s.739 - Application to deal with a dispute
Pacific National Services Pty Ltd T/A Pacific National
Alleged dispute about any matters arising under the enterprise agreement - meaning of various agreement clauses.
"This section applies if a term referred to in section 738 requires or allows the Commission to deal with a dispute."
"If, in accordance with the term, the parties have agreed that the Commission may arbitrate the dispute, however described, the Commission may do so."
Allan Cooper - Project Manager Victoria Bulk Rail
"The construction of an award, like that of a statute, begins with a consideration of the ordinary meaning of its words. As with the task of statutory construction regard must be paid to the context and purpose of the provision or expression being construed. Context may appear from the text of the instrument taken as a whole, its arrangement and the place in it of the provision under construction. It is not confined to the words of the relevant Act or instrument surrounding the expression to be construed. It may extend to '...the entire document of which it is a part or to other documents with which there is an association'. It may also include '....ideas that gave rise to an expression in a document from which it has been taken' - Short v FW Hercus Pty Ltd (1993) 40 FCR 511 at 518 (Burchett J); Australian Municipal, Clerical and Services Union v Treasurer of the Commonwealth of Australia [1998] FCA 249; (1998) 80 IR 345 (Marshall J)."[11]
"It is trite that narrow or pedantic approaches to the interpretation of an award are misplaced. The search is for the meaning intended by the framer(s) of the document, bearing in mind that such framer(s) were likely of a practical bent of mind: they may well have been more concerned with expressing an intention in ways likely to have been understood in the context of the relevant industry and industrial relations environment than with legal niceties or jargon. Thus, for example, it is justifiable to read the award to give effect to its evident purposes, having regard to such context, despite mere inconsistencies or infelicities of expression which might tend to some other reading. And meanings which avoid inconvenience or injustice may reasonably be strained for. For reasons such as these, expressions which have been held in the case of other instruments to have been used to mean particular things may sensibly and properly be held to mean something else in the document at hand.
But the task remains one of interpreting a document produced by another or others. A court is not free to give effect to some anteriorly derived notion of what would be fair or just, regardless of what has been written into the award. Deciding what an existing award mean is a process quite different from deciding, as an arbitral body does, what might fairly be put into an award. So, for example, ordinary or well-understood words are in general to be accorded their ordinary or usual meaning."[13]
"[41] The construction of an enterprise agreement, like that of a statute or a contract, begins with a consideration of the ordinary meaning of the relevant words. The disputed words must be construed in the context of the agreement as a whole. The process of interpretative analysis focusses upon the language of the agreement itself. In Amcor Limited v CFMEU,[15] Gleeson CJ and McHugh J described the process in the following terms: '[t]he resolution of the issue turns upon the language of the particular agreement, understood in the light of its industrial context and purpose ...'.[16] Or, as Kirby J put it in the same case, '[i]nterpretation is always a text-based activity'.[17]
"The principles relevant to the task of construing a single enterprise agreement may be summarised as follows:
1. The construction of an enterprise agreement, like that of a statute or contract, begins with a consideration of the ordinary meaning of the relevant words. The resolution of a disputed construction of an agreement will turn on the language of the agreement having regard to its context and purpose. Context might appear from:
(ii). the disputed provision's place and arrangement in the agreement;
(iii). the legislative context under which the agreement was made and in which it operates.
2. The task of interpreting an agreement does not involve rewriting the agreement to achieve what might be regarded as a fair or just outcome. The task is always one of interpreting the agreement produced by parties.
3. The common intention of the parties is sought to be identified objectively, that is by reference to that which a reasonable person would understand by the language the parties have used to express their agreement, without regard to the subjective intentions or expectations of the parties.
4. The fact that the instrument being construed is an enterprise agreement made pursuant to Part 2-4 of the FW Act is itself an important contextual consideration. It may be inferred that such agreements are intended to establish binding obligations.
5. The FW Act does not speak in terms of the 'parties' to enterprise agreements made pursuant to Part 2-4 agreements, rather it refers to the persons and organisations who are 'covered by' such agreements. Relevantly s.172(2)(a) provides that an employer may make an enterprise agreement 'with the employees who are employed at the time the agreement is made and who will be covered by the agreement'. Section 182(1) provides that an agreement is 'made' if the employees to be covered by the agreement 'have been asked to approve the agreement and a majority of those employees who cast a valid vote approve the agreement'. This is so because an enterprise agreement is 'made' when a majority of the employees asked to approve the agreement cast a valid vote to approve the agreement.
