Access Strata Pty Ltd v Central Coast Council
[2024] NSWLEC 1402
At a glance
Source factsCourt
Land and Environment Court (NSW)
Decision date
2024-07-03
Source
Original judgment source is linked above.
Judgment (18 paragraphs)
- The applicant filed the amended plans and documents outlined above with the Court on 5 July 2024.
Orders
- The Court orders that: 1. The applicant is to pay the respondent's costs thrown away under s 8.15(3) of the Environmental Planning and Assessment Act 1979 as agreed or assessed. 2. The appeal is upheld. 3. Development consent is granted to Development Application No. DA/1847/2023, as amended, for the demolition of existing structures, amalgamation of two land parcels, removal of identified trees, and the construction of a single storey 85 place centre based child care facility with basement level parking on land legally described as Lot 22, Lot 23 and Lot 24 in Deposited Plan 21348, subject to the conditions at Annexure A.