General information, not legal advice.
Supreme Court of Queensland
2025-04-24
Freeburn J
Original judgment source is linked above.
(a) rule 367, a general provision of the Uniform Civil Procedure Rules 1999 which gives the court a discretion to make any order or direction about the conduct of the proceeding that the court considers appropriate and bearing in mind that the interests of justice are paramount;
(b) the specific rules relating to expert evidence, such as rule 427 which gives the court a discretion to give appropriate directions about the use of expert evidence;
(c) rule 7 which permits the extending or shortening of times specified by the rules or orders.
"[55] ...[R]elevant expert evidence which has not been dealt with in accordance with the rules may still be admitted in evidence if the interests of justice in ensuring a fair trial require it. The power of the Court of grant leave to a party to tender a non-compliant report or to permit oral evidence to be given by an expert is unfettered by an express provision of the rules. However, the discretion is informed by the purpose of the rules set out in r 5, namely to facilitate the just and expeditious resolution of the real issues in civil proceedings at a minimum of expense. The discretion is also informed by r 5(2) which obliges the Court to apply the rules with the objective of avoiding undue delay, expense and technicality.
[56] Of course, these express provisions which guide the Court in the exercise of discretion are subject to the overarching obligation of the Court to ensure that a trial is fair."[5] [emphasis added]
"...the proposition that a just resolution of proceedings remains the paramount objective and that while speed and efficiency, in the sense of minimum delay and expense, are essential to a just resolution, these factors must not detract from a proper opportunity being given to the parties to put their case."[7]
(a) the point the litigation has reached relative to the trial;
(b) the extent of any failure to comply with the directed timetable;
(c) the adequacy of the plaintiffs' explanation for its delay in presenting the real case it wanted to take to trial;
(d) the prejudice which would be caused to the defendants if leave is granted;
(e) the prejudice which would be caused to the plaintiffs if leave is refused, including whether the plaintiffs might be denied a fair opportunity to present their real case;
(f) the effect on other litigants awaiting resolution of their proceedings; and
(g) the extent to which prejudice on either side can be ameliorated by alteration to the existing timetable.[9]
(a) the nature of the evidence sought to be adduced;
(b) the complexity of the proceeding; and
(c) the nature of an expert's duty to the court.
(a) the overriding object is to progress the proceeding expeditiously with the real issues to be resolve at a minimum of expense, which may mean that the preparation of the case is not perfect; and
(b) the need for a proportionate approach.[16]
(a) the Lane Compendium;
(b) delays in the creation of the Master Database;
(c) delays in the performance of the sampling program.[22]
(a) the context is that this case appears to have taken some considerable time to get going, with the proceeding having commenced in 2017, and substantive expert evidence not being available to ASA until 2022;
(b) ASA's progress in preparing its expert evidence has also been painfully slow and, to say the least, ASA is significantly in breach of court orders;
(c) explanations have been provided, but they are less than satisfactory;
(d) any further delays in the expert reports of are likely to cause hardship to Mr Lane and BAC, and are likely to have flow-on effects for other important expert evidence;
(e) nevertheless, at present the proposed trial dates in late 2026 are not in danger and some adjustments to the timetable are still possible; and
(f) the further evidence of Dr Benotti and Dr Petrozzi is crucial evidence.
[1] Brisbane Airport Corporation v Airservices Australia (2025) QSC 54.
[2] The submissions included 14 pages of supplementary submissions from ASA.
[3] ASA set out the principles at paragraphs 62 to 80 of their submissions. BAC did not contest those principles.
[4] See rules 374 and rule 5(4).
[5] [2017] QCA 127; [2018] 1 Qd R 429 (Sofronoff P, with whom McMurdo JA and Applegarth J agreed).
[7] Ibid. These passages are quoted by ASA's submissions.
[9] Ibid, at [15]. ASA's list omits (f) and (g). Note that an appeal against this decision succeeded ([2019] QCA 160) but the principles were accepted.
[10] See Uniform Civil Procedure Rules 1999 (Qld) at chapter 11, part 5.
[12] Unfortunately, this appears to be the modern approach to litigation - to gather the evidence in the course of the litigation as opposed to marshalling the evidence before or shortly after commencement. That, not surprisingly, leads to amendments to pleadings.
[13] For BAC the expert here is Mr Lane. For ASA the experts are Drs Merrick, Benotti and Petrozzi.
[14] For BAC the remediation expert is Mr Goulding. For ASA it is Mr Stuckey.
[15] I have simplified this slightly. The reports were to be staged with 31 July 2024 being the last date.
[16] Reliance was placed on the decision Finkelstein J in Black and Decker (Australasia) Pty Ltd v GMAC Pty Ltd [2007] FCA 1623 at [4].
[17] The field testing and plans of the experts changed after September 2023 but the time now required is the full two years originally requested.
[19] Maddocks' letter of 12 August 2024.
[21] There is likely to be an overlap in the data.
[23] For example, Mr Abrams and Mr Cavanagh.
[24] See Ms Byrne's affidavit of 28 October 2024 (from page 79 onwards).
[25] Mr Ibbotson's affidavit at page 170.
[26] BAC's submissions at [18]-[20]; ASA's submissions at [4], [20], 88]-[190]; ASA's counsel also described the proposed evidence as 'key evidence'.
Brisbane Airport Corporation Pty Ltd
Airservices Australia & Anor [No 2] [2025] QSC 81
(2009) 239 CLR 175