6. Enterprise agreements are not instruments to which the Acts Interpretation Act 1901 (Cth) applies, however the modes of textual analysis developed in the general law may assist in the interpretation of enterprise agreements. An overly technical approach to interpretation should be avoided and consequently some general principles of statutory construction may have less force in the context of construing an enterprise agreement.
7. In construing an enterprise agreement it is first necessary to determine whether an agreement has a plain meaning or it is ambiguous or susceptible of more than one meaning.
8. Regard may be had to evidence of surrounding circumstances to assist in determining whether an ambiguity exists.
9. If the agreement has a plain meaning, evidence of the surrounding circumstances will not be admitted to contradict the plain language of the agreement.
10. If the language of the agreement is ambiguous or susceptible of more than one meaning then evidence of the surrounding circumstance will be admissible to aide the interpretation of the agreement.
11. The admissibility of evidence of the surrounding circumstances is limited to evidence tending to establish objective background facts which were known to both parties which inform and the subject matter of the agreement. Evidence of such objective facts is to be distinguished from evidence of the subjective intentions of the parties, such as statements and actions of the parties which are reflective of their actual intentions and expectations.
12. Evidence of objective background facts will include:
(i) evidence of prior negotiations to the extent that the negotiations tend to establish objective background facts known to all parties and the subject matter of the agreement;
(ii) notorious facts of which knowledge is to be presumed; and
(iii) evidence of matters in common contemplation and constituting a common assumption.
13. The diversity of interests involved in the negotiation and making of enterprise agreements (see point 4 above) warrants the adoption of a cautious approach to the admission and reliance upon the evidence of prior negotiations and the positions advanced during the negotiation process. Evidence as to what the employees covered by the agreement were told (either during the course of the negotiations or pursuant to s.180(5) of the FW Act) may be of more assistance than evidence of the bargaining positions taken by the employer or a bargaining representative during the negotiation of the agreement.
14. Admissible extrinsic material may be used to aid the interpretation of a provision in an enterprise agreement with a disputed meaning, but it cannot be used to disregard or rewrite the provision in order to give effect to an externally derived conception of what the parties' intention or purpose was.
15. In the industrial context it has been accepted that, in some circumstances, subsequent conduct may be relevant to the interpretation of an industrial instrument. But such post-agreement conduct must be such as to show that there has been a meeting of minds, a consensus. Post-agreement conduct which amounts to little more than the absence of a complaint or common inadvertence is insufficient to establish a common understanding."
"should not be a strict one but one that contributes to a sensible industrial outcome such as should be attributed to the parties who negotiated and executed the Agreement."[19]
"The task of interpreting an agreement does not involve rewriting the agreement to achieve what might be regarded as a fair or just outcome."[20]
Under clause 3.9.1 (Attachment 1 Rostering Guidelines) does Pacific National have to provide direct contact when providing notice? Or is a text message or voicemail acceptable?
3.9 Barracks working (a shift where train crew are rostered to complete a shift at a barracks location away from their home base) can be altered after the posting of the working roster under the following conditions:
3.9.1 The employee is provided a minimum of 12 hours' notice before the original rostered sign on time of the first/ outward shift. At this time advice will be provided for both the outward and return shifts (including rostered sign on and sign off times).
"I do not myself regard the word `notice' as a synonym for the word `knowledge'. Notice is a word which involves that knowledge may be imparted by notice, but `notice' and `knowledge' are not the same thing, although loosely one sometimes talks as if to act with notice and to act with knowledge were indeed the same".
How many changes can Pacific National make to the working roster on a barracks shift for:
Barracks working - where drivers perform a shift that concludes at a different "barracks" location. Drivers rest at the barracks location before returning back to their local depot on a return train service after having had a rest period.
Single shifts where drivers report to duty at their local depot and return from their duties to that same depot at the end of the day.[36]
"3.9 Barracks working (a shift where train crew are rostered to complete a shift at a barracks location away from their home base) can be altered after the posting of the working roster under the following conditions:
3.9.1 The employee is provided a minimum of 12 hours' notice before the original rostered sign on time of the first/ outward shift. At this time advice will be provided for both the outward and return shifts (including rostered sign on and sign off times).
3.9.2 The sign on time for the first/ outward shift is no earlier than the original time posted on the working roster. (Note: lift up and lay back is applicable subject to clause 9, Attachment 1).
3.9.3 The second/return shift has a rostered sign off time is no later than the original posted on the working roster.
3.9.4 Provided the above conditions are satisfied the employee can be rostered on alternative work for the first/outward and or second /return shifts.
