[2025] QCAT 219
General information, not legal advice.
Queensland Civil and Administrative Tribunal
2025-06-11
Original judgment source is linked above.
(a) The first respondent is to maintain its file on the Complaint open until the earliest of the following to occur:
(i) 1 December 2026;
(ii) the occurrence of one or more substantial rain weather events between the date of this Order and 1 December 2026 (the Weather Events), from which it is able to determine that the building work performed by RRR Civil Pty Ltd under the supervision of the second respondent (the RRR Work) is defective such requiring a direction to rectify to be issued; or
(iii) a date the applicant may agree to in writing.
(b) during any of the Weather Events, the first respondent is to promptly inspect the applicant's house to ascertain and identify the extent of water ingress (if any) in the vicinity of the RRR Work; and
(c) subject to that provided for in Order 3(d) herein, to the extent the first respondent identifies any such water ingress it is to promptly undertake the requisite investigation to identify the source of the water ingress, such to be as provided for in Order 3(e) herein (the Investigation).
(d) the first respondent is not required to undertake the Investigation in the circumstances it can and does contemporaneously identify the source of that ingress, and in turn whether:
(i) the RRR Work is defective such requiring a direction to rectify to be issued; or
(ii) it is from a location or component of the construction of the applicant's house that did not fall within the scope of the RRR Work;
(e) to the extent Investigation is required, the first respondent is to proceed as follows:
(i) any such Investigation is to cover the entirety of the RRR Work and not be limited only to the location of the water ingress identified;
(ii) to the extent the Investigation is by way of non-invasive techniques, it is to be of sufficient ambit, duration, and intensity, to ensure all possible scenarios as to sources of the ingress are considered; and
(iii) to the extent it is not possible to adequately investigate without invasive techniques being engaged, it is to direct the second respondent, or any other relevant person in the manner provided for under s 71I, s 72, s 72A, and s 72B of the Queensland Building and Construction Commission Act 1991 (Qld), to perform the requisite level of invasive investigation.
(f) Upon the respondent reaching a conclusion within the Continuing Internal Review in the manner contemplated by Order 3(a) or 3(d) herein, or on completion of the relevant Investigation provided for by Order 3(e) herein, such that a decision can be made, it shall promptly make a decision and conclude the Continuing Internal Review.
4. Should the applicant disagree with the extended period of time for the Continuing Internal Review as provided for in Order 3 herein, she is to notify the first respondent in writing within 14 days of the date of these orders, and on such occurring the first respondent will be taken to have made an internal review decision that is the same as the Original Decision in the manner contemplated by s 86C(3) of the Queensland Building and Construction Commission Act 1991 (Qld).
ADMINISTRATIVE LAW - ADMINISTRATIVE TRIBUNALS - QUEENSLAND CIVIL AND ADMINISTRATIVE TRIBUNAL - a homeowner sought review of a decision of the Queensland Building and Construction Commission not to direct rectification of building work - the homeowner was subject to water ingress through a bank of windows in her house - the homeowner contracted a building company to remedy the water ingress problem - the water ingress problem continued after the building work was done - the building contractor went into liquidation - the home-owner made a complaint to the Queensland Building and Construction Commission asserting defective work in the remedial work undertaken by the building contractor - the Queensland Building and Construction Commission inspected the works but was unable to replicate the water ingress during the inspection - the Queensland Building and Construction Commission then decided, in the absence of being able to identify the defect by way of observing water ingress, that the work was not defective and so would not issue a direction to rectify and closed its file - whether the Queensland Building and Construction Commission should have maintained its file open awaiting further adverse weather events to inspect any water ingress occurring at that time - whether the Queensland Building and Construction Commission should have directed an invasive investigation to be carried out to ascertain the existence of any defective work causing or permitting water ingress - where the investigation performed in response to the complaint was inadequate - where the decision was remitted to the Queensland Building and Construction Commission for further consideration with directions
Queensland Civil and Administrative Act 2009 (Qld) s 17, s20, s 21(2)(a), s 24
Henderson v Queensland [2014] HCA 52; (2014) 255 CLR 1
Interlink Developments Pty Ltd v Queensland Building and Construction Commission [2020] QCAT 480
Murphy v QBCC [2024] QCATA 27
Investigation was undertaken at the property in relation to the existing front facing windows allowing water ingress during events of heavy or wind driven precipitation. The client has given an overview of the symptoms experienced during these events and shown the resultant damage caused to window reveals, skirting and time to the internal areas of the house. ... This quotation has been compiled with the most complete and accurate scope of works required in assessing and resolving the issues that have been identified on ground level, level one, and level two, respectively.
