[2025] QCAT 338
General information, not legal advice.
Queensland Civil and Administrative Tribunal
2025-09-08
Original judgment source is linked above.
PROFESSIONS AND TRADES - BUILDERS - STATUTORY INSURANCE SCHEME - where applicant sought review of decision by Commission to disallow claim under the Queensland Home Warranty Insurance Scheme - where Commission found that the applicant was in breach of the Contract in not paying the deposit - where deposit paid in in instalments - where builder acquiesced - where builder delayed in obtaining building approvals - where Builder gave Notice - Delay Damages and allowed insufficient time for applicant to comply - where builder wrongly terminated Contract
Queensland Building and Construction Commission Act
(a) $8,000.00 on about 10 April 2021 for "initial deposit";
(b) $1,800.00 on or about 8 March 2022 for "contract fee claim";
(c) $7,300.00 on or about 26 April 2022 for "insurance & Costs claim".
(a) the claimant is a "consumer";
(b) the relevant work was to be carried out under a "fixed price residential contract";
(c) the work under that contract has not commenced; and
(d) the contract ends within 2 years after the contract was entered into.
(a) On 27 April 2022, the Contractor lodged the Building Approval, Plumbing and Build Over Sewer applications with the certifier.
(b) On 3 June 2022, Urban Utilities approved the Build Over Sewer application.
(c) On 14 July 2022, the Building Approval was received by the certifier.
(d) On or about 19 July 2022, the Contractor issued the Delay Damages Notice to the Applicant. The Notice noted that the construction could not commence by the anticipated start date due to "unforeseen circumstances" (including material, logistics and labour), and sought a price increase and change to the start of the anticipated start date. The variation referred to Clause 15 of the Contract and noted that the Applicant had 5 working days from the date of the variation to agree to the request for delay damages, and further, if an agreement could not be reached, the Contractor may exercise their rights and terminate the Contract in accordance with Clause 2.2.
(e) The anticipated start date was 31 May 2022 (being 60 days from the date of the Contract).
(f) On or about 22 July 2022, the parties had a meeting, however an agreement was unable to be reached with respect to request for payment of the Delay Damages Notice.
(g) On 25 July 2022, the Contractor sent the Contractor's Termination to the Applicant advising, noting that the Contractor chooses to end the Contract pursuant to Clause 2.5(a).
(h) Clause 2.5(a) of the Contract provides that if the necessary planning approval and/or building approval permits are not obtained by the anticipated start date, then if neither party is at fault, either party may bring the Contract to an end by giving notice in writing to the other party.
(i) Accordingly, the Commission was satisfied that the Contractor had validity terminated the Contract (by the issuing of the Contractor's Notice).
7.0 IN THE INSTANCE THE CLIENT DOES NOT PAY THE BALANCE OF THE 5% DEPOSIT OR THE QBCC INSURANCE PREMIUM WITHIN 10 DAYS OF THE CONTRACT BEING SIGNED THE CONTRACT CAN BE VOIDED.
(a) Variation 3 hot water system change from electrical to Gas due to BCC requirements on 11 May 2021 for $3,027.00;[7]
(b) Variation 3 air conditioning design change on 20 May 2021 for $1,145.00;[8]
(c) Variation 4 Carport construction including a raft slab to suit revised build over sewer - 23 May 2021.[9]
Where commencement is delayed for longer than four weeks on and after the anticipated start date due to a cause of delay for which the builder is not responsible, the owner must pay to the builder, as a debt due and payable, the higher of the amount:
(a) of the reasonable costs incurred by the building because of the delay; and
(b) representing 0.125% of the contract price for each week or part of a week of the delay after the first four weeks of the delay.
(a) That the decision of the Queensland Building and Construction Commission dated 6 October 2022 to disallow Omar Barragan's claim under the Statutory Home Warranty Insurance Scheme be set aside.
(b) That Omar Barragan's claim under the Statutory Home Warranty Insurance Scheme be allowed.
[3] QBCC Regs sch 6 s 4(1)(a).
[4] Hearing Book 822 email to builder dated 23 March 2022.
[11] Hearing Book email dated 23 May 2022 David Beitz to Applicant.
[17] Hearing Book 136 email dated 28 July 2022.
[19] J.W. Carter, Breach of Contract (Sydney: Law Book Co. Ltd, 1984) paragraph 371.
Barragan
Queensland Building and Construction Commission [2025] QCAT 338