3.9.5 All conditions associated with the rostered working will be attributed to the altered shifts.
3.9.6.1 The driver will be credited the greater of the original rostered hours, changed rostered hours or the actual hours worked.
3.9.6.2 If the return shift exceeds the sign off time this time will be paid at 1.7."
9.1 As part of their duties, employees covered by this Agreement may expect to be contacted for lift-up and lay-back purposes. Pacific National will contact crew directly for lift-up and lay-back purposes.
9.2 Subject to sub-clause 9.4 below, employees may be lifted up by two (2) hours and laid back a maximum of four (4) hours on blank line rosters or a maximum of three (3) hours on forecast rosters.
9.3 Pacific National will make no more than two (2) alterations to the confirmed sign-on time for blank line and no more than one (1) alteration to the confirmed sign-on time for forecast under Lift Up and Lay Back provisions. When at rest at a Barracks Location, a limit of only one Lift Up or Lay Back may be made.
9.4 Lift Up and Lay Back may only infringe on a Weekend (i.e. the one weekend in four) with the agreement of the employee concerned.
9.5 Where a Lift-Up or Lay Back is required that is beyond the limits defined in 9.2 above, agreement of the employee concerned must be obtained and the following will apply:
9.5.1 Pacific National will provide as much notification of the change as possible;
9.5.2 A standalone payment, at the rate of 1.7 times the employee's base rate, will be made for time lifted up or laid back beyond the limits outlined in sub-clause 9.2 above.
9.5.3 Payments under this provision will not be made where a payment for barracks detention, as outlined in Clause 10 below, is being made.
9.5.4 The shift limit for the shift will commence from the actual sign on time; and 9.5.5 Where an employee is Laid Back beyond the limits outlined in sub-clause 9.2 above and this results in the employee not being able to work their next rostered shift, the following will apply:
9.5.5.1 Pacific National will attempt to provide alternative work for the employee or, where this cannot be provided.
9.5.5.2 Provide the employee with a credit the rostered hours of the shift not able to be worked to the employee's Duty Cycle."
"The sign on time for the first/ outward shift is no earlier than the original time posted on the working roster. (Note: lift up and lay back is applicable subject to clause 9, Attachment 1)"
"All conditions associated with the rostered working will be attributed to the altered shifts_._"
"Pacific National will make no more than two (2) alterations to the confirmed sign-on time for blank line and no more than one (1) alteration to the confirmed sign-on time for forecast (work?) under Lift Up and Lay Back provisions. When at rest at a Barracks Location, a limit of only one Lift Up or Lay Back may be made."
"... When at rest at a Barracks Location, a limit of only one Lift Up or Lay Back may be made."
If an employee rostered on a barracks shift has his shift changed are they entitled to x 1.7 and when?
The reference to 'sign off time' in 3.9.6.2 is a reference to which roster?
"If the return shift exceeds the sign off time this time will be paid at 1.7."

Mr R Reitano of Counsel and Mr P Pasfield, Solicitor on behalf of the RTBU
Mr L Izzo, Solicitor on behalf of Pacific National
[4] Written submissions of 15 September 2021 pose questions 2 to 4
[7] Statement of A. Cuttle of 29 September 2021 at [12]
[18] [1996] IRCA 166 at 184 per Madgwick J
[20] [2017] FWCFB 3005 at Point (2) of [114]
[22] [2017] FWCFB 3005 at Point (3) of [114]
[23] RTBU's written submissions of 15 September 2021 at [15]
[25] Agreed statement of facts of 7 September 2021 at [21]
[26] Written submissions of 29 September 2021 at 6.3(a)
[29] [2002] NSWCA 95 at 55
[30] [1959] 3 All ER 656 at 657
[34] Witness statement of A. Cuttle of 29 September 2021 at [30-34]
[35] Noting it is not practical to attend an employee's residence or otherwise, to provide the notice.
[36] Agreed statement of facts of 7 September 2021 at [3]
[40] Written submissions of 15 September 2021 at [20]
[45] Written submissions of 15 September 2021 at [26]
[52] PN472, Written submissions of 29 September 2021 at [7.23-7.24]
[55] Witness statement of 29 September 2021 at [7]
[56] Witness statement of 6 October 2021 at [13(c)]
[58] Witness statement of 29 September 2021 at [8(c)]
[60] Noting that the Agreement states 12.5 hours is the commencement time.
[61] Witness statement of P. Mundey 6 October 2021 at [8]
[62] Witness statement of 11 October 2021 at [9]
[67] Written submissions of 15 September 2021 at [37]