Sealant removal: All front levels + left windows.
External sealing: All front levels + left windows.
Window sill mechanical rubber seal: All front levels + left windows.
Sealant Application to installed mechanical seals: All front levels + left windows.
Surface preparation for coating installation: (.... all windowsills ... external walls ...).
Surface protective coating Duluxe (sic) external primer: (Entire window sill areas ....).
Top Coating. Dulux External Wash and Wear: (Installation of ... external paint to the building window sills including all trims).
Removal of existing double glazed window.
Window penetration water proofing.
Supply and installation of new single pane window.
...RRR... was engaged by me to carry out repair work at my home ...
The scope of works included, to rectify water ingress problems that occur when we experience heavy storms or cyclonic conditions. ...
...
... the builders have failed to "rectify the problems", in fact they have made matters worse as, prior to my contracting with them, water ingress would only occur as explained above. Now we have a situation where water is coming through when its just heavy rain and not necessarily that windy. The builders were called back on numerous occasions to fix the problems, but they have failed miserably. In an Unusually (sic) rainy April and May this year, it became very clear that the ingress problem had not been fixed and may have deteriorated further. ...
I have paid RRR a considerable amount of money to achieve very little as they have failed to rectify water ingress which was the whole purpose of engaging them.
... there is insufficient evidence to determine this complaint item falls within the definition of defective building works carried out by RRR ...
(a) Is the work performed by RRR under the Contract defective?
(b) If yes, should Mr Rewald be directed to rectify it?
(a) to regulate the building industry:
(i) to ensure the maintenance of proper standards in the industry; and
(ii) to achieve a reasonable balance between the interests of building contractors and consumers; and
(b) to provide remedies for defective building work
in relation to building work, includes faulty or unsatisfactory.
Rectification of Building Work and Remediation of Consequential Damage
(1) Rectification of defective building work
- It is a policy of the Queensland Building and Construction Board that a building contractor who carries out defective building work should be required to carry out that work.
(2) ...
(3) Notification of defects
It is a policy of the Board that if a consumer is seeking the assistance of the Queensland Building and Construction Commission (QBCC) to issue a direction to a building contractor to rectify defective building work, the consumer must lodge a formal complaint with the QBCC of defective building work as soon as possible but no later than within 12 months of becoming aware of the defects.
The QBCC will then consider the issuing of direction to rectify to a building contractor:
for structural defective building work, within 6 years and 3 months of the building work being completed; or
...
In this policy -
Defective building work means building work that is faulty or unsatisfactory, and includes, for example, work that:
does not comply with the Building Act 1975, Building Code of Australia or an applicable Australian Standard;
....
Structural defective building work means defective building work (other than residential construction work causing subsidence) that is faulty or unsatisfactory because it does one or more of the following:
- ...
- adversely affects the health or safety of persons residing in or occupying a building;
- adversely affects the functional use of a building;
- allows water penetration into a building.
This Tribunal's jurisdiction and the Respondent's role in this proceeding
(a) confirming or amending the decision;
(b) setting aside the decision and substituting its own decision; or
(c) setting aside the decision and returning the matter for reconsideration by the decision-maker, together with directions (if any) the Tribunal considers appropriate.
(a) There was a substantial number of photographs showing inter-alia what on its face appeared to be sealant work around windows, and water ingress in the vicinity of the windows and walls, those windows being that which was the subject of the works performed by RRR under the Contract.
(b) She stated therein:[14]
These photos should prove to all parties that a problem does exist.
What is concerning about this matter, is that the QBCC has apparently chosen to totally ignore this evidence which was forwarded to it at the outset.
HOWEVER, More of concern is that the QBCC seems to have totally ignored or overlooked the fact that the builder RRR was engaged for the SOLE PURPOSE of locating the source of water ingress whatever the cause, (i.e.: around the sill area) and to rectify whatever was necessary.
