[2022] FWC 2448
General information, not legal advice.
Fair Work Commission
2022-09-14
Original judgment source is linked above.
s.604 - Appeal of decisions
Appeal against decision [2022] FWC 1840 of Commissioner McKinnon at Sydney on 20 July 2022 in matter number C2022/1228
(b) The parties agree that interstate site differentials will be maintained for the period of the Agreement and recognise that Wage Parity across Orora Fibre packaging sites is an issue between the parties. The parties agree to consult with each other at a national level to review their respective positions on Wage Parity prior to the next EBA. Initial consultation will commence 3 months after approval of the agreement by FWC, except that where within a state a site is identified as having a significant wages anomaly, then the parties shall meet within one month of the Agreement being accepted by the members to ensure an outcome which will rectify the anomaly.
This Agreement will come into force on the seventh day after it is approved by the Fair Work Commission (FWC) and will remain in force until 30 September 2022 or thereafter until a replacement Agreement is negotiated.
(a) construing the phrase 'period of the Agreement' in cl.5(b) to mean the nominal expiry date of the Agreement, being 30 September 2022;
(b) finding that Opal could implement the proposed roster change by virtue of the dispute resolution procedure and/or consultation pursuant to cls. 15 and 16 of the Agreement;
(c) finding Opal's proposed roster change was not an extra claim pursuant to cl.9.1(m) of the Agreement; and
(d) answering the question for the determination 'Yes, but only on or after 1 October 2022'.
"In accordance with the dispute resolution procedure contained in the Orora Fibre Packaging National Enterprise Agreement 2019, Opal was restrained from taking steps to implement the proposed roster change with respect to Revesby maintenance employees from 14 December 2021".
"[5] In determining whether to grant a stay application the Commission must be satisfied that there is an arguable case, with some reasonable prospects of success, in respect of both the question of leave to appeal and the substantive merits of the appeal. In addition, the balance of convenience must weigh in favour of the order subject to appeal being stayed. Each of the two elements referred to must be established before a stay order will be granted."

A Pollock of counsel and C Yuen for the respondent.
[6] Applying, by parity of reasoning, Wills v Grant, Marley & The Government of New South Wales, Sydney Trains and Anor [2020] FWCFB 4514; 298 IR 254
[7] [2000] AIRC 785, Print S2639
[8] Supreme Caravans Pty Ltd v Pham [2013] FWC 4766 at [9]
[9] Construction, Forestry, Mining, and Energy Union v Collinsville Coal Operations Pty Limited [2014] FWC 4276 at [11]; Bahonko v Sterjov [2007] FCA 1717 at [50]
Printed by authority of the Commonwealth Government Printer
Australian Manufacturing Workers' Union
Opal Packaging Australia Pty Ltd [2022] FWC 2448