headnote
[This headnote is not to be read as part of the judgment]
The appellant (Bunderra) and the first respondent (Pasminco) own neighbouring parcels of land in the Lake Macquarie area, the "TriPad site" and the "Main site" respectively.
The second respondent (the Council) granted development consent for the subdivision of the TriPad site into 90 residential lots. Condition 16 of the Development Consent required certain stormwater management works to be undertaken.
Two stormwater strategy reports (the August GCA Strategies) were submitted to Council and expressly incorporated into the Development Consent. Relevantly, they provided for the construction of a reinforced concrete pipe under a roadway owned by the Council (Main Road) up to the boundary of Pasminco's property, as part of a future stormwater solution in the event that the Main site was developed.
Condition 1 of the Development Consent provided that the August GCA Strategies could be varied by the conditions of the Development Consent.
A subsequent strategy report (the September GCA Strategy) was prepared for the purpose of satisfying Condition 16 of the Development Consent, namely to provide further information prior to the issue of a construction certificate. It contained amendments to proposed stormwater structures.
The primary judge granted an injunction restraining the Council from issuing a subdivision certificate to Bunderra in respect of the development of the TriPad site until Bunderra constructed the reinforced concrete pipe under Main Road.
The main issues on appeal were:
(i) whether Condition 16 placed an obligation on Bunderra to construct the reinforced concrete pipe under Main Road;
(ii) whether the September GCA Strategy was incorporated into the Development Consent by necessary implication;
(iii) whether, by reason of s 80(12) of the Environmental Planning and Assessment Act 1979 (NSW), to the extent that there was an inconsistency between the plans in a Construction Certificate issued by Council and those in the Development Consent, the former prevailed;
(iv) whether the primary judge in erred in factual findings, that there are "substantial issues with flooding on the TriPad site" and that the Development Consent "did not include Lot 2", which was a drainage reserve owned by the Council.
The Court (McColl JA, Leeming JA and Payne JA) allowing the appeal, held:
In relation to issue (i), per McColl JA at [25]-[37]; per Leeming JA at [55]-[59]; per Payne JA at [159]-[181]
(1) Condition 16, on its proper construction, did not require Bunderra to construct the reinforced concrete pipe under Main Road.
Parramatta City Council v Shell Co of Australia Ltd [1972] 2 NSWLR 632; Westfield Management Limited v Perpetual Trustee Company Limited [2006] NSWCA 245; Baulkham Hills Shire Council v Ko-veda Holiday Park Estate Ltd (2009) 167 LGERA 395; [2009] NSWCA 160 considered.
In relation to issue (ii), per McColl JA at [38]-[42]; per Leeming JA at [60]-[74]; per Payne JA at [192]-[198]
(2) the September GCA Strategy, which is inconsistent with the terms of the Development Consent, was not capable of being incorporated by "necessary implication".
House of Peace Pty Ltd v Bankstown City Council (2000) 48 NSWLR 498; [2000] NSWCA 44; Winn v Director-General of National Parks and Wildlife (2001) 130 LGERA 508; [2001] NSWCA 17 considered.
Allandale Blue Metal Pty Ltd v Roads and Maritime Services (2013) 195 LGERA 182; [2013] NSWCA 103 applied.
In relation to issue (iii), per McColl JA at [43]-[52]; per Leeming JA at [75]-[78]; per Payne JA at [211]-[217]
(3) consistently with s 80(12) of the EPA Act, the plans in the Construction Certificate formed part of the Development Consent.
(4) to the extent that there is an inconsistency between plans and specifications in a Construction Certificate, and plans and specifications originally approved in a development application, the former must prevail.
Burwood Council v Ralan Burwood Pty Ltd (No 3) [2014] NSWCA 404; (2014) 206 LGERA 40 applied.
In relation to issue (iv), per Payne JA at [225]-[228] and [234]-[237] (McColl and Leeming JJA agreeing)
(5) based on the evidence it was open for the primary judge to conclude that there were substantial issues with flooding.
(6) the primary judge erred in finding that Lot 2 was excluded from the Development Consent, however such an error had no consequence.