[2025] QSC 349
General information, not legal advice.
Supreme Court of Queensland
2025-12-16
Kelly J
Original judgment source is linked above.
ARBITRATION - ARBITRATION AGREEMENT - CONSTRUCTION OF ARBITRATION AGREEMENT OR REFERENCE - GENERALLY - where the plaintiff and the defendant are parties to a design consultancy agreement entered into by deed - where the design consultancy agreement concerned the provision of design engineering services by the defendant for a new runway project at the Brisbane Airport - where the plaintiff started a proceeding by way of claim and statement of claim seeking an indemnity or damages for allegedly defective design work performed by the defendant said to have caused cracking in parts of the runway - where the defendant contends that the proceeding has been started in contravention of an arbitration agreement contained in a clause in the deed - where the defendant applies for a stay pursuant to s 8(1) of the Commercial Arbitration Act 2013 (Qld) or in the court's inherent jurisdiction - where there emerged four real issues on this application - where the first issue concerned the proper construction of the clause and whether, properly construed, the clause conferred upon the parties a choice or option as to whether to commence litigation or to engage the dispute resolution process - where the second issue concerned whether, in circumstances where the steps outlined in the clause had not occurred, the arbitration agreement was to be regarded as "inoperative" within the meaning of that expression as contained in s 8 - where the third issue concerned whether, upon the proper construction of the clause, what might be styled as "non-contractual claims" were excluded from the agreement to arbitrate - where the fourth issue concerned whether, in circumstances where s 8 had no application, this court in its supervisory jurisdiction could and should impose a stay of the proceeding - whether the proceeding should be stayed pursuant to s 8(1) of the Act, pending any arbitral reference between the parties or until further order
Australian Broadcasting Commission v Australasian Performing Right Association Ltd [1973] HCA 36; (1973) 129 CLR 99, cited
Broken Hill City Council v Unique Urban Built Pty Ltd [2018] NSWSC 825, cited
Ecosse Property Holdings Pty Ltd v Gee Dee Nominees Pty Ltd [2017] HCA 12; (2017) 261 CLR 544, cited
Electricity Generation Corporation v Woodside Energy Ltd [2014] HCA 7; (2014) 251 CLR 640, cited
John Holland Pty Ltd v Kellogg Brown & Root Pty Ltd [2015] NSWSC 451, cited
Pacific Carriers Ltd v BNP Paribas [2004] HCA 35; (2004) 218 CLR 451, cited
PMT Partners Pty Ltd (in liq) v Australian National Parks and Wildlife Service [1995] HCA 36; (1995) 184 CLR 301, cited
Siam Steel International Plc v Compass Group (Australia) Pty Ltd [2014] WASC 415; (2014) 293 FLR 260, cited
Stevens Constructions Pty Ltd v Zorko [2002] SASC 42; (2002) 81 SASR 316, cited
WCX M4-M5 Link AT Pty Ltd v Acciona Infrastructure Projects Australia Pty Ltd (No 2) [2022] NSWSC 505, cited
A J H O'Brien and L Heit for the plaintiff/respondent
(a) an indemnity pursuant to a clause of the Varied Deed;
(b) damages for breach of contract;
(c) damages for negligence;
(d) damages pursuant to s 236 of the Australian Consumer Law ("the ACL").
Subject to clause 23.2, if a dispute or difference between the Consultant and BAC arises out of or in connection with the Agreement, then either party may serve the other with a notice of dispute, in writing, adequately identifying and providing details of the dispute or difference. Notwithstanding the existence of a dispute or difference, the Consultant must continue to perform its obligations under the Agreement.
If the Consultant disputes a direction or determination given pursuant to the Agreement then the Consultant must serve BAC with a notice of dispute which complies with clause 23.1, within 5 Business Days of the direction or determination being given. If the Consultant fails to serve a notice of dispute regarding a direction or determination strictly in accordance with this clause 23.2, the Consultant will be forever barred from disputing BAC's direction or determination.
Within 5 Business Days after a dispute or difference is notified in accordance with either clause 23.1 or 23.2, BAC's Representative (and any other representative of BAC, nominated by BAC's Representative) and the Consultant (if a person) or a director of the Consultant (if a company) must meet to discuss the issue in good faith with a view to resolving the issue by agreement.
If a dispute or difference remains unresolved after the parties have met in accordance with clause 23.3, either party may refer the issue to the Management Committee immediately (or within such longer period as the parties may agree). For the purposes of this clause 23.4, Management Committee means the committee established by the parties comprising two senior managers from each party.
The Management Committee must meet at BAC's offices within 10 Business Days of having the issue referred to it under clause 23.4, to discuss the dispute or difference in good faith with a view to resolving the issue by agreement.