(c) In terms of that last comment, Mrs Bridge also made this statement later therein:[15]
The builder prepared a quotation / scope of works which I agreed to, not because I understood it, I am not a builder, but because the builder assured me that the scope of works was necessary to achieve the required result of leakage prevention. It failed to do this. It didn't do what it was supposed to do. It was not fit for purpose. It was defective.
Clearly, as I still have water penetration, either the remedial works undertaken under the scope of works were defective, or the builder wrongly assessed the scope of works necessary to do the job, with the result that the scope of works were inadequate to achieve the required result. If QBCC insists that the works undertaken were not defective, then the scope of works must have been inadequate. They didn't address what needed to be address. They didn't do what they were intended to do. They were defective.
This is the inescapable truth, it must be one or the other or both, and if the scope of works is inadequate or ineffective or defective, them, as the scope of works determines what remedial works are undertaken, it follows that those remedial works will be inadequate or defective. ...
(a) Water ingress had been a problem for a while, commencing approximately two (2) years after she purchased the house, however then it was minor but increasing since;
(b) Since RRR's involvement the water ingress had become worse;
(c) When Mr Auditore from the QBCC attended to carry out his inspection following her complaint to the QBCC, the focus was on only one location in the window bank; and
(d) She accepted that the water testing Mr Auditore carried out during his inspection could not replicate a leak during rain.
No - this will require me to do invasive investigation.
(a) a written statement by its inspector Mr Auditore, he being the inspector who performed the initial inspection and made the initial decision not to direct rectification;[18] and
(b) a written statement by its Mr Ferguson, who at the time of giving the statement was the Acting Principal Technical Officer within the QBCC's Internal Review Unit, he being the person who undertook the internal review which was the foundation for the Internal Review Decision.[19]
Mrs Bridge Is that switched on - I'm just going to put it on that other wall over here?
Mr Auditore Yeah Yeah - But these windows aren't leaking on this side.
Mrs Bridge At this stage they haven't but I'm terrified.
...
Mrs Bridge See on these ones he did do an extra piece that came up the wall.
Mr Auditore Oh Yeah.
Mrs Bridge See - all of the sealant is starting to break up. I'm terrified - I was hoping we would get a cyclone to test it ....
Mr Auditore Yeah to test it.
Mrs Bridge ... because I have no idea as to whether these are going to stand up to it.
From my inspection and from what the Applicant had advised me, I could tell that the Contractor had removed the original windows and installed a sill flashing at the bottom of the windows and installed a metal angle serving as a drip rail along the top edge of the masonry above the windows. The original windows were then re-instated. The building work undertaken by the Contractor was compliant with all relevant Performance Requirements and/or Deemed to Satisfy Provision in that water has been prevented from entering the Property.
I did not issue a direction to rectify to the Contractor as there was insufficient evidence that the building work undertaken by the Contractor was defective. That is, I could not reasonably apportion responsibility to the Contractor as I could not rule out for instance produce (sic) failure (of the original window).
Method of Determination
When conducting an inspection, the QBCC Building Inspector will carry out a visual inspection only. This will involve visually observing each complaint item. Invasive investigations are not undertaken by the QBCC to determine the cause of an alleged defect. Examples of invasive investigations include cutting a hole in a wall to look at damage behind the wall. ...
Mrs Bridge You tested for only 20 minutes. Had more intense testing been done might leaks have shown up?
Mr Auditore It might have, but the question is - Is the work done building work and is it defective? - When I was there, there was no defective work. I used a hose, and I could not see anything.
Me You were told that the contractor removed and reinstalled the windows. Did you check compliance with weatherproofing of the windows under the 2019 National Construction Code?
Mr Auditore No - I did not check it.
Me Did you check if water was penetrating through the blockwork surrounding the windows?
Mr Auditore No - paint was not peeling.
As noted in my IRU Desktop Report, a review of the scope of work found that the remedial building work consisted of generally removing the glazing seals and reinstalling new seals and sealant and resealing the junction between the glazing unit and masonry walls.
It is my opinion that regardless of the work carried out by the Contractor, in the circumstance, the original window units were leaking.
It is my opinion that only removing and reinstalling the glazing seals may not necessarily remedy any leaks to the window units in general.
I consider that the water ingress is most likely the result of a manufacturing issue in relation to the original window unit frame components.
