© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2012] NSWLEC 248
Land and Environment Court (NSW)
2012-11-07
Sheahan J, Talbot J, Mr P
Original judgment source is linked above.
Introduction 1The Court is asked for an urgent ruling as to whether elements of a development the subject of a Class 1 appeal, listed for hearing this week, render it "designated development", such that an environmental impact statement will be required.
The subject site 2The subject development is proposed for Lot 2 DP 608814 and Lot 111 DP 541783, known as 64-80 Sandgate Rd, Wallsend, or Birmingham Gardens, is an unusually shaped area of 9.778 ha, of which 1.55 ha has been identified as suitable for development of a seniors living project such as is proposed. 3The site is located between the Dark Creek canal to its north and Sandgate Rd to its south. It is also situated within the Hunter River floodplain, and is mostly classified "flood fringe" and partly "flood storage", under flood mapping adopted by the Council, after its refusal of the relevant development application. The site drains to Dark Creek including through a small drainage channel, which runs, generally, south-to-north through the centre of the land to the west of the main development site.
Contamination 4The site is extensively contaminated, largely from the days of its partial use as a scrap metal/recycling operation, with associated petroleum storage and usage. The Court understands that that use ceased in 1999, that some buildings were later demolished, and that the underground storage tanks were removed, but the site has been vacant and little used otherwise, since, except that there is a greyhound track to the north, on the other side of Dark Creek, and apparently its patrons use this land for parking. 5It is common ground that the remaining contamination can be effectively dealt with, and that the residential proposal cannot proceed on the site in its present state. The owner of the site commissioned a Remediation Action Plan ('RAP'- dated August 2010, and annexed to Ian Gregson's affidavit of 31 October 2012), and the site obtained a reasonably favourable assessment from the Environment Protection Authority ('EPA') on 14 February 2012 (Exhibit T2).
The Planning regime 6The site's zoning, under Newcastle Local Environmental Plan ('LEP') 2003, was partly 2(a) Residential and partly 7(c) Environmental Investigation, and, under the Newcastle Local Environmental Plan 2012 ('2012 LEP'), which was in draft at the time of Council's assessment of the project, partly E3 Environmental Management and partly E2 Environment Conservation. Under the 2003 LEP, the residential project component, as such, would be on the 7(c) land, but seniors housing is prohibited in both E2 and E3 zones under the 2012 LEP, and must rely on the State Environmental Planning Policy (Housing for Seniors or People with a Disability) 2004 ('SEPP') for development consent. 7On 16 November 2010, the Director General of the Department of Planning issued a site compatibility certificate, pursuant to cl 25 of that SEPP. That certificate will expire on 16 November 2012, hence the expedition of the appeal, and the urgency of the present separate question. An application was made by the applicant for a new certificate, apparently around the time of the launching of the appeal, but no decision has yet been made.
The Project DA 8The relevant development application (DA 10753 - Exhibit T1) was lodged on 20 December 2010. It specified the "type of development" as "building or structure", "demolition", and "earthworks", and sought consent to: a. remediate a portion of the site to a standard suitable to support residential use; (Area A or 1 - for simplicity referred to herein as the RED area) b. use another portion of the site for the containment of contaminated soils excavated from the site in 2 capped mounds of contaminated material. Approximately 27,480 cubic metres of soil are proposed to be excavated and placed in the capped mounds; (on Areas B1/B2, to which I will refer as the WHITE areas) c. refill the excavated area with clean fill to the required flood level; (Areas 2, 3, and 4, to which I will refer as the GREEN area) d. erect a Seniors Living Development including 29 x 2 bed, 17 x 3 bed dwellings and community hall (staged development) on the remediated portion of the site. (the RED area) (The area numbering, and the colour "code" in the above, is drawn from figure 4.2 of the RAP, but the numbers, and the letters 'A", "B", etc, are used on various figures.)
The RAP 9The RAP of August 2010 indicates that the site has been comprehensively assessed. The underground fuel tanks were removed (from the RED area), but heavy metals and some asbestos remain (p10). 10The RAP says (p4) that, in its current state, the site poses no risk to the environment or neighbouring properties, and its remediation is not an "environmental imperative". Remediation options, both on-site and off-site, are canvassed (pp12-13), with "cap and contain" preferred. A detailed plan is developed for the work (pp13-15), and for the longer-term management of the site (p20).