(1) If the dispute or difference is not resolved within:
(i) 25 Business Days after the service of the notice of dispute under clause 23.1 or clause 23.2 (as the case may be); or
(ii) such longer period of time as the parties may agree in writing,
then unless the parties have, prior to that time, agreed some other means of attempting to resolve the dispute or difference (such as mediation), the dispute or difference shall be finally settled by arbitration under the Rules of Arbitration of the International Chamber of Commerce (Rules) in effect at the time of the arbitration by one arbitrator appointed in accordance with the Rules.
(2) The seat of the arbitration shall be Brisbane, Australia, and it shall be conducted in the English language.
(3) The arbitration award shall be final and binding on the parties. The parties undertake to carry out any award without delay and waive their right to any form of recourse based on grounds other than those contained in the United Nations Convention on the Recognition and Enforcement of Foreign Arbitral Award of 1958 insofar as such waiver can validly be made. Judgement upon the award may be entered by any court having jurisdiction thereof or having jurisdiction over the relevant party or its assets.
(4) Either party has the right to apply to any court of competent jurisdiction for interim relief, including urgent injunctive relief, necessary to preserve the party's rights. A request by a party to a court of competent jurisdiction for interim measures necessary to preserve the party's rights shall not be deemed incompatible with, or a waiver of, this agreement to arbitrate.
23.7 Condition precedent to commencing proceedings
Compliance with the procedures in this clause 23 is mandatory and is a condition precedent to either party commencing arbitration (other than urgent or injunctive relief) in relation to a dispute under the Agreement."
"It is trite law that the primary duty of a court in construing a written contract is to endeavour to discover the intention of the parties from the words of the instrument in which the contract is embodied. Of course the whole of the instrument has to be considered, since the meaning of any one part of it may be revealed by other parts, and the words of every clause must if possible be construed so as to render them all harmonious one with another. If the words used are unambiguous the court must give effect to them, notwithstanding that the result may appear capricious or unreasonable, and notwithstanding that it may be guessed or suspected that the parties intended something different. The court has no power to remake or amend a contract for the purpose of avoiding a result which is considered to be inconvenient or unjust. On the other hand, if the language is open to two constructions, that will be preferred which will avoid consequences which appear to be capricious, unreasonable, inconvenient or unjust, 'even though the construction adopted is not the most obvious, or the most grammatically accurate', to use the words from earlier authority cited in Locke v Dunlop (1888) 39 Ch D 387, at p 393, which, although spoken in relation to a will, are applicable to the construction of written instruments generally; see also Bottomley's Case (1880) 16 Ch D 681, at p 686. Further, it will be permissible to depart from the ordinary meaning of the words of one provision so far as is necessary to avoid an inconsistency between that provision and the rest of the instrument. Finally, the statement of Lord Wright in Hillas & Co Ltd v Arcos Ltd [1932] UKHL 2; (1932) 147 LT 503, at p 514, that the court should construe commercial contracts 'fairly and broadly, without being too astute or subtle in finding defects', should not, in my opinion, be understood as limited to documents drawn by businessmen for themselves and without legal assistance (cf. ; , at p 437)."
"Generally, 'inoperative' has been interpreted across jurisdictions implementing the Convention and the Model Law as meaning that the arbitration agreement has ceased to have effect for the future, either for a specific type of dispute or at large. An arbitration agreement may be 'inoperative' as it is unenforceable, has been amended by a further agreement, is the subject of res judicata, has been set aside by a Court, has been frustrated or discharged by breach or by reason of waiver, estoppel, election or abandonment or has otherwise been repudiated.
John Holland falls outside this rubric. It may be observed that Hammerschlag J was not taken to the authorities referred to in this judgment. Whilst John Holland was approved in Blanalko and Transurban, neither case concerned whether proceedings should be referred to arbitration notwithstanding that a preliminary step under a tiered dispute resolution clause had yet to be completed. (The case may also be distinguished as the arbitration agreement expressly provided, 'It is a condition precedent to a party being entitled to refer a Dispute to arbitration ... or to commence court proceedings ... that the procedures referred to ... first be complied with.' Schedule 3 of the D&C Deed does not so provide.)
Whilst a more experienced commercial judge would be hard to find, I respectfully consider that, to the extent that John Holland is authority for the proposition that failure to complete preliminary steps in a tiered dispute resolution clause before arbitration makes the clause 'inoperative', it should not be followed. Such a construction would undermine the object of the Act, depart from the interpretation of the term more widely and enable a party to bypass their contractual bargain to submit their disputes to arbitration by commencing proceedings before all preliminary steps have been completed: Channel Tunnel Group at 669 (per Staughton LJ). As Findlay J put it in Westco, 'It cannot possibly have been the intention of the parties that, if one of them issues a writ before that [preliminary] step is taken, their joint wish to avoid proceedings at law is frustrated': at [11]. Or as Le Miere J stated in Siam Steel, 'To construe "inoperative" to cover such a situation would turn the exception ... into a backdoor for a party wanting to escape the arbitration agreement': at [45].
