[2025] QCAT 321
General information, not legal advice.
Queensland Civil and Administrative Tribunal
2025-08-21
Original judgment source is linked above.
PROFESSIONS AND TRADES - BUILDERS - STATUTORY INSURANCE SCHEME - where there was a complaint of defective work with respect to a car port - where the Commission issued a direction to rectify - where the contractor failed to rectify in time - where the matter was referred to insurance - where a scope of work was prepared - where the contractor sought review of the scope of work in the Tribunal - where the decision about scope of work was returned to the Commission for reconsideration - where an amended scope of work was drawn - where the contractor claimed it was denied access to the site - where the home owner's failure to unlock premises on a particular day was not an unreasonable denial of access - where the amended scope of work was reasonable and necessary to rectify the defective work
Queensland Building and Construction Commission Regulation 2018 (Qld), Schedule 6 s 18(a)
Crocker v Queensland Building and Construction Commission [2024] QCAT 73
Middling v Queensland Building Services Authority [2005] QCCTB 14
The consumer is not entitled to claim assistance mentioned in section 15 if -
(a) the consumer has unreasonably refused the licensed contractor who carried out the defective work access to the site to carry out rectification work; ...
I just wanted to make it noted that we have called Barry today and attempted to book the installation of the base plates for Monday 25th. However, Barry was not willing to confirm access to the site.
We will wait for his cooperation.
I am requesting a further extension of time for the directive at ... as your client is again uncooperative. My building supervisor is now going on leave and we cannot be onsite until the end of September.
Extension requested: 30 September 2022
Hi Barry
As per the engineer's request there will be structural grout, under and around the base plates.
We have availability on Wednesday 3rd or Thursday 4th August for install. Does (sic) any of these days work for you?
Thanks
[25] I agree with the Authority's submissions that the exercise to be undertaken pursuant to the applicant's review of the Authority's quotation/scope of works is towards assessing whether the scope of works are works reasonable and necessary to rectify and/or complete the items referred to in the Authority's direction of 28 January 2003.
[26] In that regard it is neither relevant, nor is evidence admissible, towards questioning the Authority's Direction to Rectify, and whether the works are defective and/or incomplete such as to require rectification and/or completion.
MR COOKE: Okay. All right. So the generic form 15 that was used for the purposes of constructing this carport was a generic one; is that what you're saying?
MR BELL: That is correct.
MR COOKE: And this is by no means what you'd call a generic carport, is it?
MR BELL: No, it is not.
MR COOKE: Because in general terms it's bespoke in the sense that the design elements have a different shape than the standard type carport; that's right, isn't it?
MR BELL: It's - it's outside of the norm, yes.
MR COOKE: Yes. And one of the unique features of this carport as well is that it attaches to the house on one side, doesn't it?
MR BELL: That is correct.
MR COOKE: Yes. And that creates stability problems as well if it's not attached correctly; that's correct?
MR BELL: Yes, that is - would be a design consideration, the stability of the carport.
MR COOKE: Yes. And you didn't design the attachment to this particular home for this particular carport, did you?
MR BELL: No, I did not.
Supply and install 1800 x 90 x 35 mm MPG12 to side of rafters.
[1] At hearing Mr Heron clarified Ashcam returned 7 times to do work but on each occasion there was a meeting beforehand to work out what was needed - Transcript 1-83 Line 19.
Ashcam Pty Ltd
Queensland Building and Construction Commission & Anor [2025] QCAT 321