[2025] NSWCATCD 103
General information, not legal advice.
NCAT Consumer and Commercial
2025-08-05
Original judgment source is linked above.
(1) 23 August 2024, being a bundle of correspondence including emails under cover of a page headed "Case Description and Formal Correspondence"; and
(2) 17 October 2024 which included:
(a) A document headed "Points of Claim" (the Points of Claim);
(b) a "Tender Contract" between the applicant and the respondent dated 12 May 2022 (the Tender Contract);
(c) the Building Contract;
(d) a "paid" tax invoice from the respondent to the applicant for the Deposit; and
(e) a Contract for the Sale and Purchase of Land between the applicant as the purchaser and Dahua Group Sydney Project 3 Pty Ltd as the vendor dated 19 May 2022 (the Land Contract) for the purchase of the Land for $498,600.00
(1) the respondent's Defence to Points of Claim; and
(2) an affidavit of Akish Palan, an employee of the respondent, and the annexures to that affidavit.
"I want NCAT to help get the builder to respond. Cancel contract and get full refund back."
(1) attached a letter from the NSW Building Commission informing the applicant to the effect that his dispute with the respondents related to "the terms and conditions of your contract" and that the Building Commission is therefore unable to intervene; and
(2) under the heading "Why the orders are being sought", stated to the effect that:
(a) In breach of the Building Contract, the respondent received payment of the Deposit despite not having issued the applicant with a home warranty insurance certificate;
(b) A letter had been sent by the applicant's lawyer to the respondent advising of various breaches, but that a response had not been received;
(c) That since the land was registered, he had talked to the respondent to start work but that the respondent had requested the applicant to pay extra money and demanded to change the price and that no work has been done.
(1) Referring to s 127 of the Corporations Act 2001 (Cth), that the Building Contract and Tender Contract are invalid because they were only signed by one director of the respondent and that the Deposit was therefore taken "illegally";
(2) That the respondent is in breach of the Building Contract because it had not yet confirmed easement boundaries, obtained a contour survey, or obtained a s 88B instrument or a s 10.7 planning certificate;
(3) That the Deposit was received in breach of the HBA and the Building Contract because it was received before the applicant had been provided with a certificate of home warranty insurance;
(4) That the respondent pressured the applicant to sign the Building contract;
(5) That the respondent should have but failed to invite the applicant to obtain independent legal advice.
(1) whether the Building contract has been terminated or otherwise rescinded; and
(2) whether:
(a) in that circumstance; or
(b) otherwise having regard to the facts (as found) and the terms of the Building Contract,
the applicant is entitled to an order that the Deposit be refunded.
(1) commented (at [280]) that
"[t]he language and purpose of the provisions relating to insurance seem to us to favour an interpretation of residential building work as including the preparatory work which precedes construction"; and
(2) concluded (at [298]) that the preliminary work done in that case, which consisted of obtaining structural engineering drawings, a BASIX report, a BAL certificate, a s149 certificate, a pre-assessment for the CDC application and landscape architectural services, was "residential building work".
an order that one party to the proceedings pay money to another party or to a person specified in the order, whether by way of debt, damages or restitution, or refund any money paid by a specified person;
...
(a) am satisfied of the facts; and
(b) make the determinations
(1) The Contract Price was $360,000.00
(2) The first payment was to be a 10% Deposit of $39,600.00.
(3) The Building Works must reach the stage of practical completion no more than 36 weeks after the building period commenced (which is to be determined by reference to clause 12and Special Conditions Clause 49), subject to clause 19 which concerns Delays and Extensions of Time.
(4) The builder must not carry out any building work or demand or receive any part of the contract price until warranty insurance is in force and the owner is provided with the certificate of insurance.
"The owner acknowledges and agrees that:
The deposit to divine homes as the preliminary tender fees will be non-refundable. The fees will be used to generate the preliminary contract, tender, draught HIA and the draft plan.
If the client decides not to go further with Divine Homes, the client does not hold any right to claim the refund of the fees paid initially stop"
(1) the design and preparation of concept plans (which include the address of the Property and name the applicant as the client) that were referred and attached to an email from the respondent dated 31 October 2023 (the Plans); and
(2) a variation dated 12 January (the Variation) for $ 149,000.00.
