[2025] VCAT 980
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2025-11-21
Original judgment source is linked above.
THE PROPOSED BUILDINGS ARE CONSISTENT WITH THE AGRICULTURAL USE OF THE LAND
Land used to:
a) propagate, cultivate or harvest plants, including cereals, flowers, fruit, seeds, trees, turf, and vegetables;
b) keep, breed, board, or train animals, including livestock, and birds; or
Land used to store unprocessed agricultural produce, or products used in agriculture
THE LOCATION OF THE SHED EXTENSION IS NOT ACCEPTABLE HAVING REGARD TO ITS PROXIMITY TO 22 LAKE ROAD AND LAKE MOODEMERE
Whether the site is suitable for the use or development and whether the proposal is compatible with adjoining and nearby land uses.
The impact of the siting, design, height, bulk, colours and materials to be used, on the natural environment, major roads, vistas and water features and the measures to be undertaken to minimise any adverse impacts.
The impact on the character and appearance of the area or features of architectural, historic or scientific significance or of natural scenic beauty or importance.
To protect and enhance the rural setting surrounding Lake Moodemere.
To protect the Lake from inappropriate development.
THE PROPOSED CONSOLIDATED STRUCTURE IS ACCEPTABLE

No polluted and/or sediment laden run-off is to be discharged directly or indirectly into drains or watercourses on Crown land. Overland flow must be maintained at the same rate post-development as on the undeveloped land.
Runoff from buildings and other impervious surfaces shall be directed to a rainwater tank for re-use or on-site dispersal without impact on neighbouring properties to the satisfaction of the Responsible Authority.
Matters in the proceeding relating to application for costs
Council has no view on whether Ms Honan should be added as a party, or if further notice is required.
(1) Subject to this Division, each party is to bear their own costs in the proceeding.
(2) At any time, the Tribunal may order that a party pay all or a specified part of the costs of another party in a proceeding.
(3) The Tribunal may make an order under subsection (2) only if satisfied that it is fair to do so, having regard to -
(a) whether a party has conducted the proceeding in a way that unnecessarily disadvantaged another party to the proceeding by conduct such as -
(i) failing to comply with an order or direction of the Tribunal without reasonable excuse;
(ii) failing to comply with this Act, the regulations, the rules or an enabling enactment;
(iii) asking for an adjournment as a result of (i) or (ii);
(iv) causing an adjournment;
(v) attempting to deceive another party or the Tribunal;
(vi) vexatiously conducting the proceeding;
(b) whether a party has been responsible for prolonging unreasonably the time taken to complete the proceeding;
(c) the relative strengths of the claims made by each of the parties, including whether a party has made a claim that has no tenable basis in fact or law;
(d) the nature and complexity of the proceeding;
(e) any other matter the Tribunal considers relevant.
(4) If the Tribunal considers that the representative of a party, rather than the party, is responsible for conduct described in subsection (3)(a) or (b), the Tribunal may order that the representative in his or her own capacity compensate another party for any costs incurred unnecessarily.
(5) Before making an order under subsection (4), the Tribunal must give the representative a reasonable opportunity to be heard.
(6) If the Tribunal makes an order for costs before the end of a proceeding, the Tribunal may require that the order be complied with before it continues with the proceeding.
(7) A power of the Tribunal under this section is exercisable by any member.
Construct a building within 100 metres of a dwelling not in the same ownership and within 20 metres of a road
Construct a building and construct or carry out works.
(a) be prepared to the satisfaction of the responsible authority;
(b) be drawn to scale with dimensions;
(c) submitted in electronic form; and
(d) show the following details:
- An accurate site plan providing clarification in respect of all existing buildings and works on site and the proposed location of the consolidated shipping container structure.
- Deletion of the shed extension from the plans.
- Floorplan and elevations of the shipping container structure, which show the completed structure as a enclosed building with roller doors.
- If an additional water tank is required to meet the requirements of conditions 5, 8 and 11 of this permit, the location of the water tank.
The layout of the site, dimensions and elevations of the proposed development as shown on the endorsed plans must not be modified or altered without the written consent of the Responsible Authority.
(a) Grading, excavation and construction does not proceed during periods of heavy rainfall;
(b) Sediment traps are designed, installed and maintained to maximise the volume of sediment trapped from the site during development and construction;
(c) Top soil from the construction site or builders' sand is stockpiled in a location where it will not be eroded from the site;
(d) All erosion control measures are maintained after rainfall and are retained until the site has fully revegetated, and;
(e) Disturbed areas are stabilised and revegetated following the completion of works.
(a) The use and development is not started within two years of the date of this permit.
(b) The development is not completed within two years of the date of commencement
The Responsible Authority may extend the periods referred to if a request is made in writing before the period expires or within three months of the date of expiration.
[1] The submissions and evidence of the parties, any supporting exhibits given at the hearing and the statements of grounds filed have all been considered in the determination of the proceeding. In accordance with the practice of the Tribunal, not all of this material will be cited or referred to in these reasons.
[2] The additional notice was discussed at a practice day hearing conducted on 10 July 2025.
[3] As a consequence of the PNPE9 process Ms Honan was made a party at this time.
Brown
Indigo SC [2025] VCAT 980
Chisnall v Indigo SC [2008] VCAT 28