[2007] VCAT 1696
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2007-09-20
Mr J
Original judgment source is linked above.
[11] The purpose of clause 65(1)(b) stands out like a beacon. The purpose is to provide a permit applicant with security once a permit, licence, or works approval has actually been issued. That security is provided not only in respect of an objector appeal, but also in respect of the enlargement of time to permit an objector appeal out of time.
An application for review under section 82 of the Act must be made within 21 days after the responsible authority gave notice to the objector under section 64 of the Act.
An Objector may apply for review of the Decision of the Responsible Authority to grant a permit. The application for review must be lodged within 21 days of the giving of this notice.
(1) Where an Act or subordinate instrument authorizes or requires a document to be served by post (whether the expression "serve" or the expression "give", "send" or "deliver" or any other expression is used), the service shall -
(a) unless the contrary intention appears, be deemed to be effected by properly addressing, prepaying and posting the document as a letter to the person on whom it is to be served; and
(b) unless the contrary is proved, be deemed to have been effected at the time at which the letter would be delivered in the ordinary course of post.
[10] There are two components to section 49(1) and the application of each will normally yield a different date. Which date will be relevant will depend upon the circumstances and why it is important to know when a notice (or the like) has been given. The most common reason why the date of "giving" a notice will be important is to calculate some time limit. Which date is relevant - i.e the date the letter was posted or the date it was delivered - will depend upon who has the benefit of the time limit.
[11] Thus in the case of Wilbow Corporation Pty Ltd v Boroondara CC, I held that it was the responsible authority that had the benefit of the 28 day time limit for requesting further information under section 54 of the Planning and Environment Act 1987. Therefore what was important in that case was the date upon which the requirement for more information was sent, not the date upon which the requirement was received.
[12] In the present case, it is the objector who is given the notice of the decision who should have the benefit of the 21 day time limit within which to lodge an application for review. Therefore, the relevant date for calculating this time period should be the date upon which the notice is "received". Under section 49(1)(b) of the Interpretation of Legislation Act 1984 this would be when the letter containing the notice was delivered in the ordinary course of post, unless the contrary is proved.
[13] To ensure consistency and certainty when calculating time limits for the lodging of applications for review, the Tribunal's practice is to apply section 141 of the Victorian Civil and Administrative Tribunal Act 1998.
[14] Under the Victorian Civil and Administrative Tribunal Act 1998, section 140 deals with service of a notice, order or other document for the purposes of the Victorian Civil and Administrative Tribunal Act 1998. Section 141 provides as follows:
(1) For the purposes of this Act, a notice or other document must be taken to have been served on, or given to, a person or an unincorporated association -
(a) in the case of delivery in person - at the time the document is delivered;
(b) in the case of posting - 2 business days after the day on which the document was posted;
(c) in the case of facsimile or other electronic transmission - at the time the facsimile or transmission is received.
(2) If a facsimile or other electronic transmission is received after 4.00 p.m. on any day, it must be taken to have been received on the next business day.
(b) a public holiday or public half-holiday in the place to where the notice is sent or delivered.
[15] In applying section 141 of the Victorian Civil and Administrative Tribunal Act 1998 when determining the closing date for applications against a responsible authority's decision to grant a planning permit, the Tribunal will treat the date from which it calculates the 21 day period for applications for review under section 82 of the Planning and Environment Act 1987 as being two business days after the date on which the notice of decision was posted. ...
The need for certainty regarding the issue of permits
[3] See comments in Willbow Corporation Pty Ltd v Boroondara CC [2006] VCAT 437 [at 20]
Archerduck Pty Ltd
Ballarat CC [2007] VCAT 1696