Conditions 84 and 87 - Flood analysis and finished levels
53 The council has always been aware of the flooding potential for the site. Starting with a site audit report by Coffey and Parkes in 1999 through to December 2002 when flood related issues raised by the applicant and others were the subject of comment by Ms Martin in her report.
54 It is the opinion of Mr Nash that, based on the information provided to the council in support of the development application, including the RAPs, the EIS and the requirements of the EPA and ANZECC guidelines, the council should have been in a position to form a balanced view in regard to future capping integrity under flood conditions. Mr Hosking's evidence is to a similar effect. In the opinion of Mr Hosking it was appropriate to provide conditional site auditor approval of the RAPs and SEMPs notwithstanding that the site was flood prone land. There is no evidence to support a conclusion that the council simply turned a blind eye to all of the above information and took no account of the potential impact of flooding on the development itself. The advice it had from the experts was that the containment proposal would work despite flooding of the site.
55 If the advice proves to be wrong and the containment cell cannot be built unless there are radical changes to the design then that will be an issue to be addressed at the time of its determination. For the moment the proposal is to build in accordance with the design on the basis of the opinions and advice regarding potential impacts accepted by the council at the time of its determination.
56 The council was entitled to conclude that any variation in surface level would not alter the overall remediation concept of the proposed cell. Mr Nash's evidence has re-iterated this advice.
57 Ms Martin's report deals with flooding impacts and notes and comments made by the council Development Engineer that:-
s The site is subject to inundation in a 1 in 100 flood event with the majority in the fringe or low hazard area
s The site is bisected by an existing stormwater pipe which conveys stormwater from Beardy Street to Dumaresq Street.
s Additionally the site contains an overland flow path that operates when the pipe system can no longer cope with the discharge. It is essential that this overland flowpath be retained during and post encapsulation to ensure flood levels in the Beardy Street precinct are not raised as a result of this development.
s The Armidale Flood Mitigation Study has identified the site as flood prone and as such any additional filling on the site will impact on the predicted flood height upstream of the development.
s In October 2000 it was identified that due to the bulk of part of the building (initial shopping centre proposal in DA 9900/3480 occupying some of the flood plain, provision had to be made within the development for floodwater storage. Consulting Engineers, Tierney and Partners, provided some sketches and flood modelling analysis, indicating that the loading dock at the rear of the premises would be excavated to provide additional storage for flood water to compensate for the loss of floodplain as a result of the building footprint. These details will need to be taken into account in determining the finished surface level of the carpark to ensure no loss of flood plain storage. Details should be provided and approved by Council prior to the commencement of construction.
s In relation to the filling plan there appears to be approximately 150mm of fill in the immediate vicinity of the property at 106 Jessie Street.
58 Condition 84 is in the exact terms of a recommendation by the engineer.
59 Mr O'Rourke correctly concedes that the council did take the issue of flooding into account during its consideration of the development application. However, his point is that when condition 84 and condition 87 are read together it is apparent that the council did not take into account the impacts that the building of the remediation works might create. The evidence simply shows there was a concern. But ultimately the impacts were not assessed. Mr Nash so much as acknowledges this omission when he says, as quoted above at [43], that "final site levels are required to be known from the point of view of flood analysis and mitigation".
60 It is contended by the applicant that the flood analysis may lead to a different development to the development, which the council purported to approve. Furthermore, the impact on flood patterns has not been assessed (Mison and Others v Randwick Municipal Council (1991) 23 NSWLR 734 at 740; Cameron v Nambucca Shire Council (1997) 95 LGERA 268 and Weal v Bathurst City Council and Another (2000) 111 LGERA 181).
61 Unlike condition 3 and condition 5, condition 84 has an addendum by way of a paragraph referred to as "Advising" in the following terms:-
ADVISING
As the site is proposed to be redeveloped post remediation as a commercial shopping centre, it is advised that the flood analysis should be undertaken with the proposed footprint of the development included in the analysis to establish any additional floodway capacity areas required as a result of the placement of building structures within the floodway.
62 No provision is made for review of the development or the means to impose conditions requiring the developer to establish "any additional flooding capacity areas". It is open for the Court to construe the condition to have the effect that any information forthcoming to the council from the flood analysis is only for its information. There is no provision for modification of the development in any way. Nor is there any capacity to impose further conditions to deal with an adverse report on floodway capacity.
