28 Objectors said, they are frustrated over an alleged seven development applications on the site in the last two years or so. They are wary of any proposal on this land. That history is not relevant to the decision I must make on the merits of these amended plans and conditions now put forward by both parties as acceptable. I have considered the plans and conditions and the evidence as referred to above and I have formed the opinion there is nothing sufficient for me to refuse the consent orders forwarded by the parties.
29 The formal orders of the Court by consent are:
1. The appeal is upheld.
2. Consent is granted to the demolition of the existing building and construction of the new part 3, part 4 storey mixed use development containing 1 small shop, 7 units and associated parking on Lot 1 DP 15662 known as 30A Hastings Parade, Bondi Beach as shown on drawings 2007-014-A00, 2007-014-A01, 2007-014-A02, 2007-014-A03, 2007-014-A04 all Issue A of Brenchley Architects and dated 10 November 2008 and the Landscape plan and elevation join L-DA-01 Issue A prepared by LANDknit, as amended by and subject to the conditions in Annexure A.
3. The exhibits are returned to the parties except Exhibits A, B, C, D, 4 and 5 shall be retained on the Courts file.