had some value, with particular reference to the Rio Tinto contract.[400]
(f) The primary judge failed to determine the issue of whether, pursuant to the Agreement, the sale of the share in Rexwells would have completed, or what contingency should be applied in that regard, but for the appellant's termination of the Agreement.
2.1 the Condition Precedent would not have been fulfilled, but for the termination of the Agreement;
2.2 had the appellant proved that it had suffered any loss as a result of a loss of opportunity, or otherwise as a result of the termination of the Agreement, the primary judge was required to take into account, in the assessment of damages, the contingency in relation to the non‑fulfilment of the Condition Precedent; and
2.3 had the appellant proved that it had suffered any loss as a result of a loss of opportunity, or otherwise as a result of the termination of the Agreement, the contingency in relation to the non‑fulfilment of the Condition Precedent was so certain to occur, that no damages should be awarded to the appellant, other than nominal damages.
3.1 The primary judge stated at J [435] that her Honour accepted the evidence of Mr Leaman that he did not intend to employ anyone to replace Mr Steele in the Business.[407] The primary judge relied upon exh 1.108E for the finding, which did not support it.
3.2 The primary judge also stated at J [435] that her Honour accepted that Mr Leaman would have taken payments from the Business in the form of dividends as opposed to a full salary.
3.3 In making those findings, the primary judge appeared to accept the assumption made by CH Leaman's expert, Mr Barry Honey,[408] that Mr Leaman would have himself replaced Mr Steele in the Business and taken payments from the Business in the form of dividends. There was no evidence to either of those effects. Such evidence as there was to the latter effect, which the primary judge failed to take into account, was that Mr Leaman intended to expand Rexwells' business and, for that purpose, reinvest profits and distribute relatively nominal dividends.[409]
3.4 In finding that a deduction of only $50,000.00 should be made for the employment of Mr Leaman in the Business the primary judge erred because:
(a) there was no evidence supporting the findings referred to in sub‑paragraphs 3.1 and 3.2 above;
(b) there was no evidence supporting the assumption made by Mr Honey, referred to in sub‑paragraph 3.3 above, which assumption appeared to underpin the primary judge's findings referred to in sub‑paragraphs 3.1 and 3.2 above;
(c) in any event, the question of the loss suffered by CH Leaman, by reason of the Agreement having been renunciated (if the Court so finds), by the respondents, is to be assessed objectively and the findings referred to in sub‑paragraphs 3.1 to 3.3 above are subjective matters and ought not to have been taken into account by the primary judge.
I certify that the preceding paragraph(s) comprise the reasons for decision of the Supreme Court of Western Australia.
[1] C H Leaman Investments Pty Ltd v Tuesday Enterprises Pty Ltd [2022] WASC 447 (primary reasons).
[2] C H Leaman Investments Pty Ltd v Tuesday Enterprises Pty Ltd [2022] WASC 447 (S) [51.1].
[10] The legislative history is discussed in Connective Services Pty Ltd v Slea Pty Ltd [2019] HCA 33; (2019) 267 CLR 461 [9] - [20].
[15] Austin and Black's Annotations to the Corporations Act [2J.260A].
[16] Appeal ts 152, 171 - 172. See primary reasons [296] - [319].
[17] Peters' American Delicacy Co Ltd v Heath [1939] HCA 2; (1939) 61 CLR 457, 481 - 482, 504.
[18] Corporations Act s 588G(1A) item 6.
[21] Amended statement of claim dated 9 March 2020 (ASC) par 23(a) BAB 154.
[22] Appellant's submissions in answer to notice of contention par 7 WAB 175.
[23] Appellant's submissions par 7 WAB 24.
[24] Appellant's submissions par 57 WAB 35.
[25] ASC pars 23(b) - (f) BAB 154 - 156; appellant's further and better particulars of loss and damage dated 2 July 2020 BAB 157 - 172.
[26] Respondents' outline of closing submissions pars 1.4, 137 - 149 BAB 272, 304 - 306.
[28] Appellant's closing submissions pars 121 - 123 BAB 256 - 257.
