[2025] NSWCATCD 116
General information, not legal advice.
NCAT Consumer and Commercial
2025-08-18
Original judgment source is linked above.
"Even if a dispute has arisen the parties must, unless acting in accordance with an express provision of this contract, continue to perform their obligations under the contract so that the work is completed satisfactorily within the agreed time."
(a) That contractors/trades coming the Premises were to contact the on site representative Mr Lewis before attending. The document says that that was a "clearly stated requirement". The respondent says that that did not occur.
(b) The respondent contends "deficient project progress reporting to clearly identify what work had been done". It says that it required clearly identified before and after photos.
(c) The respondent also raises "continuous staff turnover". It says that a Mr Gatley performed the original assessment and that a Mr Peterson provided a revised quotation. It then says that Mr Gatley had left the company and that a Bianca Moscato was the advised Project Manager but that she did not attend the site.
(1) The respondent is to pay the applicant $17,044.33 within twenty-one (21) days.
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.
AGC Roof Maintenance Pty Limited
The Owners Corporation of Strata Plan 7704 [2025] NSWCATCD 116;