The SEE 11A Statement of Environmental Effects ('SEE' - Exhibit C1) was prepared in June 2011. 12The SEE says (p10) that: The remediation will actually improve the site by containing the excavated material within compacted and vegetated mounds that are graded to increase the ration of run-off to infiltration. In its proposed future zoning and use, the site will not require further remediation. As stated in the ... RAP ... a long term management plan will be prepared following remediation, outlining any future monitoring and/or management requirements. It is likely that the only requirement for future monitoring is one which checks the integrity of the mound (i.e. addresses any potential erosion). Lots 2 and 111 will then both be owned by the owner of the seniors living development. 13In section 3.9.3 (at p16), the SEE continues: In its present state, the OneSteel property contains contaminated fill material dispersed over a reasonably large proportion of the site. Due to the dispersed nature of the pollutants (mainly metallic by-products from the lead and zinc smelting process and impurities associated with reject coal wash material), there is an ongoing risk of pollutant emissions from the site via the air (as dust), via groundwater, and via surface overflow. The risks translate into possible impacts on human health and the environment via pathways such as ingestion or absorption. While there are potential risks of adverse impacts to humans and the environment, the actual risks have been assessed as being very low ... and the site does not require remediation for it to remain unoccupied or to have its present temporary use by Energy Australia. However remediation is required for any residential occupation of the site. Also, the construction of the mound and the regrading of low spots on the site will further reduce the already low contamination risks of the non-residential area of the site. 14In section 3.9.4 (at p17), the SEE notes that "leaving the site unremediated is not considered to be the most desirable outcome for the community". 15In section 5.13 (at p41), the SEE continues: The Site Auditor has been involved in the initial discussion of the revised project, in the formulation of the additional groundwater investigation and has reviewed the groundwater reports findings. The Site Auditor fully supports the revised remediation proposal. As a result, the project will include the excavation of contaminated soil with subsequent re-filling, re-grading and surface stabilisation with imported fill (VEHM) as necessary, treatment of excavated materials as required, the emplacement of excavated material and possibly other on-site materials into a mound that will be sealed with appropriate environmental controls applied.
Council Assessment and Refusal 16Additional information was required, and Council officers had a series of negotiations or discussions with the applicant, eventually recommending approval (Exhibit T3). However, the Council resolved, on 13 March 2012, to refuse the DA, and the notice of determination states the following reasons for refusal (emphasis mine):
The present appeal 18The Class 1 appeal was lodged on 17 September 2012, one day before the expiry of the statutory six month limitation period, and Council quickly briefed external experts on the complex contamination and flooding issues involved. 19On 5 October 2012, the applicant filed a motion for expedition of the hearing, and expedition was granted on 12 October by the Acting Registrar, who also gave a series of directions, including fixing a preliminary conference under s 34 for 29 October 2012, and a hearing for 8 November 2012. Commissioner Hussey was allocated to both fixtures.
The question of designated development is raised 20The Council had filed its Statement of Basic Facts and Contentions ('SFC') on 19 October 2012. Contention 1 relevantly asserted - the applicant says for the very first time - that the proposed development is "designated development", meaning that consent cannot be granted until/unless an environmental impact statement has been prepared and exhibited according to the Environmental Planning and Assessment Act 1979 ('the EPA Act').
The Section 34 process 21Commissioner Hussey conducted the preliminary s 34 conference on 29 October 2012, and accepted into evidence a joint statement on the questions of flooding prepared by Dr Phillip Haines, on behalf of the applicant, and Mr Mark Babister, on behalf of the respondent. 22The Commissioner prepared a conference report in the following terms: 1 Drainage contention discussed, resolved and deleted.
2 Contamination remains substantive issue, with particular reference to the status of the proposed "storage area" on which the contaminated soil is to be placed and capped, as to whether this constitutes Designated Development.
3 Motion to be lodged by A on Designated development question i.e. Contentions 1 and 2.
4 Matter listed for hearing 8, 9 Nov and parties agree to Hussey determining matter, if no s 34 Agreement in meantime.
5 S34 adjourned until 9.30, 8 November 2012, proceeding to determination if no agreement.
.1 Parties to file Joint Expert Contamination Report by 2/11/12.
The separate question arises 23A Notice of Motion ('NOM') was filed on the next day (30 October), on behalf of the Council, seeking an order that the question of whether or not the development application is an application in respect of designated development be determined as a separate question. 24If the answer to the separate question of law is determined in the affirmative, the NOM asked that the appeal be dismissed. 25The parties agreed on 31 October that I, as Duty Judge, should order the separate question, and I directed that the relevant experts (Mr Greyson for Council, and Dr Zines for the applicant) confer on a disagreement between counsel as to a proposed agreed statement of facts. The parties and experts came back to Court next afternoon (1 November), and I heard evidence and argument on the question, which will now be answered in what follows.