[29] Wenham v Ella [1972] HCA 43; (1972) 127 CLR 454.
[30] Compare Supreme Court (Court of Appeal) Rules 2005 (WA) r 32(4)(b), r 33(7).
[31] Respondents' grounds of cross-appeal WAB 215.
[33] Appeal ts 121, 152, 171 - 172, 175, 191.
[35] Primary reasons [421] - [431].
[36] Appellant's submissions pars 15 - 16 WAB 26 - 27.
[37] Supreme Court (Court of Appeal) Rules r 32(5)(a).
[41] Primary reasons [320] - [337]. But see also primary reasons [5](b), [339], [481].
[42] Primary reasons [129] - [193].
[43] Primary reasons [233] - [319].
[46] Primary reasons [304] - [305].
[48] Primary reasons [305] - [310].
[51] Primary reasons [321] - [326].
[52] Woodar Investment Development Ltd v Wimpey Construction UK Ltd [1980] UKHL 11; [1980] 1 WLR 277.
[54] Appeal ts 158. See also respondents' submissions on the cross-appeal par 10 WAB 224.
[55] Primary reasons [328] - [332].
[59] Primary reasons [5](b), [339], [481].
[61] James Shaffer Ltd v Findlay Durham & Brodie [1953] 1 WLR 106, 120 - 121, 123.
[62] Woodar Investment Development Ltd v Wimpey Construction UK Ltd (283).
[63] See respondents' submissions on the cross-appeal pars 15 - 35, 38 - 44 WAB 226 - 231, 232 - 233.
[64] Appellant's amended statement of claim dated 9 March 2019 par 21 BAB 153.
[65] Koompahtoo Local Aboriginal Land Council v Sanpine Pty Ltd [2007] HCA 61; (2007) 233 CLR 115 [44].
[66] Koompahtoo Local Aboriginal Land Council v Sanpine Pty Ltd [44].
[67] Shevill v Builders Licensing Board [1982] HCA 47; (1982) 149 CLR 620, 625 ‑ 626; Progressive Mailing House Pty Ltd v Tabali Pty Ltd [1985] HCA 14; (1985) 157 CLR 17, 33, 40; Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd [1989] HCA 23; (1989) 166 CLR 623, 634, 643, 647 ‑ 648, 658, 666.
[68] Woodar Investment Development Ltd v Wimpey Construction UK Ltd (281), (294).
[69] Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd (648), (657 - 658); Koompahtoo Local Aboriginal Land Council v Sanpine Pty Ltd [44].
[70] Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd (647), (657).
[71] Ross T Smyth & Co Ltd v T D Bailey Son & Co [1940] 3 All ER 60, 71. See also: Woodar Investment Development Ltd v Wimpey Construction UK Ltd (292); Shevill v Builders Licensing Board (633); Progressive Mailing House Pty Ltd v Tabali Pty Ltd (32); Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd (643), (657).
[72] Woodar Investment Development Ltd v Wimpey Construction UK Ltd (280 - 281), (292), (294 - 296), (299); Shevill v Builders Licensing Board (633).
[74] Sopov v Kane Constructions Pty Ltd [2007] VSCA 257; (2007) 20 VR 127 [9]. See also [10] - [17].
[75] See eg R & A Cab Co Ltd v Kotzman [2008] VSCA 68 [49]. Woodar Investment Development Ltd v Wimpey Construction UK Ltd also refers to bona fides: (283).
[78] Ross T Smyth & Co Ltd v T D Bailey, Son & Co (72).
[79] Spettabile Consorzio Veneziano di Armamento e Navigazione v Northumberland Shipbuilding Co Ltd (1919) 121 LT 628.
[80] Sweet & Maxwell Ltd v Universal News Services Ltd [1964] 2 QB 699.
[81] Woodar Investment Development Ltd v Wimpey Construction UK Ltd (283).
[82] James Shaffer Ltd v Findlay Durham & Brodie (118).
[83] James Shaffer Ltd v Findlay Durham & Brodie (121).
[84] James Shaffer Ltd v Findlay Durham & Brodie (123).
[85] James Shaffer Ltd v Findlay Durham & Brodie (126).
