21 None of the defendants have any prior convictions. Accordingly, with respect to Akerman-Apache, the maximum penalty I am able to impose is $550,000. With respect to the personal defendants, the maximum penalty is $55,000.
22 Some background as to the genesis of the corporate defendant is necessary at this point. Evidence as to that is contained in the affidavits of the two personal defendants in these proceedings in their capacity as directors of Akerman-Apache. For the reasons already explained, there is no evidence from Mr Akerman, a co-defendant who, as the third director of Akerman-Apache, is being dealt with in separate proceedings on an ex parte basis in relation to his offence.
23 The background leading to the incorporation of Akerman-Apache is contained in the affidavits of Mr Walker and Mr Herbert and is in essentially similar terms. It was not disputed by the prosecution.
24 The two personal defendants in these proceedings are directors of Apache Earthworks Pty Limited (Apache). That company was set up in 2002 as a construction and cable laying company that sub-contracts to major head contractors. In early 2003, Apache was engaged as a sub-contractor for John Holland Pty Limited to undertake trenching, shaft sinking, pipe laying and construction work on a project in Melbourne. While overseeing that project, Mr Herbert was approached in relation to what ultimately became the corporate defendant in these proceedings. As he described:
[7] Sometime in early 2003, and most likely in or about April or May 2003, I was called to a meeting at the offices of the John Holland Group in Melbourne. Peter Kessler (Kessler), General Manager of John Holland Tunnelling and Underground Mining, Chris Moore (Moore) and Evan Stantanpolous, all employees of the John Holland Group, were present at this meeting. Steve Akerman (Akerman) was also present at this meeting, who was introduced to me as a contractor based in the United States of America (USA), specialising in horizontal directional drilling (HDD), and president of Akerman Construction, Inc. (Akerman Construction).
[8] I recall the effect of what Kessler said to me at the meeting as follows:
(a) Akerman is interested in tendering for a project with Sydney Water in Wollongong to do HDD.
(b) John Holland is part of the alliance known as the Priority Sewerage Program Alliance (PSPAT) which has been engaged by Sydney Water to undertake the project so we can't be involved with Akerman.
(c) We really want Akerman's expertise in HDD for the project.
(d) An Australian entity is needed to tender for the contract and as such, Akerman needs an Australian company to partner him; and
(e) We will support Akerman through out the project.
[9] Following this, Kessler said to me words to the following effect:
Would you do it? Would you partner Steve?
[10] There was no discussion about what was meant by "partnering" with Akerman or how it would operate in practice.
[11] I then said to Akerman in words to the following effect:
I only have general construction experience in trenching and surface work and I don't have any experience in drilling, particularly horizontal drilling, and I cannot do a thing because I do not know anything about it. Plus, the Melbourne Project is so high risk in terms of safety that I can't afford to spend time away from it.
[12] Akerman said words to the effect of:
I will handle the first pilot project, will fund it and do everything. You won't have to worry about it. In time I will teach you the business. If I don't make any money and the pilot project doesn't go well, I won't commit to working in Australia though. We may not work well together either. We need to test the water on these things and see how these things go. I'm also tendering for other jobs, so whether I commit to working with you guys in Australia also depends on how these other tenders go.
25 Subsequent discussions between Mr Walker and Mr Herbert as directors of Apache resulted in a decision to enter into the proposed joint venture with Mr Akerman and Akerman Construction Inc. As Mr Herbert further elaborated, he:
... thought it may be a good opportunity for Apache in the long-term, particularly if this pilot project was successful and Akerman wished to continue in Australia, and it would in any event provide me with an opportunity to gain some experience and expertise in HDD. In addition, notwithstanding my commitment to the Melbourne Project, it was feasible given the fact that Akerman would provide the required finance, skills, expertise, supervisory role, equipment, resources etc. for this pilot project.