Designated Development 26In s 4 of the EPA Act, "development" means (emphasis added): (a) the use of land, and (b) the subdivision of land, and (c) the erection of a building, and (d) the carrying out of a work, and (e) the demolition of a building or work, and (f) any other act, matter or thing referred to in section 26 that is controlled by an environmental planning instrument, 27Section 77A (which s 4 calls up to define "designated development") provides as follows: 77A Designated development (1) Designated development is development that is declared to be designated development by an environmental planning instrument or the regulations. (2) Designated development does not include State significant development despite any such declaration. 28The following particulars were provided by the SFC, in respect of Contention 1, which asserts that the development proposed in this matter is "designated development" (see [20] above): (a) The proposed development involves works for the on site treatment and storage of more than 30,000 cubic metres of contaminated soil originating exclusively from the site on which the development is located, namely
i. Approximately 27,480m3 of contaminated soil is to be relocated to the site of the proposed mounds;
ii. Approximately 14,700m3 of contaminated soil is already present at the location of the proposed mounds;
iii. Together approximately 42,180m3 of contaminated soil is proposed to be treated by capping and stored on site.
(b) The proposed development involves works for the on site treatment of contaminated soil originating exclusively from the site on which development is located which disturb more than an aggregate area of 3 hectares of contaminated soil, namely:
i. Approximately 2.93 hectares of contaminated soil is to be disturbed by the relocation of contaminated soil to the proposed mounds
ii. Approximately 1.47 hectares of contaminated soil at the location of the proposed mounds is to be disturbed by the preparation of the areas of the proposed mounds including removal of vegetation and levelling;
iii. Together approximately 4.4 hectares of contaminated soil is proposed to be disturbed. 29These numerical particulars are relevant to the Court's consideration of the application of Schedule 3 of the Environmental Planning and Assessment Regulation 2000 ('The Regulation'), dealing with "designated development". 30Essentially, as s 3.2 of the SEE makes clear, the triggers for the Schedule's application to the subject site requires the inclusion, in both the volumetric and area calculations, of the WHITE lands (the site proposed for the mounds). 31Clause 4 of the Regulation, which calls up Schedule 3, relevantly provides as follows: 4. What is designated development? (1) Development described in Part 1 of Schedule 3 is declared to be designated development for the purposes of the Act unless it is declared not to be designated development by a provision of Part 2 or 3 of that Schedule. ... 32The present proposal does not involve any contaminated material from other than the subject site. 33Part 1 of Schedule 3, which defines designated development, includes the following clause (emphasis mine): 15 Contaminated soil treatment works Contaminated soil treatment works (being works for on-site or off-site treatment of contaminated soil, including incineration or storage of contaminated soil, but excluding excavation for treatment at another site): ... (c) that treat contaminated soil originating exclusively from the site on which the development is located and: (i) incinerate more than 1,000 cubic metres per year of contaminated soil, or (ii) treat otherwise than by incineration and store more than 30,000 cubic metres of contaminated soil, or (iii) disturb more than an aggregate area of 3 hectares of contaminated soil. 34Part 3 of the Schedule is headed "What is excepted from designated development?", and includes (emphasis mine): 37A Ancillary development (1) Development of a kind specified in Part 1 is not designated development if: (a) it is ancillary to other development, and (b) it is not proposed to be carried out independently of that other development. (2) Subclause (1) does not apply to development of a kind specified in clause 29 (1) (a). (Clause 29 deals with sewage systems and sewer mining systems, not relevant to the present proceedings. Clause 29, in its present form, and cl 37A were added to the Schedule by amendments, gazetted on 1 March 2007, the purposes of which were stated to be: (a) to remove storage facilities for sewage or effluent and some small-scale sewerage systems or works (including those that reuse sewage or effluent) from the categories of development that are prescribed as designated development, and (b) to make it clear that (apart from some sewerage systems or works) ancillary development (which would otherwise be considered to be designated development) is not designated development if it is ancillary to other development and is not proposed to be carried out independently of that other development.) 35The relevant provisions of the Regulation were considered by Talbot J in WRF Property Pty Limited v Armidale Dumaresq Council [2003] NSWLEC 223 ('WRF'), to which both parties referred in their submissions to me on the question. 36In that case there were RAPs and other environmental management plans ('EMP') in place, a "capping and containment" remediation strategy had been adopted, and the ANZECC requirements were considered. There were "hot spots" to be removed, and one risk to be managed was presented by "gasworks wastes", which may cause "volatile emissions". An "engineered cap" was to be placed over a "containment cell", and gases were to be released at controlled external areas (see [20] - [22] of Talbot J's judgment). Clearly, on the facts, there were greater environmental challenges to be faced than in the present case. 37His Honour dealt with all the technical issues and then said (emphasis mine): 78 The first respondent seeks to establish that the proposal for the construction of the containment cell in Area 1 and the capping layer in Area 2 does not constitute treatment and storage of contaminated soil on the basis that the proposed works will not "treat" contaminated soil. Mr Craig's argument is that the soil will not be subject to any chemical or other process or action to eliminate or reduce the contaminants in the soil and there will be no physical or chemical change to the soil. This submission, in the Court's view, overlooks the natural process of attenuation over time, the movement of groundwater and the ventilation of gases which, together with the removal of hot spots, will have the effect in both the short and long term of changing the constituents in the soil and the level of contaminants. Mr Craig submits that while this may constitute "treatment" of the contaminants it is not treatment of the soil itself. It is difficult to understand how the treatment of contaminated soil can be regarded as distinct from a treatment of contaminants in soil when it is the latter that characterises the soil as contaminated soil. The two aspects are integrated and should not be treated in isolation.