[86] James Shaffer Ltd v Findlay Durham & Brodie (124).
[87] Woodar Investment Development Ltd v Wimpey Construction UK Ltd (280), (289 - 290), (292), (294), (298 - 299).
[88] Woodar Investment Development Ltd v Wimpey Construction UK Ltd (291 -292).
[89] Woodar Investment Development Ltd v Wimpey Construction UK Ltd (280).
[90] Woodar Investment Development Ltd v Wimpey Construction UK Ltd (281 - 282).
[91] Woodar Investment Development Ltd v Wimpey Construction UK Ltd (282).
[92] Woodar Investment Development Ltd v Wimpey Construction UK Ltd (283). Compare, however, the contrary observations of Lord Russell of Killowen: (293).
[93] Woodar Investment Development Ltd v Wimpey Construction UK Ltd (296) Lord Keith of Kinkel, (299) Lord Scarman.
[94] Woodar Investment Development Ltd v Wimpey Construction UK Ltd (295 - 296).
[95] Woodar Investment Development Ltd v Wimpey Construction UK Ltd (297).
[96] Woodar Investment Development Ltd v Wimpey Construction UK Ltd (289 - 290).
[97] Woodar Investment Development Ltd v Wimpey Construction UK Ltd (292).
[98] Summers v The Commonwealth [1918] HCA 33; (1918) 25 CLR 144.
[100] DTR Nominees Pty Ltd v Mona Homes Pty Ltd [1978] HCA 12; (1978) 138 CLR 423.
[101] DTR Nominees Pty Ltd v Mona Homes Pty Ltd (432).
[102] DTR Nominees Pty Ltd v Mona Homes Pty Ltd (432).
[103] DTR Nominees Pty Ltd v Mona Homes Pty Ltd (432).
[104] Progressive Mailing House Pty Ltd v Tabali Pty Ltd (37). See also DTR Nominees Pty Ltd v Mona Homes Pty Ltd (432).
[105] DTR Nominees Pty Ltd v Mona Homes Pty Ltd (433).
[106] Green v Sommerville [1979] HCA 60; (1979) 141 CLR 594, 611.
[107] Dainford Ltd v Smith [1985] HCA 23; (1985) 155 CLR 342, 366.
[108] Sopov v Kane Constructions Pty Ltd [7] - [17].
[109] Sopov v Kane Constructions Pty Ltd [17].
[111] DTR Nominees Pty Ltd v Mona Homes Pty Ltd (432).
[112] Sopov v Kane Constructions Pty Ltd [17]. See also [18], [123], [129] - [141], [148]. Compare: James Shaffer Ltd v Findlay Durham & Brodie (118), (123), (126); Woodar Investment Development Ltd v Wimpey Construction UK Ltd (280), (283).
[113] Summers v The Commonwealth (152); DTR Nominees Pty Ltd v Mona Homes Pty Ltd (432).
[114] Ross T Smyth & Co Ltd v T D Bailey, Son & Co (72).
[115] DTR Nominees Pty Ltd v Mona Homes Pty Ltd (432 ‑ 433).
[116] DTR Nominees Pty Ltd v Mona Homes Pty Ltd (432).
[118] Sopov v Kane Constructions Pty Ltd [9] - [11].
[119] See eg: Woodar Investment Development Ltd v Wimpey Construction UK Ltd (280 - 283), (297); DTR Nominees Pty Ltd v Mona Homes Pty Ltd (432 - 433).
[120] Respondents' submissions on the cross-appeal par 14 WAB 226.
[121] Respondents' amended substituted defence dated 9 March 2020 pars 19.4(a) - (b), 21.2(a) BAB 181, 194.
[122] Respondents' amended substituted defence dated 9 March 2020 par 19.4(c) BAB 181.
[123] Respondents' amended substituted defence dated 9 March 2020 par 21.2(c) BAB 195.
[124] Respondents' amended substituted defence dated 9 March 2020 pars 21.2(c) - (d) BAB 195.
[125] Respondents' amended substituted defence dated 9 March 2020 par 21.2(g) BAB 196.