I doubt that Hammerschlag J had such a result in mind. Rather, in both John Holland and Broken Hill City Council v Unique Urban Built, his Honour made facultative orders to hold the parties to their bargain to arbitrate, notwithstanding a failure to comply with the precise terms of the arbitration agreement, at least by the time that the application for a stay was heard. Hammerschlag J either stayed or stood over the proceedings until the preliminary steps required before arbitration had been completed.
As such, the arbitration agreement in the D&C Deed is 'operative' notwithstanding that the expert determination phase has yet to be undertaken. As such, the Court "must" refer the parties to arbitration. The fact that preliminary steps must be taken before the Jurisdiction Dispute or Directions Dispute reaches the arbitration stage matters not. As the Court explained in Hancock Prospecting Pty Limited v Rinehart, section 8 'involves the referral to arbitration, by a stay of court proceedings': at [146]. In that case, the Court stayed the proceedings under section 8(1) 'pending any arbitral reference between the parties or until further order': at [417], relevantly upheld by the High Court on appeal (Rinehart v Hancock Prospecting Pty Ltd [2019] HCA 13; (2019) 267 CLR 514 at [81]. The same result was achieved, albeit by a different route, in Channel Tunnel Group. As Staughton LJ observed at 669:
'The defendant in the court proceedings who applies for a stay may not have any claim which he wishes to make against the plaintiff, or any other reason either to start an arbitration or to carry out any preliminary action before there can be one; he may merely wish to resist the plaintiff's claim. I can see no reason why he should not say to the plaintiff: "I dispute your claim. If you wish to pursue it, you must carry out the preliminary step and then proceed to arbitration".'"
"An arbitration agreement is not inoperative in relation to particular claims merely because an arbitrator has not been appointed or a step that must be taken before an arbitrator is appointed has not yet been taken in relation to those claims. To construe 'inoperative' to cover such a situation would turn the exception in s 7(5) into a backdoor for a party wanting to escape the arbitration agreement. The effect of s 7 of the International Arbitration Act is that the parties are to be held to their bargain to arbitrate except relevantly where the arbitration agreement has ceased to have effect for the future at least in relation to the claims the subject of the action."
"Section 7(2) of the International Arbitration Act provides that if the specified conditions are met the court shall stay the proceedings and refer the parties to arbitration. The plaintiff objected that the court cannot refer the parties to arbitration because no valid notice of referral to arbitration has been given by the parties and no arbitrator has been validly appointed. In its further written submissions filed on 30 October 2014 the defendant said that more than one construction s 7 of the International Arbitration Act was open but that the better construction gave rise to the conclusion that the court should not stay the proceedings where a condition precedent to the referral of the relevant dispute to arbitration has not occurred. The argument is as follows. The court's power under the International Arbitration Act s 7(2) is to stay the proceedings and refer the parties to arbitration. If the operation of the contractual provisions is such that the court cannot refer the parties to arbitration because the matters in dispute have not been identified by the mandatory mechanism provided by the contract in the event of a dispute then that itself indicates that the agreement is relevantly inoperative.
I do not agree that the arbitration agreement is inoperative because a step that must be taken before an arbitrator is appointed has not yet taken place. I do not agree that the court cannot refer the parties to arbitration, and therefore cannot stay the proceedings, because an arbitrator has not been appointed or a step that must be taken before an arbitrator is appointed has not yet been taken."
[2] [1973] HCA 36; (1973) 129 CLR 99 at 109-10.
[3] Ecosse Property Holdings Pty Ltd v Gee Dee Nominees Pty Ltd [2017] HCA 12; (2017) 261 CLR 544 at 551 per Kiefel, Bell and Gordon JJ.
[5] Pacific Carriers Ltd v BNP Paribas [2004] HCA 35; (2004) 218 CLR 451 at 461-2 [22] per Gleeson CJ, Gummow, Hayne, Callinan and Heydon JJ; Electricity Generation Corporation v Woodside Energy Ltd [2014] HCA 7; (2014) 251 CLR 640 at 656-7 [35] per French CJ, Hayne, Crennan and Kiefel JJ.
[6] Electricity Generation Corporation v Woodside Energy Ltd [2014] HCA 7; (2014) 251 CLR 640 at 656-7 [35].
[8] [1995] HCA 36; (1995) 184 CLR 301 at 311.
[9] [2002] SASC 42; (2002) 81 SASR 316 at [25] to [28].
[10] [2022] NSWSC 505 at [95] to [121].
Brisbane Airport Corporation Pty Ltd
Jacobs Group
(1973) 129 CLR 99
(2017) 261 CLR 544
(2014) 251 CLR 640
(2004) 218 CLR 451
(1995) 184 CLR 301
(2014) 293 FLR 260
(2002) 81 SASR 316
(1968) 118 CLR 429
(2019) 267 CLR 514