26 Mr Herbert asserted that in his discussions with Mr Kessler, it was his understanding, if the joint venture proposal went ahead in relation to the PSPAT project, he would have no direct involvement in it as he would be tied up in the Melbourne project as sub-contractor for John Holland. That project, as he stated, was 'so high risk in terms of safety that I can't afford to spend time away from it'.
27 Notwithstanding Mr Herbert's concern for safety on the Melbourne project, he acknowledged in cross examination that he made no inquiries as to safety standards in relation to the proposed joint venture project. I will return to that issue later in this judgment.
28 As a result of the above, the joint venture company Akerman-Apache (Joint Venture) Pty Limited was incorporated on or about 7 August 2003. Mr Steve Akerman was to be an executive director and Mr Herbert and Mr Walker were non-executive directors of the company. According to Mr Herbert:
At this time, it was my understanding and intention that Lindsay and I would be non-executive directors of Akerman-Apache and would play no role in respect of the project for which Akerman was tendering. This was because Akerman was responsible for financing the project and supplying all the equipment, knowledge and labour for undertaking the works. It was also because the company was not intending to be involved in any other project at the same time.
29 Notwithstanding Mr Herbert's view that he 'would play no role' in relation to the joint venture project, he was involved in a number of respects. He assisted Mr Akerman to locate and secure the truck that was being used at the time of the accident on 3 November 2003. That truck was obtained from Mr John Carey of Carey Contracting Services Pty Limited. According to Mr Herbert, having arranged the introduction, he had no further involvement in the supply of the truck.
30 The next issue in which Mr Herbert assisted the joint venture was in relation to local labour hire. According to Mr Herbert, he requested a representative of the labour hire company Direct Skills Pty Limited to assist Mr Akerman with local drivers authorised to drive trucks in Australia as the United States employees with Mr Akerman were not authorised to do so. Again, having done that, Mr Herbert says he had no further involvement in the provision of labour for the joint venture project.
31 According to Mr Herbert, he visited the worksite on two occasions for a very limited time only. By his account, apart from a cursory view of the project site and the mud plant, Mr Herbert took no active participation or great interest in the project.
32 On one of his two visits to the project worksite, Mr Herbert viewed the mud plant. As he stated:
[57] On one of my 2 visits, Akerman showed to me the mud plant. At the time it was located in Sydney Water's yard, which was fenced around with environmental fencing. This is a plastic woven cloth that is dug into the ground and supported by metal stakes. It is a semi permanent fence and would not be taken down and put back up. It confirmed to me that the mud plant was not a moveable piece of equipment.. At this time Akerman said words to the following effect:
"The mud plant has to be located in this position for the duration of the project".
[58] At no time was I informed by Akerman or anyone else, or was I aware, of any intention to move the mud plant at all. I was also not informed about, aware of, or shown on any of my visits to the site any alterations to the truck to allow it to tow the mud plant.
33 Like Mr Herbert, Mr Walker's involvement in the joint venture was peripheral as far as work on the PSPAT project was concerned. Mr Walker was involved in assisting Mr Akerman with matters such as the initial incorporation of the joint venture company, opening the company bank accounts as well as overseeing the payment of expenses on behalf of the company. On Mr Akerman's behalf but, as I understand it, following the incorporation of the joint venture, Mr Walker signed the sub-contract with PSPAT. Exactly when this happened is not clear. As Mr Walker stated:
[25] The formal sub-contract with PSPAT is dated 31 July 2003. However, at a later date (which I now no longer recall) Akerman rang me from the USA and said to me words to the effect:
I have to sign the acceptance of the sub-contract and Sydney Water have asked if you'll sign it on my behalf because neither of us want to wait until I am back in Australia before it gets signed. It's important to me that this is done as quickly as possible, because the completion date for the contract is tight as they have recorded the start date back on 31 July 2003.
[26] I agreed to do this and I travelled to Sydney Water's offices at Helensburgh and signed the contract on Akerman's behalf as "per L Walker".
34 All three directors of the joint venture were signatories to the bank account opened and operated on behalf of the joint venture.
35 With the exception of the labour hire workers from Direct Skills, Mr Jasper and Mr Haigh, the other workers on site were American residents employed by Akerman Construction Inc.
36 According to both Mr Herbert and Mr Walker, they understood Mr Steve Akerman was generally on site managing the project on a day to day basis. While the impression certainly is to that effect, it is clear there were occasions when Mr Akerman was not there. At the time of the accident involving Mr Boyer, Mr Akerman was in the United States with Mr Burch acting as site foreman.
37 Both Mr Herbert and Mr Walker were at pains to emphasise their roles as non-executive directors of the corporate defendant and that they played very much an arms length role in the day to day operations of the corporate defendant in the PSPAT project. It is clear they were content to leave all operational matters, including safety, to Mr Akerman. In part, this would appear to be because of discussions between Mr Herbert and Mr Kessler of John Holland Pty Limited in or about April 2003 when Mr Kessler first raised the possibility of Apache Earthworks and Akerman Constructions Inc coming together in a joint venture for the PSPAT project. As one of the corporate team of companies involved in the overall PSPAT sewerage project in the Illawarra, John Holland Pty Limited seemingly had an interest in bringing the two companies together.
38 According to Mr Herbert, in encouraging Apache Earthworks to join with Mr Akerman's company in the joint venture, Mr Kessler stated that John Holland would have an engineer embedded in the overall project operations that would be able to assist Mr Akerman, as the project manager for the corporate defendant, with advice and guidance on operational matters, including safety. As Mr Herbert deposed:
[36] For the period from when the works commenced to the date of the accident, I had dealings with Kessler and Moore, from time to time. When speaking with them they informed me that they were really happy with Akerman. In addition, I received general information that Akerman was doing well in Sydney as far as the general conditions of the contract were concerned. I received this information from Moore and Kessler after they spoke to David Grist, the engineer employed by John Holland on the site. David Grist was employed and placed in the position of HDD engineer for the PSPAT. He was specifically placed there by John Holland to assist Akerman on this project.
39 No issue was taken with Mr Herbert's evidence as to the above matters.
40 Like Mr Herbert, if anything, even more so in operational terms, Mr Walker took no interest in workplace issues involving the project, including safety. On that issue, personally, he said, he did nothing. He did visit the project worksite once, as he deposed:
[39] I recall in late September or possibly early October, 2003 when I had driven Akerman to a site where the drilling rig was operating, I stopped to look at the drilling operation, as I was interested in how it worked. I recall Akerman or one of his men (I cannot now recall) saying to me words to the following effect:
"Lindsay. Don't get any closer there. You have not been inducted onto the site and you don't have a helmet, or other safety gear. I'm sorry, but that is as close as you go".
41 According to Mr Walker, he took comfort in John Holland's involvement in the project as being indicative of ensuring safe workplace standards would be observed.
42 Both men, in somewhat different terms and for somewhat different reasons, acknowledged they took no active involvement in ensuring workplace safety in the work being undertaken by the corporate defendant. It would be fair to say, between them, they relied on a combination of assurances from John Holland, Mr Akerman's role as project manager and the belief that the corporate defendant would not be awarded the project without meeting it's obligations in relation to workplace safety contained within the provisions of the sub-contract.
43 Those explanations only go so far. As directors of the corporate defendant, Mr Herbert and Mr Walker took upon themselves the non-delegable responsibility that the Act requires. It is no answer to such an obligation to simply point, for whatever reason, to an arms length director's role. I believe, in many respects, Mr Herbert and Mr Walker have acknowledged that by the entry of their respective pleas of guilty.
44 Further, I do not believe that their actions in distancing themselves from the corporate defendant's operations and attendant safety obligations was indicative of a careless disregard for workplace safety. It was primarily, I believe, more in the nature of a serious misjudgement on their part as to the legal obligations that arise for directors of a company where workplace safety is a paramount consideration.
45 On the part of the corporate defendant, I accept that there is no evidence it operated with an overall cavalier approach to workplace safety. The comments of Mr Barker, the Project Manager for the PSPAT project, in para [33] of the agreed facts attest to that.
46 As the agreed facts identify, the business of the corporate defendant in the PSPAT project was the provision of directional drilling and civil construction services.
47 As is evident, two items of plant became essential to enable the contracted services to be provided. That is, a transportable mud plant and a water truck. The transportability of the mud plant was achieved by it being permanently secured onto the trailer such that the trailer with the mud plant essentially became an integrated item of plant and equipment. Together, the trailer with the mud plant weighed 9561.82kgs. For the purposes of these proceedings, reference to the mud plant embraces the trailer and vice versa.
48 Viewed objectively, I accept that it was not readily foreseeable that the truck would be adapted and used in the manner it was and then tow the trailer in the manner and circumstances in which it did. Indeed, by themselves, the truck and the trailer would appear to have been two items of plant that were inherently safe if properly used. However, as the agreed facts detail, when coupled together in the way they were and in the manner and circumstances in which they were being utilized on 3 November 2003, the combined plant and equipment was rendered inherently unsafe and a clear and foreseeable risk to safety. The circumstances leading to the death of Mr Boyer was, on any view, clear evidence of that.
49 There seems little doubt, on the evidence before me, that it was never contemplated the mud plant be moved from it's initial location at the project base. What facts and circumstances led to the decision to move it and to do so in the way that was done is not known. As the agreed facts disclose:
[35] Barker and Steve Akerman agreed that the directional drilling equipment should not be driven on the road but rather transported by low loader and this was included in safe work method statements. Barker and Steve Akerman also drew up an environmental management plan that was prepared for the project site which showed that the mud plant would be set up on site.
50 For the workmen to do as they did on 3 November clearly flies in the face of the above agreement and safe work method statements. If anything, it highlights a serious failure in the system of work in place in that a fundamental issue going to safe work methods was able to be effectively ignored.
51 Reference to the agreed facts, in particular paras [18] to [27] inclusive, detail only too vividly the steps taken by the workmen identified to do as they did. That is, hitch the mud plant weighing 9561.82kg to the truck in an improvised fashion, fail to establish any brake connections between the truck and the trailer and then proceed to have the truck tow the mud plant down a relatively steep incline on a public road. As Inspector White responded when asked:
Q47: In your opinion was it dangerous for the truck to be pulling the trailer without brakes down Otford Road?
A47: Other than travelling at a snails pace it would have been dangerous to tow the trailer on any road without any brakes on the trailer.
52 Senior Constable Wreford ultimately expressed his opinion on the unsafe braking system in operation at the time of the accident as follows:
[5] I would like to expand on information provided ... In my (earlier) statement I said "However, due to the tare weight of the trailer being less than the tare weight of the truck, the truck is capable to tow the trailer without brakes." This should read, "However, due to the tare weight of the trailer being less than the tare weight of the truck, the truck is capable of towing the trailer, so long as the trailer has adequate size brakes".
[6] ... In my (earlier) statement I said, "Due to the amount of damage to the truck and trailer wiring I was unable to determine if the trailer brakes were operational via the truck and in my opinion the trailer brakes were inadequate in size for the weight of the trailer". The trailer brakes were an electrical type with emergency override operating drum brake on all axles. Electric trailer brakes operate as follows. The towing vehicle is fitted with a signalling device to activate the brakes on the trailer via electrical wiring. This device is usually in the cabin of the truck or plumbed in the brake pressure system. I was unable to find any device or additional wiring to activate the trailer brakes from the truck. The emergency override is a separate battery fitted to the trailer to activate the trailer brakes if the trailer becomes separated from the hauling unit. The brakes on the trailer were of a drum and shoe type fitted to all wheels. I observed the size of the brake drums and shoes to be quite small for the weight of the trailer 9561.82 kilograms gross vehicle mass (GVM). I compared the size of the brake drums and shoes to that of a small truck with a gross vehicle mass of 3000 kilograms. These brakes, in my opinion, are far too undersize for the trailer and would put extra pressure on the
hauling units (the truck) braking system.