It is my opinion that if the window seals were causing the leaking, in isolation of the aluminium components or window frame design, the water testing carried out by Mr Auditore would have most likely caused ingress to occur. ...
There is insufficient evidence to determine the Complaint Items fall within the definition of defective works ...
That is. I could not reasonably apportion responsibility to the Contractor as I could not rule out for instance product failure (of the original window). As such, a direction to rectify cannot be given to the Contractor (pursuant to section 72 of the QBCC Act).
Me Was this done?
Mr Ferguson I hope it is in the Auditore Report.
Me If the glazing seals to the existing windows were not removed and replaced would this give rise to some prospect of leaks?
Mr Ferguson Yes.
Me Are you saying the leaks are due to rotten seals?
Mr Ferguson Not just that - it could be many causes at different times.
Mrs Bridge You made a decision based on assumption - is that correct?
Mr Ferguson Always make decisions on many assumptions.
Me What facts was your decision based on?
Mr Ferguson Old windows.
Me It is a fact - the windows were removed and replaced.
Mr Ferguson Yes - I considered this, but I could not find any defective work.
Me Did you consider any issue with the use of sealants - Sikaflex and the like - in the work done?
Mr Ferguson I did not consider sealant issues?
Me If sealant work was cracked, could it be a contributing factor to leaks?
Mr Ferguson Yes - possible, but the caveat is what is the purpose of the seal - what is behind the seal.
I did not replace these because the windows are too old. You cannot get replacements. I used a clear silicone over the entire gasket.
The evidence is - I still have water ingress - therefore the work must be defective.
(a) It would satisfy the QBCC Rectification of Building Work Policy that a building contractor who carried out the defective work should be required to carry out the rectification work; and
(b) It would meet the objects of the QBCC Act, being to not only maintain proper standards in the industry but to achieve the requisite balance between contractors and consumers.
[1] This information is drawn from the documentary evidence as it was before this Tribunal. The relevant Exhibit received during the hearing is footnoted.
[3] Ex 2 pg 86. Mrs' Bridges evidence was that there was no formal contract document signed by the parties.
[4] Ibid pg' 87 to 90. The quote continued and included remedial work internally to the house in terms of water affected surfaces including skirtings and gyprock plastering. I have not detailed that work in this summary of the relevant facts and circumstances because none of it is the subject of any issue arising in this proceeding.
[10] Ex 1 pg 19. See the Conclusions in the Internal Review Report at Ex 1 pg 223.
[11] That was originally published pursuant to s 19 of the QBCC Act as it then was in force. That section was repealed by s 255 of the Building Industry Fairness (Security of Payment) Act 2017 (Qld), but under the relevant Transitional Provisions for that Act as laid out in the QBCC Act, namely Schedule 1 s 76, that policy presently remains in force.
[12] QBCC Act s 86(1)(e), s 86A, s 86C, s 86E.
[13] Ex's 2 to 7. Attachments to her originating application were also tendered as evidence during the hearing - Ex 11.
[14] Ex 2 pg 1. Emphasis as bold and/or capitals is as per the original.
[16] The words stated here as attributed to Mrs Bridge is not taken from a transcript and so is not to be read as being verbatim. It is as per the notes I took during the hearing. Wherever similar references are made in these reasons to statements by her or other persons when giving oral evidence, the same applies.
[17] Ex 1. Such is as required under QCAT Act s 21(2)(a).
[20] Ex 1 Annexure SOR-9 at time approximately 38:40 to 39:32
[21] Ex 12 para's 24 and 30. The reference to being 'that switched on' is, as I understood the context of the conversation, a reference to a moisture testing meter.
[22] Ex 12 - Annexure PJA-6 - Pg 2 of 11 in the Report.
[23] Ex 13 para's 16, 19, 25 to 28, 32 and 33.
[24] Ex 14 being his statement. Ex 15 being the statement of Dion Hammond.
[25] Document marked for identification 'A'.
[26] Referring to Interlink Developments Pty Ltd v Queensland Building and Construction Commission [2020] QCAT 480 at [40] and [41], affirmed in Murphy v QBCC [2024] QCATA 27 at [19].
[27] Referring to Henderson v Queensland [2014] HCA 52; (2014) 255 CLR 1 at [88].
Bridge
Queensland Building and Construction Commission & Anor [2025] QCAT 219
(2014) 255 CLR 1