Boambillee [2025] QBCCMCmr 282
George Katsioulas and Rebecca Allen (respondents)
Body Corporate and Community Management Act 1997 (Qld) (Act), sections 227(1)(b) and 229(3)(a)
ARCHITECTUAL CODE / BY-LAWS - where the body corporate seeks orders in relation to landscaping works being undertaken by the respondents - whether the orders sought by the body corporate are warranted in the circumstances.
(1) A copy of the Code in place at the time the scheme's current CMS was recorded.
(2) Details of any purported alterations to the Code since then.
(3) Evidence of any resolutions without dissent agreeing to any changes to the Code since the CMS was recorded.
(4) If there have been changes to the Code since the CMS was recorded, the basis on which the body corporate asserts those changes have been validly incorporated into the CMS.
(5) The basis on which the body corporate asserts the respondents are required to pay an improvement bond.
Are the respondents in breach of the scheme's by-laws?
3.1 An Owner or Occupier of a Lot will:-
(a) be responsible for the proper maintenance and decoration of his Lot;
(b) maintain the interior of his Lot in a clean condition and take all practical steps to prevent infestation by vermin and/or insects;
(c) maintain in good condition and repair and keep clean any part of the Common Property which the owner has the exclusive use of.
(a) For the purposes of this By-Law "Improvements" includes walls, windows, garage roller doors, doors, fly screens, gates, walkways, paths, driveways, yard, lawn, landscaping, garden, plants and irrigation, and drainage facilities located within a Lot.
An Owner or Occupier of a Lot must not do anything to vary the external appearance of the Lot or vary the Common Property without the prior written consent of the Committee.
24.1 Unless the Body Corporate provides some other means of garbage disposal, the Occupier of a lot must keep a receptacle for garbage in a clean and dry condition and adequately covered on the Lot, or on a part of the common property designated by the Body Corporate for the purpose.
(a) comply with all local government local Laws about disposal of garbage: and
(b) ensure that the Occupier does not, in disposing of garbage, adversely affect the health, hygiene or comfort of the Occupiers of other Lots.
(c) ensure that garbage bins left out for garbage collection are removed from the Common Property and returned to the relevant lots as soon as practical after garbage collection, and, if possible on the same day of collection.
25. Damage to Lawns, etc. on the Scheme Land
25.1 An Owner or Occupier of a Lot must not:-
(a) damage or remove any lawn, garden, tree, shrub, plant or flower being part of or situated upon the Scheme Land: or
(b) except with the prior written consent of the Body Corporate, use for his own purposes as a garden any portion of the Common Property.
26. Damage to the Common Property or Lot
An Owner or Occupier of a Lot must not, without the prior written approval of the Body Corporate, mark, paint, drive nails or screws or the like into, or otherwise damage or deface, any structure that forms part of the Common Property or any Body Corporate asset.
Non Statutory Motion (Refer Explanatory Note 11)[14]
That; the Architectural Review Committee (ARC) in consultation with the Committee be at liberty to provide works approval in accordance with the Architectural design Code and at their sole discretion request that the applicant owner pay a bond prior to the commencement of any works, to cover any foreseeable damage to the Common property as a result of the works being undertaken, and;
Further that; the minimum bond shall be no less than $500.00 with the upper limit of the bond being set at a value reasonably estimated for the reinstatement of the Common property based on any anticipated damage that may be caused to the Common property.
[3] I note Mr Katsioulas confirmed receipt of the notice of the application and the respondents' invitation to make submissions in response.
[5] Section 276(1)(a) and (b) of the Act
[7] I note the email from the BCM to the respondents dated 21 November 2022 which refers to the pool being approved by the ARC.
[8] I note a late response to my request for further information was received from the body corporate secretary which suggests the body corporate is no longer seeking order 1.
[11] I understand this included approval for a concrete driveway and paths, garden edging, retaining walls and aluminium side fence with a gate.
[12] Within the body corporate's application there is a letter from the ARC approving the respondents' application with certain conditions.