© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2016] FCA 536
Federal Court of Australia
2016-05-16
Mr P, Mr J, Greenwood J
Original judgment source is linked above.
The 2005 Swanbank Contract Extension
GREENWOOD J: 1 On 29 April 2016, the Court published judgment in relation to the pecuniary penalty aspects of the proceeding and other related outstanding questions. 2 In those Orders, the Court directed the applicant to submit to the Court proposed final Orders having regard to the reasons for judgment and the matters set out in the Orders made on 29 April 2016, also taking account of the Court's decision concerning the Orders sought by the applicant in Annexure A to its principal submissions. 3 On 12 May 2016, the applicant submitted a draft containing five proposed Orders which were confined to only those matters addressed at Order 2 of the Orders made on 29 April 2016. 4 The Court had in mind that the applicant would address the field of final Orders to be made having regard to the reasons for judgment published on 29 April 2016 and the other matters mentioned above. 5 Those Orders would necessarily distil, into final form, the pecuniary penalty findings made in the reasons for judgment. The final Orders would also need to take account of the relationship between the earlier Declarations and the further proposed Declaration at Order 1 of these reasons and the findings as to the amount of the penalties. 6 The final Orders would also need to deal with the dismissal of the proceeding as against Mr Leon and the costs consequences of the applicant having been unsuccessful as against Mr Leon in the proceedings and any other matters that would require attention in order to bring all outstanding matters to finality. 7 The Orders published today take account of all those matters. 8 They also make provision for dealing with the various confidentiality/non-publication Orders made during the course of the proceedings. 9 The reasons for judgment published on 29 April 2016 contain significant references to market sensitive data relating to prices charged by trade rivals especially in the period 2011 to 2013. The Orders made on 29 April 2016 directed the parties to submit a schedule to the Court setting out confidential market data recorded in the reasons for judgment which ought to be excised from those reasons so as to preserve the confidentiality of that information with a view to ensuring that market sensitive information provided to the Court by one trader would not be published to trade rivals. The Court has now received that schedule and the Orders made today provide for the non-publication of that information and its excision from the reasons for judgment to be published publicly on the Court's website. 10 The information so excised will remain subject to a confidentiality/non-publication Order until further Order. The information will be excised from the reasons for judgment and placed into a confidential schedule. That schedule will be held on the Court file as a permanent record of the market data excised from the reasons for judgment cross-referenced to the relevant paragraphs of the judgment. 11 These Orders are now published from Chambers pursuant to ss 23 and 37P of the Federal Court of Australia Act 1976 (Cth) and rules 1.32 and 1.36 of the Federal Court Rules 2011. I certify that the preceding eleven (11) numbered paragraphs are a true copy of the Reasons for Judgment herein of the Honourable Justice Greenwood.
SCHEDULE OF PARTIES QUD 295 of 2008 Respondents Second Respondent: CEMENT AUSTRALIA HOLDINGS PTY LTD ACN 001 085 561 Third Respondent: CEMENT AUSTRALIA (QUEENSLAND) PTY LTD FORMERLY QUEENSLAND CEMENT LTD ACN 009 658 520 Fourth Respondent: POZZOLANIC ENTERPRISES PTY LTD ACN 010 367 898 Fifth Respondent: POZZOLANIC INDUSTRIES PTY LTD ACN 010 608 947 Sixth Respondent: CHRISTOPHER GUY LEON Seventh Respondent: CHRISTOPHER STEPHEN WHITE
Australian Competition and Consumer Commission
Cement Australia Pty Ltd