[130] Primary reasons [25], [184].
[131] Primary reasons [25], [188] - [191].
[134] Respondents' submissions on the cross-appeal par 51 WAB 235.
[135] Respondents' submissions on the cross-appeal par 54 WAB 236; particulars to cross-appeal ground 2 WAB 217 - 220. See also appeal ts 172, 175.
[150] See also the discussion in Milburn v Pivot Ltd (1997) 78 FCR 472, 514 - 522.
[152] See eg GAB 692 - 693, 720, 731. This continued to be the case for Mr Honey's calculations in the joint expert report: see eg GAB 1042, 1044, 1060.
[153] See eg GAB 686, 698, 721, 732, 734.
[156] GAB 693 - 699. See also GAB 731 - 737.
[157] GAB 698. See also GAB 721 (note 10), 724 (note 7), 726 (note 7), 732 (note 7), 734 (note 7).
[158] Appellant's submissions par 90 WAB 42.
[159] Appellant's further and better particulars of loss and damage dated 2 July 2020 row 2 (table headed 'Elements of Calculation') BAB 159 - 160.
[160] GAB 1046; primary reasons [433].
[162] GAB 1051; primary reasons [403].
[164] GAB 1046 - 1047; primary reasons [399] - [400].
[165] Hadley v Baxendale (1854) 9 Exch 341, 354; 156 ER 145, 151.
[167] Appellant's submissions par 90 WAB 42.
[168] Appellant's further and better particulars of loss and damage dated 2 July 2020 row 4 (table headed 'Elements of Calculation') and annexure C BAB 162 - 163, 166. Prima facie the $860,000 is understated insofar as annexure C records the $4 million being received at the end of year 1 (ie the year ended 31 January 2020) and therefore being discounted at 20.5% when it should be recorded as having been received at year 0 (ie on 31 January 2019) and thus not being subject to any discount.
[169] Based on the $3.7 million sought on appeal.
[170] Based on the $5.267 million to $6.049 million sought at trial.
[171] Cessnock City Council v 123 259 932 Pty Ltd [2024] HCA 17; (2024) 98 ALJR 719 [49], [61], [127].
[172] Baltic Shipping Co v Dillon [1993] HCA 4; (1993) 176 CLR 344, 367.
[173] Paciocco v Australia & New Zealand Banking Group Ltd [2016] HCA 28; (2016) 258 CLR 525 [283].
[174] Cessnock City Council v 123 259 932 Pty Ltd [7].
[175] Robinson v Harman (1848) 1 Ex Rep 850, 855; [1848] EngR 135; 154 ER 363, 365.
[176] Clark v Macourt [2013] HCA 56; (2013) 253 CLR 1 [109].
[177] The Commonwealth of Australia v Amann Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64, 82; Cessnock City Council v 123 259 932 Pty Ltd [6], [48], [191].
[178] Haines v Bendall [1991] HCA 15; (1991) 172 CLR 60, 63.
[179] See eg Wenham v Ella (460), (471); The Commonwealth of Australia v Amann Aviation Pty Ltd (80), (98), (134), (148), (161); Tabcorp Holdings Ltd v Bowen Investments Pty Ltd [2009] HCA 8; (2009) 236 CLR 272 [13]; Clark v Macourt [7], [26], [60], [106]; Cessnock City Council v 123 259 932 Pty Ltd [6], [48], [117], [190].
[180] See eg Tabcorp Holdings Ltd v Bowen Investments Pty Ltd [13]; Clark v Macourt [60] - [61], [106] ‑ [111], [129] - [130]; Cessnock City Council v 123 259 932 Pty Ltd [6].
[181] See eg The Commonwealth of Australia v Amann Aviation Pty Ltd (116).
[182] Cessnock City Council v 123 259 932 Pty Ltd [7].
[183] Clark v Macourt [10]. See also [25], [111].
[185] J Edelman, McGregor on Damages (22nd ed, 2024) [30-003].
[189] Primary reasons [422], [425].
[190] Primary reasons [427], [430].
[192] Bellgrove v Eldridge [1954] HCA 36; (1954) 90 CLR 613, 617 - 618.
