© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2017] NSWCA 263
Court of Appeal (NSW)
2017-08-31
McColl JA, Leeming JA, Payne JA
Original judgment source is linked above.
Principal judgment Parties: Bunderra Holdings Pty Ltd (Appellant) Pasminco Cockle Creek Smelter Pty Ltd (subject to Deed of Company Arrangement) (First respondent) Lake Macquarie City Council (Second respondent) Representation: Counsel: I Hemmings SC with J McKelvey (Appellant) S B Lloyd SC with L T Livingston (First Respondent)
Solicitors: Bradley Allen Love Lawyers (Appellants) Speirs Ryan Pty Ltd (First respondent) Moray and Agnew (Second respondent) File Number(s): 2017/8668 Decision under appeal Court or tribunal: Land and Environment Court Jurisdiction: Class 4 Citation: [2016] NSWLEC 143 Date of Decision: 11 November 2016 Before: Robson J File Number(s): 2016/159532
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
headnote [This headnote is not to be read as part of the judgment] The appellant (Bunderra) and the first respondent (Pasminco) own neighbouring parcels of land in the Lake Macquarie area, the "TriPad site" and the "Main site" respectively. The second respondent (the Council) granted development consent for the subdivision of the TriPad site into 90 residential lots. Condition 16 of the Development Consent required certain stormwater management works to be undertaken. Two stormwater strategy reports (the August GCA Strategies) were submitted to Council and expressly incorporated into the Development Consent. Relevantly, they provided for the construction of a reinforced concrete pipe under a roadway owned by the Council (Main Road) up to the boundary of Pasminco's property, as part of a future stormwater solution in the event that the Main site was developed. Condition 1 of the Development Consent provided that the August GCA Strategies could be varied by the conditions of the Development Consent. A subsequent strategy report (the September GCA Strategy) was prepared for the purpose of satisfying Condition 16 of the Development Consent, namely to provide further information prior to the issue of a construction certificate. It contained amendments to proposed stormwater structures. The primary judge granted an injunction restraining the Council from issuing a subdivision certificate to Bunderra in respect of the development of the TriPad site until Bunderra constructed the reinforced concrete pipe under Main Road. The main issues on appeal were: (i) whether Condition 16 placed an obligation on Bunderra to construct the reinforced concrete pipe under Main Road; (ii) whether the September GCA Strategy was incorporated into the Development Consent by necessary implication; (iii) whether, by reason of s 80(12) of the Environmental Planning and Assessment Act 1979 (NSW), to the extent that there was an inconsistency between the plans in a Construction Certificate issued by Council and those in the Development Consent, the former prevailed; (iv) whether the primary judge in erred in factual findings, that there are "substantial issues with flooding on the TriPad site" and that the Development Consent "did not include Lot 2", which was a drainage reserve owned by the Council. The Court (McColl JA, Leeming JA and Payne JA) allowing the appeal, held: In relation to issue (i), per McColl JA at [25]-[37]; per Leeming JA at [55]-[59]; per Payne JA at [159]-[181] (1) Condition 16, on its proper construction, did not require Bunderra to construct the reinforced concrete pipe under Main Road. Parramatta City Council v Shell Co of Australia Ltd [1972] 2 NSWLR 632; Westfield Management Limited v Perpetual Trustee Company Limited [2006] NSWCA 245; Baulkham Hills Shire Council v Ko-veda Holiday Park Estate Ltd (2009) 167 LGERA 395; [2009] NSWCA 160 considered. In relation to issue (ii), per McColl JA at [38]-[42]; per Leeming JA at [60]-[74]; per Payne JA at [192]-[198] (2) the September GCA Strategy, which is inconsistent with the terms of the Development Consent, was not capable of being incorporated by "necessary implication". House of Peace Pty Ltd v Bankstown City Council (2000) 48 NSWLR 498; [2000] NSWCA 44; Winn v Director-General of National Parks and Wildlife (2001) 130 LGERA 508; [2001] NSWCA 17 considered. Allandale Blue Metal Pty Ltd v Roads and Maritime Services (2013) 195 LGERA 182; [2013] NSWCA 103 applied. In relation to issue (iii), per McColl JA at [43]-[52]; per Leeming JA at [75]-[78]; per Payne JA at [211]-[217] (3) consistently with s 80(12) of the EPA Act, the plans in the Construction Certificate formed part of the Development Consent. (4) to the extent that there is an inconsistency between plans and specifications in a Construction Certificate, and plans and specifications originally approved in a development application, the former must prevail. Burwood Council v Ralan Burwood Pty Ltd (No 3) [2014] NSWCA 404; (2014) 206 LGERA 40 applied. In relation to issue (iv), per Payne JA at [225]-[228] and [234]-[237] (McColl and Leeming JJA agreeing) (5) based on the evidence it was open for the primary judge to conclude that there were substantial issues with flooding. (6) the primary judge erred in finding that Lot 2 was excluded from the Development Consent, however such an error had no consequence.
Judgment
Stormwater drainage works: structure
Development consent: construction
Development consent: consideration
Incorporation of September GCA Strategy
Paramountcy of the Construction Certificate
Grounds 1, 2 and 4 - Construction of condition 16
Ground 3 - Incorporation by necessary implication of the September GCA Strategy
Grounds 6 and 6A - effect of the construction certificates
Remaining grounds and orders
Relevant facts
The Development Consent
The August GCA Strategies
The September GCA Strategy
Primary Judgment
Issues on appeal
Bunderra's submissions
Pasminco's submissions
Consideration of grounds 1, 2 and 4
Ground 3
Bunderra's submissions
Pasminco's submissions
Consideration of ground 3
Bunderra's submissions
Pasminco's submissions
Consideration of ground 6A
Bunderra's submissions
Pasminco's submissions
Consideration of ground 7
Bunderra's submissions
Pasminco's submissions
Consideration of ground 8
Conclusion and orders
Endnotes
Amendments 20 October 2017 - Typographical error corrected at para [60] DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 20 October 2017
Bunderra Holdings Pty Ltd
Pasminco Cockle Creek Smelter Pty Ltd
[2004] SASC 373
(2013) 195 LGERA 182
(2013) 195 LGERA 34
(2009) 167 LGERA 395
(2014) 206 LGERA 40
(2004) 220 CLR 472
(2000) 48 NSWLR 498
(2004) 137 LGERA 189
(1993) 78 LGERA 404
(2007) 82 ALJR 74
(2001) 130 LGERA 508
(2004) 61 NSWLR 707