63 The Court rejects the submission by the respondents and, in particular, the first respondent that condition 84 ensures that neither the remediation works nor the future shopping centre will have an adverse effect on flood levels. There is no mechanism whereby any remedy, that is perceived to be necessary as a consequence of the outcome of the flood analysis, is to be implemented or enforced. The final site levels are not known. Even though eventually the projected range of levels may be achieved, the issue has not been finally determined.
64 The respondents rely on a series of historical documents starting with the 1999 Coffey report. However, none of the references, although recognising the location of the site as being in a floodway, address the issue of the potential effect on other properties, specifically as a consequence of building the containment cell as proposed in the latest development application. The council had been informed about the likely impact of the construction of the proposed retail development on flood behaviour. However, the design of the soil treatment works has arisen as a consequence of the deferred commencement conditions in the development consent granted in respect of the shopping centre development. The Court is not in a position to conclude that the flood studies, reports and reviews undertaken for the purpose of assessing the shopping complex applications took into account the specific development of the subject containment cell.
65 The requirement for a detailed flood analysis prior to the issue of a construction certificate does not reflect the two stages of the planning process. If the flood analysis dictates that changes to the design are necessary in order to alleviate the flooding impacts upstream and downstream of the site and the plans presented for certification nonetheless take no account of those changes but are otherwise in accordance with the approved concept there is no basis for accepting that the changes are mandated by the operation of the condition and can be enforced pursuant to its terms. Furthermore, the nature of prospective changes is essentially a matter of conjecture.
66 The issue is not just that the council failed to finally resolve the form of the development. More importantly, and indeed critically, the condition discloses that the council neglected to inform itself specifically about the effect on flooding capacity.
67 Moreover, it discloses an omission to consider the means, if any, by which it could ensure that the Dumaresq Creek flood levels upstream and downstream will not be affected by any changes to site levels following construction of the cell. It has been assumed that the levels achieved will be consistent with the levels adopted for the shopping centre. The terms of the condition itself recognises that there is no stipulation to that effect. It leaves the undertaking of the flood analysis to a future time after the actual site levels have been finally determined and submitted to the council. Otherwise, there could be no point of imposing the condition. That the final surface levels are yet to be determined is further confirmed by condition 87.
68 Even if the council had regard to the potential flooding impact in general terms, or the Court can recognise the accumulation of knowledge from the consideration of earlier development applications in respect of the retail development, it is not sufficient merely for the council to be aware of the problem. There needs to be an understanding and evaluation of the possible impacts of flooding before it can be accepted that the council relevantly took the flooding impact, as it relates to the subject development into consideration (see Priestly and Giles JJA in Weal). The council recognised, by the addition of condition 84, that the process of evaluation could not be completed without the flood analysis. If the council intended to prohibit development, except in the absence of impact upstream and downstream of the site, it failed to do so either by making the carrying out of development conditional upon that fact being demonstrated or by providing a mechanism to ensure the implementation of measures to ensure a desired outcome.
Whether development consent is required
69 The first respondent raised this issue in an amended points of defence filed on 1 September 2003. Notwithstanding the late filing of the amended points of defence leave was granted to rely on [15] as follows:-
In further defence of the entirety of the Points of Claim the First Respondent says that the development which is the subject of the Consent does not require development consent.
70 It is contended by the first respondent that the remediation work is classified as "category 2 remediation work" as defined in cl 14 of SEPP 55. That is, a remediation work that is not category 1 remediation work of a kind described in cl 9(a) to 9(f) of SEPP 55. The applicant submits that the proposed remediation work is relevantly "designated development" within the meaning of cl 9(a).
71 It is not in issue that each of the measures, including the demolition of existing buildings and structures, is concerned with "removing, dispersing, destroying, reducing, mitigating or containing" contamination within the definition of "remediation" contained in cl 4 of SEPP 55.
72 Relevantly, "contaminated soil treatment works" are defined under cl 15 of Pt 1 of Sch 3 - Designated Development to the Environmental Planning and Assessment Regulation 2000 ("the EPA Regulation").
73 Both parties have concentrated on the effect of cl 15(c)(ii). The applicant also refers to cl 15(a)(v). The relevant parts of cl 15 are reproduced as follows:-
15 Contaminated soil treatment works
Contaminated soil treatment works (being works for on-site or off-site treatment of contaminated soil, including incineration or storage of contaminated soil, but excluding excavation for treatment at another site):
(a) that treat or store contaminated soil not originating from the site on which the development is proposed to be carried out and are located: