[2019] WASC 76
General information, not legal advice.
Supreme Court of WA
2019-03-12
Martin J
Original judgment source is linked above.
(1) the defendant shall not be required to provide any further discovery in relation to pars [11], [14] and [15] of the further amended substituted statement of claim (filed 15 July 2018 - 'the further amended SSOC'); and
(2) subject to obtaining leave, the plaintiff shall not be permitted to file further expert evidence in relation to pars [11], [14] and [15] of the further amended SSOC.
(a) conflate the definition of the General Drawing Deficiencies with the alleged consequences of the General Drawing Deficiencies;
(b) fail to identify the alleged defects that constitute the General Drawing Deficiencies;
(c) fail to demonstrate causation of the alleged loss suffered by reason of the alleged defects; and
(d) as a consequence will prejudice, embarrass or delay the fair trial of the action.
Balance of the defendant's chamber summons dated 18 October 2017
(a) that Party must give the other Party notice of that category on or before 7 May 2018; and
(b) the other Party is to provide notice to the first Party within seven days as to whether it accepts the exclusion, or part thereof.
The issue on the defendant's present application of 22 November 2018
The 'before' and 'after' pleas under pars [11], [14] and [15]
[11] In breach of the terms pleaded in paragraphs [5](f), [6] or [7] above, or alternatively, in breach of the warranty pleaded in [5](g) or [8] above, the Drawings and Specifications did not meet the standard referred to in paragraph [9] above, and as a consequence the Drawings and Specifications required additional work and augmentation by:
(a) the issuing of 7,565 requests for information, under the Contract;
(b) the processing and management of 4,842 requests for information from subcontractors;
(c) the review of 6,723 sketches issued by the Defendant and the Defendant's Designers;
(d) the carrying out of not less than 1,211 Variations;
(e) an increase in resources applied by the plaintiff;
(f) the raising of 709 extensions of time claims; and
(g) the issuing of 7,737 delay notices and requests for extensions of time,
(General Drawing Deficiencies)
[11] In breach of the terms pleaded in paragraphs [5](f), [6] or [7] above, or alternatively, in breach of the warranty pleaded in [5](g) or [8] above, the Drawings and Specifications did not meet the standard referred to in paragraph [9] above and were deficient (General Drawing Deficiencies), and as a consequence the Drawings and Specifications required additional work and augmentation by:
(a) the issuing of 7,565 requests for information, under the Contract;
(b) the processing and management of 4,842 requests for information from subcontractors;
(c) the review of 6,723 sketches issued by the Defendant and the Defendant's Designers;
(d) the carrying out of not less than 1,211 Variations;
(e) an increase in resources applied by the plaintiff;
(f) the raising of 709 extensions of time claims; and
(g) the issuing of 7,737 delay notices and requests for extensions of time,
(General Drawing Deficiencies).
(a) The deficiencies in the electrical building services engineering and vertical transportation drawings are set out in section 6.8 of the Preliminary Expert Report of Gerry Brannigan dated 16 Apil 2018 (Brannigan Report) at pages 30 to 39;
(b) The deficiencies in the mechanical building services engineering drawings are set out in section 7.7 of the Brannigan Report at pages 45 to 49;
(c) The deficiencies in the hydraulic building services engineering drawings are set out in section 8.7 of the Brannigan Report at pages 54 to 58;
(d) The deficiencies in the mechanical fire protection engineering drawings are set out in section 9.7 of the Brannigan Report at pages 63 to 65;
(e) The deficiencies in the architectural drawings are set out in section 10.7 of the Brannigan Report at pages 76 to 96; and
(f) The deficiencies in the facade engineering drawings are set out in section 11.7 of the Brannigan Report at pages 105 to 110.
[14] By reason of the General Drawing Deficiencies, it was necessary for the Plaintiff to:
(a) issue 7,565 requests for information, under the Contract;
(b) process and manage 4,842 requests for information from subcontractors;
(c) review 6,723 sketches issued by the Defendant and the Defendant's Designers;
(d) carry out not less than 1,211 Variations;
(e) increase its resources;
(f) raise 709 extension of time claims; and
(g) issue 7,737 delay notices and requests for extensions of time.
[15] The Plaintiff suffered loss and damage for its costs of project preliminaries as follows:
(a) $4,662,759.01 (excluding GST); or
(b) alternatively, if the daily delay cost cap applies (as to which the Plaintiff relevantly pleads in paragraphs [65] to [67] below), $8,797,309.06 (excluding GST) for costs of preliminaries,
the particulars of which are provided in Schedule V to this Statement of Claim.
[15] By reason of the matters pleaded in paragraphs 11 and 14, the Plaintiff suffered loss and damage for its costs of project preliminaries as follows:
(a) $4,662,759.01 (excluding GST); or
(b) alternatively, if the daily delay cost cap applies (as to which the Plaintiff relevantly pleads in paragraphs [65] to [67] below), $8,797,309.06 (excluding GST) for costs of preliminaries,
the particulars of which are provided in Schedule V to this Statement of Claim.
Consequences of the June 2018 amendments to the SSOC
This area is heavily congested. A cross section is required to show how systems fit together.
See also page 263 and the square box notation in reference to the plan:
See also items 15 and 16 at page 264 under the table headed 'Electrical Building Services Document Review Comments'.
For the reasons that follow, I am satisfied that DM Civil's claims are global claims, and modified total costs claims.
The claims are global in nature because nothing in the statement of claim or schedules attempts to draw any causal link between any particular items in sch A (the giving of access or approval), sch B (the sequencing directions), or sch F(the issue of IFC drawings) and any particular consequence in relation to any particular part of the work identified in sch C, or to the incurring of any particular cost referred to [in] sch C. That proposition was not seriously contested by DM Civil. Rather, DM Civil contended that Karara's complaint in this respect failed to appreciate the nature of the case being put by DM Civil.
DM Civil denies that its claims are in the nature of a total costs claim or a modified total costs claim. Counsel submits that DM does not claim all of the costs of the Affected Works, but only those additional costs of the Affected Works that were caused by the redesign, or the resequencing, or the combined effect of those two matters.
For the reasons that follow, I do not accept DM Civil's submission as to the effect of its pleaded case.
(a) the contractor might reasonably have been expected to perform the work for a particular sum, usually the contract price;
(b) the proprietor committed breaches of contract;
(c) the actual reasonable cost of the work was a sum greater than the expected cost;
(d) the proprietor's breaches are the only cause of any significance for the difference between the expected cost and the actual cost.
These authorities firmly establish that in order for a total costs claim to succeed, the contractor must establish that there were no operative causes of its loss and expense apart from matters that were the responsibility of the principal. Further, I agree, with respect, with Byrne J [referring to John Holland Pty Ltd v Kvaerner] that this proposition is necessary, as a matter of logic, in order for the contractor to sustain an inference that the difference between the expected cost and actual cost was caused by the principal's breaches, variations or other relevant conduct. Without demonstrating that alternative causes are excluded, the inference of causation cannot be drawn. The same is true, in my opinion, in respect of a modified total costs claim, within the sphere(s) in which the contractor claims the whole of its actual costs less what it has been paid.
I certify that the preceding paragraph(s) comprise the reasons for decision of the Supreme Court of Western Australia.