Second Issue: Discretion
27 The applicants relied upon two reasons why security should not be ordered:
(1) First, it was contended that the claims of Dr Brecher and EBPL shared a common factual substratum and substantially overlapped. It was expressly accepted by the applicants that, if they were both unsuccessful, they would be jointly and severally liable for the whole of the costs of the proceedings. It was contended that the respondents were no worse off as a result of the joinder of the corporate applicant and their costs were not significantly increased, if increased at all. This was put as a factor in favour of not ordering security, rather than of itself being determinative of the issue.
(2) Secondly, Dr Brecher has offered, and undertakes, to submit to an order to pay any costs that EBPL is ordered to pay to the first to third respondents. This was said to remove any concern arising from the possibility of EBPL being ordered to pay costs which Dr Brecher might not be ordered to pay and which EBPL might not be able to meet.
28 In my view, this is not an appropriate case in which to order security for costs for the following reasons. First, I am not satisfied that there are sufficiently substantial incremental costs over and above what would be incurred in meeting Dr Brecher's claims in any event: Luna Park at [27], [28]; Funds First Pty Ltd v Owners Corporation Strata Plan 66609 (No 2) [2008] NSWSC 428 at [13]. It is evident from the pleading that there is substantial overlap between the claims brought by each and that substantially all of the factual substratum would need to be traversed in the claim brought by Dr Brecher. In my view, the principles referred to in Harpur v Ariadne Australia Limited [1984] 2 Qd R 523 (Harpur) and Luna Park at [26] to [28] apply. In my view, there is no realistic possibility of different outcomes as between the applicants. In particular, it was not demonstrated, as it was in Luna Park, that the defence of the corporate applicant's case substantially increased the complexity and likely cost of the case or its nature. It may be accepted that both applicants have different causes of action and that, if EBPL recovers certain damages, then Dr Brecher will not recover damages reflecting that loss and, indeed, may be unsuccessful in obtaining certain relief. For example, Dr Brecher's financial liability under the guarantees may not be shown to be greater if EBPL is successful in its claim for damages. A not dissimilar situation arose in Harpur, where the company had the claim for compensation rather than the individual shareholders and, if the company failed, the individuals also necessarily failed: at 525. So too, the individual shareholders would not recover damages to the extent the relevant damages were obtained by the company. The real difficulty for the first to third respondents is that, if Dr Brecher had brought his claims alone, or the proceedings were now stayed vis-à-vis EBPL, it would still be necessary to traverse substantially the same facts and issues in the claim brought by Dr Brecher. This weighs heavily against an order for security.
29 Secondly, even if I had been satisfied that there were sufficient areas of dispute which did not overlap, there was no attempt by the first to third respondents to substantiate what the incremental costs would be in respect of that non-overlapping area. The first to third respondents had sought to tender a two page schedule setting out a costs estimate prepared by Mr Hourn and exhibited to his affidavit. This set out hourly rates of the various identified people who would carry out legal work, the estimated number of hours they would work and, in very general terms, the task that they would perform. This provided a total of $298,270 which was reduced to take into account that only 60% of the solicitor client costs were considered likely to be recovered. The second applicant objected to this schedule on the basis that it insufficiently set out the basis for the assumptions contained within it. The parties agreed that the schedule would be received as a submission. However, no attempt was made by the first to third respondents to identify a rational basis to determine from this total estimate what would be the incremental costs of any non-overlapping area or what additional cost would be incurred specifically by reference to the inclusion in the proceedings of the corporate applicant and its claims.
30 The applicants noted that the schedule contained entries for work in connection with expert evidence with respect to the second applicant and this informed its submission that, if security were ordered, it should only be in an amount of $14,856. I am not satisfied that the expert evidence would not be required in the case brought by Dr Brecher. The expert evidence was said to be likely to be required to establish loss of profits of EBPL. However, on the claim brought by Dr Brecher, he has suffered losses or contingent losses as a result of entering into the various arrangements, and procuring EBPL to enter into those arrangements, which requires him to establish that EBPL is worse off than it would have been if it remained at the Dapto premises and had not entered into the new arrangements. I am not satisfied that the costs associated with expert evidence would be materially increased by reason of the claims brought by EBPL. In any event, the evidence adduced and the schedule received as a submission does not provide a sufficiently reliable basis to quantify any such increase.
31 I note that, if the only basis for an order for security for costs was a relatively small additional cost associated with expert evidence a question would arise whether, particularly having regard to s 37M of the Federal Court Act 1976 (Cth), the application should be granted. Significant time and expense is associated with applications of this kind and one would not ordinarily expect to see them being fully ventilated over small amounts in otherwise substantial litigation. If the incremental costs are properly identified by the party seeking security this focuses attention on whether the incremental costs justify the application being made, and is also conducive to the parties being able to reach a practical solution thereby saving costs and reducing delay.
32 Thirdly, the provision of the undertaking by Dr Brecher weighs in favour of refusing an order for security for costs: KP Cable Investments Pty Ltd v Meltglow Pty Ltd (1995) 56 FCR 189 at 197F-198B, 202-204; Jazabas Pty Limited v Haddad (2007) 65 ACSR 276 at [74], [78]-[80] per McClellan CJ at CL (with whom Mason P agreed). The value of that undertaking is obviously relevant: Austcorp Project Number 20 Pty Ltd v LM Investment Management Ltd (in liq) [2014] FCA 1371 at [33]. Dr Brecher's evidence included that he owns valuable assets in Australia ($281,000), valuable assets in the United States (US$2 million) and I draw the inference he is able to access substantial income in light of the reporting services he performs for EBPL. Dr Brecher has lived in Australia since 2012, now with his partner, has worked professionally in Australia, was granted permanent residency in Australia in 2015 and has substantial business interests and activity in Australia.
33 Finally, there are no factors which weigh heavily in favour of granting security. It is not suggested that the proceedings will be stultified if security is ordered; indeed, it is likely that they would not be. However, a mere capacity to provide security is not a reason to order it. It is said that the assets of the South Coast X-Ray Trust are not being chanced in the litigation although it is that Trust which stands to benefit substantially if the applicants are (or EBPL is) successful. That may be accepted, but it is not the principal issue, certainly on the statutory question in s 1335 of the Corporations Act 2001 (Cth). The principal issue is the ability of the corporate applicant to pay an order for costs if unsuccessful, not whether the Trust which benefits is chancing its assets. If the respondents fail to establish that there are incremental costs (or the amount of them) which should be the subject of an order for security, it is of little importance who stands to benefit. Nor is this a case in which an individual is refusing "to come out from behind the skirts of the company" (Harpur at 532) but exposing a respondent to a large potential bill of costs; Dr Brecher is chancing his assets even if the South Coast X-Ray Trust is not. Further, Dr Brecher has undertaken to meet EBPL's costs and that undertaking is of value.
34 It is not necessary to consider the third issue, namely the quantum of security.
35 For these reasons, the interlocutory application is dismissed. I was asked to reserve costs of the interlocutory application. I make the following orders:
(1) The interlocutory application is dismissed.
(2) The proceedings are listed for argument on costs (in the absence of agreement between the parties) and for a case management hearing at 9am on 13 April 2018.
I certify that the preceding thirty-five (35) numbered paragraphs are a true copy of the Reasons for Judgment herein of the Honourable Justice Thawley.