"The final area of the snow gum design with the balcony is 269.89 SQM (29SQ) for the price of $545,000.00 inc. GST.
The inclusion stays the same which is Divine Home Elegant inclusions.
Please consider this offer and when you are ready to proceed, we would like to invite you to the office for finalising the documentation."
"Could you please get back to me with a fixed price on the build that I have chosen as we would like to start the build as soon as possible, last time ask you guys reduced the price to $550,000 however I have been comparing the market another builders and this price still seems too expensive, I'm sure you can do better for us, And when you are reducing the price are you also reducing the quality of the build?"
We have already gone through this, but I will summarise again.
The price stays at $545,000 for 269.89 sqm (29SQ) (Snowgum Design with Balcony)
The inclusions are the same, the quality is the same that has been originally offered"
"I am preparing the documents for you to sign, when can you visit us
I will schedule the meeting accordingly"
(1) a meeting for 15 January being confirmed,
(2) the applicant seeking "some discount"; and
(3) the respondent confirming the price, including the variation of $149,000.00 would be $545,000.00.
"Good afternoon, guys, unfortunately I have decided that I'm not going ahead with the build because the price is way too high and out of my budget, I would highly appreciate if you guys can release my deposit back as soon as possible,
Thank you"
"I am instructed to invite both parties to mutually agree to terminate the purported Home building contract and Tender document, and for you to refund my client the entire deposit he has paid, in an effort to prevent legal proceedings being commenced against you severally and individually."
(1) asserts that the Building Contract and tender document are invalid because one director of the respondent signed the Building Contract and that the Deposit was therefore taken "illegally";
(2) asserts that the respondent is in breach of the Building Contract because it had not yet confirmed easement boundaries, obtained a contour survey, or obtained a s 88B instrument or a s 10.7 planning certificate;
(3) notes that the Deposit was received in breach of the HBA and the Building Contract because it was received before the applicant was provided with a certificate of home warranty insurance;
(4) notes that the writer is advised that the respondent pressured the applicant to sign the Building contract;
(5) asserts that the respondent should have, but failed to invite the applicant to obtain independent legal advice;
(6) alleges various breaches of the Building Contract by the respondent and takes issue with the conduct of the respondent in respect of the applicant; and
(7) state that the writer's client's rights are reserved.
(1) Denies allegations that were made in the 8 March Letter;
(2) Notes that by entering the house and land package including entering the Building Contract, the applicant was offered the Land at a discounted rate and that following settlement of the purchase of the Land, the applicant is now seeking to withdraw from the Building Contract having purchased the Land at a discounted price.
(3) Notes that the respondent has incurred costs which it says exceed the Deposit paid.
(4) Advises that the respondent would agree to mutually rescind the Building Contract on the basis that the respondent keeps the Deposit.
(5) Notes that should the Building Contract be terminated because of the applicant's breach or repudiation, it would seek to recover, inter alia the loss of expected profit from the Building Contract.
(1) The work contemplated by the Building Contract could not commence until at least after settlement of the purchase of the Land;
(2) The purchase of the Land settled in late December 2023;
(3) In around January 2024, the applicant wanted to change the house to be built from that originally contemplated in the Building Contract;
(4) The respondent issued the Variation and informed the applicant of the increase in the price;
(5) The applicant sought to negotiate a reduced price;
(6) Agreement was not reached for a new price with the applicant considering that the price proposed by the respondent was to high;
(7) The applicant, by his solicitors, wrote to the respondent on 8 March 2024 inviting the respondent to agree to mutually terminate the Building contract and making various complaints or allegations in respect of the respondent;
(8) the Application was then filed in May 2024, shortly after which, the respondent, by letter from its solicitor denied the assertions in the 8 March Letter and stated that the respondent would agree to mutually terminate the Building Contract on the basis that the respondent keeps the Deposit.
(9) The parties did not thereafter agree to "mutually terminate" the Building Contract and there was no evidence from one or other of the parties informing the other that the Building Contract was terminated or rescinded.
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.