79 Both parties made reference to the decision in Remath Investments [No. 6] Pty Limited v Botany Bay City Council [No. 2] (Talbot J, NSWLEC, 11 December 1996, unreported). There are two significant distinguishing factors between what the Court is now addressing and the circumstances as they applied in Remath. Firstly, the definition of contaminated soil treatment works in Sch 3 to the EPA Regulation has been amended. Secondly, the proposal at the Remath site is similar to what is presently proposed only to the extent that the applicant in that case proposed a cap over the site.
80 The Court is satisfied that the development consent granted by the first respondent authorises the on-site treatment of contaminated soil.
81 The Court is also satisfied that the construction of the purpose-built containment cell will provide a chamber for storage of contaminated soil. It is not inconsistent with the accepted meaning of the word "store" as a means of providing for the safe-keeping of material for an indefinite period. The noun "storage" can have a corresponding and consistent meaning of the fact of storing for the purpose of maintaining material in a separated state. Although the particulars provided with the points of defence assert that the remediation works do not involve the treatment and storage of more than 30,000 m3, the Court does not understand the first respondent to claim that there is less than 30,000 m3 of contaminated soil on the site. The evidence is to the contrary.
82 Notwithstanding that there will be no importation of materials from off-site, the Court is satisfied that the proposals are relevantly works for on-site treatment and storage of contaminated soil. The works will treat contaminated soil originating exclusively from the site by means other than incineration. The containment cell proposed for part of Area 2 will comprise storage of contaminated soil. The volume of soil which is contaminated and is to be the subject of treatment and storage exceeds 30,000 m3.
83 The Court is satisfied, on the balance of probabilities, that the development application is in respect of contaminated soil treatment works within the meaning of that term as it is used in cl 15 of Sch 3 to the EPA Regulation and therefore development consent is required. 38In the unreported 1996 Remath [No 6] judgment, to which his Honour referred (at [79] in the above extract), His Honour had said (at p 6), in concluding that he was not satisfied that the test of designated development was made out (emphasis mine): It is the council which asserts that what the applicant proposes will amount to designated development. The evidence does not disclose that more than 30,000 m3 will be excavated. The prospect is that minimal amounts of soil will be moved around the site. The pre-existence of the soil on the site disposes of any question of storing the contaminated soil. Accordingly, for the purposes of cl3(b) of the definition, contaminated soil will not be relevantly treated or stored on the site. It is equally certain that the proposal does not involve disturbing more than an aggregate area of 3 ha of contaminated soil.
The expert evidence 39The respective experts prepared a joint report (Exhibit T4 - presented in the form of a revised Statement of Agreed Facts), and they gave concurrent oral evidence. The joint report relevantly states as follows: 11. Figure 4.1 of the RAP depicts the area and depths of contaminated soil on the site the subject of the Application. That area is at least 4.4 hectares. The volume of contaminated soil is at least 42,180 cubic metres.
currently present a potential risk of causing harm to the environment by mobilisation, including by leaching to "perched" groundwater (if present), by physical disturbance, and by wind erosion; leading to potential risk to human health resulting from subsequent exposure. It has been demonstrated that the leachate is not impacting the underlying groundwater which lies beneath a layer of confining clay underlying the fill material, and there are elevated dissolved metal concentrations (above ANZECC 2000) naturally occurring in the deeper groundwater system. There is not reported use of groundwater and no use of groundwater is intended on site, and therefore the risk of exposure to human health from groundwater beneath the site does not exist. The environmental management measures during construction, as outlined in the RAP, will further minimise the potential of exposure to air borne contaminants (if any) arising from wind erosion.
