### sec.480 Requirements for making application
The application must be—
in the approved form; and
state whether or not the applicant has complied with chapter 5 , part 7 , for reports required to be lodged in relation to the licence; and
accompanied by—
the application fee prescribed under a regulation; and
if the application is made less than 20 business days before the end of the term of the licence—an amount that is 10 times the application fee.
s 480 amd 2004 No. 26 s 164 ; 2012 No. 20 s 281 sch 2
- (a) in the approved form; and
- (b) state whether or not the applicant has complied with chapter 5 , part 7 , for reports required to be lodged in relation to the licence; and
- (c) accompanied by— (i) the application fee prescribed under a regulation; and (ii) if the application is made less than 20 business days before the end of the term of the licence—an amount that is 10 times the application fee.
- (i) the application fee prescribed under a regulation; and
- (ii) if the application is made less than 20 business days before the end of the term of the licence—an amount that is 10 times the application fee.
- (i) the application fee prescribed under a regulation; and