[2025] FCA 690
General information, not legal advice.
Federal Court of Australia
2025-06-26
Goodman J
Original judgment source is linked above.
Counsel for the Cross-Claimant on the First Cross-Claim:
Solicitor for the Cross-Claimant on the First Cross-Claim:
Counsel for the Frist Cross-Respondent on the First Cross-Claim:
Solicitor for the First Cross-Respondent on the First Cross-Claim:
Counsel for the Second Cross-Respondent on the First Cross-Claim:
Counsel for the Third Cross-Respondent on the First Cross-Claim:
A.C.N. 168 479 614 PTY LTD (FORMERLY KNOWN AS STELLER DEVELOPMENTS PTY LTD) (IN LIQ) (RECEIVERS AND MANAGERS APPOINTED)
JAMES CIRELLI (and others named in the Schedule)
NICHOLAS SMEDLEY (and others named in the Schedule)
Costs order sought by the third and fourth respondents
Applicant's claim filed 14 December 2021 (applicant's claim)
(a) Mr Cirelli's costs be fixed in the sum of $50,000.00 (including any GST); and
(b) Mr Vines's costs be fixed in the sum of $160,000.00 (including any GST).
(a) the $50,000.00 paid by the applicant into the Litigants' Fund as security for Mr Cirelli's costs be released to Mr Cirelli; and
(b) from the $215,000.00 paid by the applicant into the Litigants' Fund as security for Mr Vines's costs, the sum of $160,000.00 (plus interest accruing from 5 May 2025 at the rate prescribed under r 39.06 of the Federal Court Rules 2011 (Cth)) be released to Mr Vines and the balance be released to the applicant.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
(1) Steller Developments should pay the costs incurred by Mr Smedley on the cross-claim;
(2) Steller Developments should pay Mr Smedley's costs (including any costs of the cross‑claim) on an indemnity basis, rather than a party and party basis; and
(3) Atlas Property Investment Management Pty Ltd, a third party, should be jointly and severally liable for costs payable by Steller Developments to Mr Smedley beyond costs of the principal claim on a party and party basis.
C. COSTS INCURRED BY MR SMEDLEY ON THE CROSS-CLAIM
The following principles can be derived from these authorities:
(1) The usual rule as to costs applies to proceedings as between defendant and third party, the "event" being the success or failure of the defendant's claim against the third party.
(2) Where the third party claim is dismissed because the plaintiff's claim against the defendant fails, the defendant will ordinarily be liable for the third party's costs of the third party proceeding.
(3) The award of costs remains a matter of discretion, however, and there may be circumstances of the case which justify a departure from the usual rule.
(4) In deciding (in a case of the kind referred to in (2)) whether any departure from the usual rule is warranted, the court will ordinarily need to consider at least the following matters:
- the reasonableness of the defendant's decision to join the third party;
- whether the joinder of the third party was reasonably foreseeable by the plaintiff, such that the plaintiff might be viewed as having some responsibility for the costs of the third party proceeding. (An order for the plaintiff to pay the defendant's costs may thus include the defendant's liability to pay the third party's costs of the third party proceeding.);
- the responsibility of plaintiff, defendant and third party, respectively, for the time taken up in the hearing of the third party proceeding.
These principles would apply equally to fourth party proceedings.
(1) it was plain that the cross-claim would stand or fall with the principal claim; and
(2) the principal claim was the catalyst for the cross-claim and Mr Vines was, by the cross‑claim, seeking to deflect onto the respondents to the cross-claim, any liability that might be imposed upon him in the principal claim.
(1) it was "far from self-evident" that the "Guarantors" objectively intended the "Issuer" to be "Steller Developments" when a conclusion that was at least equally available was that the reference in cl 2(a) (and recital A) of the 7 March 2017 Deed to the Master Facility Deed was mistaken and that the true intention, consistent with the remainder of the 7 March 2017 Deed (and with the approach taken in the 15 December 2016 Deed) was that those references were intended to be to the "Information Memorandum" as defined (Steller (No 3) at [43]);
(2) the proposition that the expression "Information Memorandum" should be construed as meaning the Master Facility Deed rather than "the information memorandum issued by [SIN] from time to time" was also "far from self-evident" (Steller (No 3) at [50]);
(3) it was "far from obvious" that the phrase "a direction by the requisite majority of Investors as specified in the Note Terms" was used in the 7 March 2017 Deed by dint of an oversight (Steller (No 3) at [55]);
(4) it was "far from self-evident" that the objective intention of the "Guarantors" was that the direction be issued by Atlas as a lone investor, rather than the "requisite majority of Investors as specified in the Note Terms" (Steller (No 3) at [57]); and
(5) to reach a conclusion that the intention of the "Guarantors" was to provide a personal guarantee to Steller Developments with respect to notes issued under the Master Facility Deed would be to engage in impermissible speculation and to travel well beyond the limits of the Court's powers to resolve errors by construction (Steller (No 3) at [60]).
(1) the rectification case was swiftly disposed of in Steller (No 3) at [65]:
The submissions made on behalf of Steller Developments do not address any prior common intention of the Guarantors that was not reflected in the 7 March 2017 Deed; and instead rely upon the terms of the 7 March 2017 Deed itself. There is no reason to infer that each of the Guarantors had a subjective intention which differs from the objectively determined construction of the 7 March 2017 Deed set out at [28] to [37] above. On this basis, the 7 March 2017 Deed is a correct record of the Guarantors' common intention, a proposition directly contrary to the position which must obtain if rectification is to be available. ;
(2) the rectification case was wholly misconceived because the whole purpose of rectification is to correct an instrument which does not reflect the subjective intention of the parties. It is nonsensical to suggest that one might achieve this outcome solely by placing reliance upon the terms of the instrument one seeks to correct;
(3) there was no reason to infer that the "Guarantors" had a particular subjective intention which differed from the objectively determined construction of the 7 March 2017 Deed, because no evidence was called to establish that they did;
(4) it is notable that Steller Developments did not seek to rely upon any documentary evidence in support of its rectification case - especially in circumstances where that evidence would have been in its own possession prior to the commencement of the proceeding - nor did it rely on oral evidence of the parties to the 7 March 2017 Deed. Four individuals were party to that deed; only three of whom gave evidence. Absent evidence from the fourth (Mr Pitard) about his subjective intention, there was no prospect that a rectification claim could succeed. Notwithstanding that obvious fact, Steller Developments took no steps to call evidence from him; and
(5) in those circumstances, Steller Developments should have always known that it would not be able to prove the facts that would support the relief it sought, and it commenced (and continued) the proceeding in wilful disregard of known facts.
I certify that the preceding thirty-seven (37) numbered paragraphs are a true copy of the Reasons for Judgment of the Honourable Justice Goodman.
STELLER ESTATE PTY LTD (IN LIQUIDATION) (RECEIVERS AND MANAGERS APPOINTED)
ACN 168 479 614 Pty Ltd (formerly known as Steller Developments Pty Ltd (in liq) (Receivers & Managers appointed)
Smedley, in the matter of ACN 168 479 614 Pty Ltd
(2003) 201 ALR 55
(2010) 31 VR 46
(1997) 7 Tas R 148