Consideration 47The real contest revolves around whether cl 37A provides, as Mr Howard argues, a "complete answer" to Mr Larkin's case that cl 15 is engaged by the DA before the Court. 48All the processes involved in the site preparation phase of the development are "works", and, in combination, involve bringing about some change to the contaminated soils, if not to the contamination itself, and, Mr Larkin argues, involve "treatment" and "storage" within the meaning of cl 15(c) of the Regulation. He also argues that those two processes are not mutually exclusive, and can overlap - "storage" can be, but is not always, "treatment", and "treatment" may or may not involve "storage". 49Mr Howard contends that cl 15(c) is not engaged, and that, consistent with Talbot J's reasoning in WRF (see [35] - [37] above), "storage" of soils, as in "containment", without any application of a process or substance to them, to bring about some change in them, cannot amount to "treatment", any more than leaving them in situ, as with the soils under the surface of the WHITE areas, amounts to a "treatment", even though Talbot J recognised that, in situ, natural processes occur. Mr Howard draws attention to the inclusion of the conjunctive "and" in cl 15(c)(ii). 50The creation of the mounds is a "storage" measure but the compaction of the materials, and their "capping", and their "shaping" to ensure "free drainage", amount to "treatment", and, contrary to Mr Howard's submissions, I believe that their establishment on top of existing contamination amounts to a "treatment" of that material as well, as it adds to the safety of humans and the environment. 51The actual wording of the statutory definition of "development" negates several of the submissions made by Mr Howard. He failed to carefully distinguish what was "a work", as mentioned in s 4, from what might be considered "a works", as in a premises or facility, establishment, or undertaking, with a purpose: Parramatta City Council v Brickworks Ltd [1972] HCA 21, 128 CLR 1, cf Merri Creek Quarry Pty. Ltd. v Foletta [1951] HCA 12, 82 CLR 347 (and see also T p 46, LL 15-18). 52He, in fact, descended to a level of specificity of "activities, transactions or processes", which was proscribed by Royal Agricultural Society (NSW) v Sydney City Council (1987) 61 LGRA 305, upon which he relies. See also Chamwell Pty Ltd v Strathfield Council [2007] NSWLEC 114, 151 LGERA 400. 53True it is that all of the earthworks proposed are being undertaken to make the site suitable for development of the proposed seniors' living project, but, although they vary in intensity across the various sectors of the site, and in the areas of land affected, they are collectively substantial, none of them could be regarded as de minimis, and, they will "disturb" the whole of the site. 54The insertion of cl 37A in Schedule 3, on 1 March 2007, followed the Court of Appeal's decision in Residents Against Improper Development Inc v Chase Property Investments Pty Ltd [2006] NSWCA 323, 149 LGERA 360, which dealt with some conflicting authorities in this Court, following Pain J's decision in Maxwell v Hornsby Council [2002] NSWLEC 92, 120 LGERA 386, in the context of sewerage systems forming part of development proposals. 55That line of authority reviewed leading decisions on the characterisation of development, dating back to Glass JA's seminal decision in Foodbarn Pty Ltd v Solicitor-General (1975) 32 LGRA 157, and including CB Investments Pty Ltd v Colo Shire Council (1980) 41 LGRA 270, Macquarie International Health Clinic Pty Ltd v University of Sydney, (1998) 98 LGERA 218, Baulkham Hills Shire Council v O'Donnell (1990) 69 LGRA 404, and others, many of which I also surveyed at length, in Bardsley-Smith v Penrith City Council [2012] NSWLEC 79, especially at [229] - [248]. 56Mr Larkin submits, and I accept, that cl 37A abrogated the decision in Chase, and reinstated and reinforced the appropriateness of the principles laid down in, particularly, O'Donnell, namely that the test of the concepts of "ancillary" and "independent" development/use (including any allegation that one might "subserve" another) is objective in character, is a question of fact and degree in all the circumstances, and is to be applied from a town planning perspective.
Conclusion 57The earthworks component of the proposal before the Court is "designated development". 58The Court file, including the exhibits before me, is returned to Commissioner Hussey. 59The costs of the separate question are reserved. DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 07 November 2012
Toner Design Pty Ltd
Newcastle City Council
[1972] HCA 21
(1998) 98 LGERA 218