[2014] VCAT 83
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2014-01-31
Original judgment source is linked above.
The permit allows use and development of the land for dwellings and shops in a Commercial 1 Zone, reduction in the car parking requirement, altered access to a Road Zone 1 and the erection of two (2) electronic major promotion signs.
The tree management plan must detail measures to protect and ensure the viability of the mature trees along the north-eastern boundary of the site, adjacent to no. 6 John Street.
Without limiting the generality of the tree management plan it must have at least three sections as follows:
(a) Pre-construction - details to include a tree protection zone, height barrier around the tree protection zone, amount and type of mulch to be placed above the tree protection zone and method of cutting any roots or branches which extend beyond the tree protection zone.
(b) During-construction - details to include watering regime during construction and method of protection of exposed roots.
(c) Post-construction - details to include watering regime and time of final inspection when barrier can be removed and protection works and regime can cease.
Pre-construction works and any root cutting must be inspected and approved by the Parks Unit. Removal of protection works and cessation of the tree management plan must be authorised by the Parks Unit.
When approved, the plan will be endorsed and will then form part of the permit. Waste collection from the development must be in accordance with the plan, to the satisfaction of the Responsible Authority.
All works must be undertaken in accordance with the endorsed Sustainability Management Plan to the satisfaction of the Responsible Authority. No alterations to the Sustainable Management Plan may occur without written consent of the Responsible Authority.
construction workers vehicles; * (g) temporary fencing works; * (h) methods for limiting escape of dust and litter from the land; * (i) a communication strategy for advising the Responsible Authority, VicRoads and residents of key stages/events (including their timing and duration) in the construction program of the development; * (j) a liaison officer for contact by residents, VicRoads and the Responsible Authority in the event of relevant queries or problems experienced.
The development must be undertaken in accordance with the approved Construction Management Plan to the satisfaction of the Responsible Authority.
The Responsible Authority may extend the periods referred to if a request is made in writing before the permit expires or in accordance with Section 68 of the Planning and Environment Act 1987.
[1] At the time of the application for permit the land was zoned Business 2. Amendment VC100 gazetted 15 July 2013 included the land within a Commercial 1 Zone.
[2] We have considered all submissions and evidence presented by the parties and Statements of Grounds although we do not recite all of the contents in these reasons.
[4] Clauses 11.01-2, 16.01-1, 16.01-2, 16.01-3, 21.03-2 and 21.05-1.
[5] At clauses 11.01-2, 16.01-4, 21.03-2 and 21.05-4 of the Scheme.
[7] Clauses 11.01-2, 16.01-2, 21.03-2, 21.03-3, 21.05-2, 21.05-3 and 34.01.
[10] Clauses 21.04-1, 21.05-3 and 34.01.
[14] Panel Report Stonnington Planning Scheme Amendment C173 20 August 2013.
[16] Dandenong Road Urban Design Framework (between Tooronga Road and Bates Street) prepared by David Lock Associates December 2012.
[17] As referred to in the Preferred Character for Precinct A in the adopted DDO10.
[18] Richmond Icon Pty Ltd v Yarra CC (includes Summary) (Red Dot) [2011] VCAT 2175; Abbotsford Joint Venture Pty Ltd v Yarra CC & Ors [2012] VCAT 146; and Peter Gibson Developments Pty Ltd v Stonnington CC [2011] VCAT 1007.
[20] Activity Centre Design Guidelines (Department of Sustainability and Environment 2005) referred to at clause 11.01-2 and 15.01-2, 11.04-2, 15.01-1, 21.04-1 and 21.06-4 of the Scheme.
[21] At clauses 21.03-3, 21.05-2 and 21.06-1
[22] At pages 57 and 58 of the Report of the Panel on Amendment C173 to the Stonnington Planning Scheme 20 August 2013.
[23] When traffic exiting the site with a destination to the north or north west may choose to turn left into Finch or Clarence Street to access Tooronga Road in preference to undertaking a U-turn at Smith Street and then a right turn at Tooronga Road
[24] Based on an assumption that half of all additional traffic with destinations to the north or north west uses Finch or Clarence Streets to access Tooronga Road, equivalent to 30% of the total exiting movements from the site. The total vehicle movements generated by the development which are estimated at an additional 70 at am peak hour, allowing for current traffic generation from the fitness centre on the site.
[26] Including at clauses 18.01-2 and 21.03-2 of the Scheme.
Bensons Property Group Pty Ltd
Stonnington CC [2014] VCAT 83