[194] Wertheim v Chicoutimi Pulp Co Ltd [1911] AC 301, 307.
[195] Wertheim v Chicoutimi Pulp Co Ltd (307).
[196] HTW Valuers (Central Qld) Pty Ltd v Astonland Pty Ltd [2004] HCA 54; (2004) 217 CLR 640.
[197] Potts v Miller [1940] HCA 43; (1940) 64 CLR 282.
[198] HTW Valuers (Central Qld) Pty Ltd v Astonland Pty Ltd [36].
[199] HTW Valuers (Central Qld) Pty Ltd v Astonland Pty Ltd [37].
[200] Gould v Vaggelas [1985] HCA 75; (1985) 157 CLR 215, 266 - 267.
[201] A Kramer QC, The Law of Contract Damages (3rd ed, 2022) [1-22].
[202] Photo Production Ltd v Securicor Transport Ltd [1980] UKHL 2; [1980] AC 827.
[203] Photo Production Ltd v Securicor Transport Ltd (849).
[204] Cessnock City Council v 123 259 932 Pty Ltd [120.1].
[206] Primary reasons [424], [430].
[208] Wenham v Ella (461) (Barwick CJ), (462 - 464) (Menzies J), (465), (467) (Walsh J), (471 ‑ 473) (Gibbs J), (474 ‑ 476) (Stephen J).
[210] Tabcorp Holdings Ltd v Bowen Investments Pty Ltd [13] (referring to Radford v De Froberville [1977] 1 WLR 1262, 1273).
[211] Tabcorp Holdings Ltd v Bowen Investments Pty Ltd [13].
[212] Tabcorp Holdings Ltd v Bowen Investments Pty Ltd [13] (referring to Ruxley Electronics and Construction Ltd v Forsyth Laddingford Enclosures Ltd [1994] 1 WLR 650, 655).
[217] Straits Engineering Contracting Pte Ltd v Merteks Pte Ltd [1996] 4 LRC 259.
[219] Primary reasons [422], [425] - [427], [430] - [431].
[222] Although, as to ground 3.2, we consider the assessment of the 'true' or 'real' value of the Rexwells' share ought to be determined as at the date for performance under the SPA rather than the date of termination. This distinction makes no difference to the disposition of the appeal. Both experts performed their net present value calculations as at 31 January 2019 for convenience and agreed that the difference between a calculation as at 22 January 2019 and 31 January 2019 was immaterial: GAB 1051.
[225] Appellant's submissions par 57 WAB 35.
[227] Agreed expert evidence schedule dated 16 December 2019 par 1.1 BAB 226.
[228] GAB 866 pars 1.1, 1.2, 2.1. See also agreed expert evidence schedule dated 16 December 2019 pars 2.1 - 2.3 BAB 226 - 227.
[229] GAB 817 - 819 pars 5 - 11; GAB 842 - 847 pars 128 - 140.
[230] GAB 819 pars 12 - 13; GAB 847 - 853 pars 141 - 169.
[232] The calculation is provided to illustrate the point that it is possible to make the net present value calculation rather than to provide a definitive net present value calculation. The parties have not had the opportunity to consider the arithmetical accuracy of the calculations. This illustration is not intended to foreclose the parties interrogating matters of arithmetical accuracy and bringing them to the attention of the court.
(2019) 267 CLR 461
(1939) 61 CLR 457
(1972) 127 CLR 454
(2007) 233 CLR 115
(1982) 149 CLR 620
(1985) 157 CLR 17
(1989) 166 CLR 623
(2007) 20 VR 127
(1918) 25 CLR 144
(1978) 138 CLR 423
(1979) 141 CLR 594
(1985) 155 CLR 342
(1997) 78 FCR 472
(2024) 98 ALJR 719
(1993) 176 CLR 344
(2016) 258 CLR 525
(2013) 253 CLR 1
(1991) 174 CLR 64
(1991) 172 CLR 60
(2009) 236 CLR 272
(1954) 90 CLR 613
(2004) 217 CLR 640
(1940) 64 CLR 282
(1985) 157 CLR 215