Zhang v Popovic
[2016] NSWSC 666
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2016-05-05
Before
Adamson J
Source
Original judgment source is linked above.
Judgment (4 paragraphs)
The application by NTI that Mr Tabuso pay its costs of the joinder of ROC
- By notice of motion filed on 28 April 2016, NTI applied for the following orders: 1. That John Tabuso pay the costs of NTI incurred and thrown away by reason of the joinder of the Seventh Defendant to these proceedings excepting to the extent that any such costs are ordered to be paid by another party to the proceedings. 2. That John Tabuso pay the costs of this application.
- I was informed at the short hearing on 5 May 2016 (before further written submissions were provided) that Mr Tabuso may have been an undischarged bankrupt. However, since that time I have been informed that it is agreed between respective counsel for NTI and Mr Tabuso that NTI does not require leave to proceed against Mr Tabuso under s 58 of the Bankruptcy Act 1966 (Cth). Although Mr King SC, who appeared with Mr Palmer for the plaintiff, indicated on 5 May 2016 that the plaintiff was considering filing a notice of motion to the same effect as that filed by NTI, the plaintiff did not ultimately press any such motion. Accordingly, the only extant motion is that of NTI referred to above.
- NTI submitted that an order should be made against Mr Tabuso pursuant to s 98 of the Civil Procedure Act on the bases that he had played an active role in the litigation; his wrongful conduct caused NTI to join ROC; and he ought, accordingly, bear the cost of the joinder. NTI also submitted that although Mr Tabuso might not have been directly involved with all the consequences of his initial falsehood (such as the subsequent amendment to the statement of claim by the filing of the sixth amended statement of claim) he, as it were, set the ball rolling and should be held liable for all the consequences.
- Mr Afshar, who appeared on behalf of Mr Tabuso, submitted that NTI had failed to discharge its onus of establishing the requisite matters that would form a proper basis for making a non-party costs order. Mr Afshar identified the following relevant findings from the principal judgment (some of which are set out in the reasons above): 1. The accident took place on 16 September 2007. 2. In May 2008 Mr Tabuso told a WorkCover inspector that Hoxton had installed the clevis mounts although this work was probably done by Interfreight ([29], [69]-[71] of the principal judgment). 3. On about 2 June 2009 NTI instructed its solicitor, Mr Hedges in relation to the question of its liability under the NTI Fleet Motor Policy (the Policy). 4. On about 17 September 2010 NTI was joined to the proceedings. It admitted that the Policy covered the liability of the first three defendants but refused indemnity on the basis of various exclusion clauses ([5] of the principal judgment). 5. In November 2010 Mr Tabuso told Mr Steven Hall, a welding inspector retained by NTI, that Hoxton had installed the clevis mounts. Mr Hall had difficulty reconciling Mr Tabuso's statements at the site visit with photographs of the trailer Mr Hall reported his disquiet to NTI in the following terms: I am not fully convinced that the bracket produced by the owner [John Tabuso] has not been removed and replaced additionally to what had been mentioned at the time of the site visit. The bracket may have been removed and reused by the various companies carrying [out] the work on the trailer or by the owner himself if the bracket had in fact broken off in the time before the said accident involving Mr Zhang." ([81] of the principal judgment). 1. On 18 January 2013 the plaintiff was granted leave to join ROC. He alleged that ROC had negligently installed the clevis mount and was therefore responsible for the failed weld. 2. ROC served evidence that it had not installed the clevis mount. The plaintiff thereafter sought leave to amend his pleading to allege that ROC was negligent in failing to ensure that the clevis mount was secure and sound before it installed the hydraulic system for the elevation of the ramp on it. Leave was granted, as a result of which the plaintiff filed the sixth amended statement of claim on 4 November 2015. 3. The accident was caused by the failure of the clevis mount ([46] and [66]). 4. Neither Mr Sanchez, nor Mr Tabuso was a credible witness. 5. NTI defended the proceedings on several bases, but principally on the basis that its liability was excluded by the Policy. This was independent of any involvement of Mr Tabuso.