[2023] NSWLEC 1768
Land and Environment Court (NSW)
2022-06-08
Original judgment source is linked above.
Judgment
Issues
The site and its context
Background and the proposal
Planning framework
Public submissions
Expert evidence
Contention 1 Development Control Plan/Urban Design
Contention 1A Vehicular and Pedestrian Access Planning
Contention 2 Floor Space Ratio (FSR)
Contravention of the FSR development standard
The Applicant's written request to contravene the FSR development standard
Wehbe 1
Webhe 5
Environmental planning grounds
Whether the proposal is in the public interest because it is consistent with the objectives of the contravened development standard and the zone
Findings regarding the cl 4.6 written request to contravene the FSR development standard
Contention 3 Adaptive Reuse of Existing Buildings
Contravention of the development standard under cl 6.11 of Leichhardt Local Environmental Plan 2013
The Applicant's written request to contravene the cl 6.11(3) of Leichhardt Local Environmental Plan 2013 development standard
Contention 4 Landscape Area
Contention 8 Streetscape and Heritage Impact of Adaptive Reuse Buildings
Contention 9 Streetscape Impact of Proposed Buildings
Contention 10 Impact upon Adjoining Buildings
Conclusion
Orders Proceedings 2021/228923
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 19 December 2023
Anprisa Pty Ltd
Inner West Council
(2018) 236 LGERA 256
(2007) 156 LGERA 446