53 Given all of the above, the risk to safety that arose when Mr Boyer drove the truck towing the mud plant down the steep incline of Otford Road without a proper braking system was self evident and the prospect of serious consequences foreseeable.
54 The Full Bench in Capral said at 650 that 'a breach where there was every prospect of serious consequences might be assessed on a different basis to a breach unlikely to have such consequences'. In isolation, the potential for 'serious consequences' is not conclusive of the nature and quality of the offence, but it is clear that such a factor may be considered when assessing the ultimate culpability of a defendant.
55 Further, as was stated in Capral, the presence of foreseeability 'will necessarily result in the offence being more serious in nature'. As such, the starting point for the determination of foreseeability within the context of the objective seriousness of an offence is whether there was 'an obvious or foreseeable risk to safety against which appropriate measures were not taken'. ( Lawrenson Diecasting at 476).
56 It is relevant to the objective seriousness of an offence to consider if there were readily and easily available remediation steps which could have been undertaken by the defendant before the accident to prevent injury occurring. To put it another way, one should have regard to remediation or the extent of remediation that is done post the accident, as an indication of the extent to which foreseeability of injury was readily identifiable.
57 As earlier stated, there is no evidence to support or explain why it was necessary to move the mud plant at all. However, if it was an imperative to move the mud plant down Otford Road, there is little doubt, if proper consideration of the braking issues relative to the weight of the truck and the trailer had been properly considered, as they should have been, and the methodology incorporated in the safe work method statements referred to in para [35] of the agreed facts observed, the events leading to the death of Mr Boyer would simply not have transpired.
58 In all the circumstances, I consider the offence a serious one and I will approach the determination of penalty on that basis.
59 In determining penalty in relation to each of the defendants as co-offenders, the principle of parity is relevant. The principle demands consistency in sentencing outcomes as between co-offenders determined by having regard to the circumstances of the co-offenders and their respective degrees of culpability: see Lowe v R (1984) 154 CLR 606 and Postiglione v R (1997) 189 CLR 295. However, 'if there are relevant differences, due allowance should be made for them': Postiglione v R at 301.
60 It is necessary at this point to consider parity in relation to the relative culpability as between the two personal defendants and as between the two personal defendants and Mr Akerman.
61 It is apparent Mr Herbert and Mr Walker, as non-executive directors of the corporate defendant, took something of a back seat role in the day to day operations of the work being performed by the company under the PSPAT contract. Accepting the evidence of Mr Herbert and Mr Walker on this point, Mr Steve Akerman was the driving force and project manager responsible for getting the work done safely, on budget and on time. He was a visible and hands on presence at the workplace notwithstanding he was not there when the accident with the truck and the mud plant occurred. Whether Mr Akerman would have sanctioned what was done and the manner in which it was done is simply not known. The evidence that there is suggests that Mr Akerman was very aware of workplace safety and, as a general assessment, ensured the observance of safe workplace standards in the work being undertaken.
62 On this point, the view of Mr Barker, project manager for the PSPAT project as referred to in the agreed facts, warrants repeating as follows:
[33] Steven Barker (Barker), Projects Manager employed by Sydney Water and PSPAT, was responsible for the overall project. In an interview with WorkCover following the accident he said that he observed that there were very few problems with the first defendant's safety performance. Its quality systems were working and it worked very well within the environmental management plan.
[34] It was Barker's responsibility to ensure the plant that sub-contractors used on the project was safe to use up to and on 3 November 2003.
[35] Barker and Steve Akerman agreed that the directional drilling equipment should not be driven on the road but rather transported by low loader and this was included in safe work method statements. Barker and Steve Akerman also drew up an environmental management plan that was prepared for the project site which showed that the mud plant would be set up on site.
[36] Barker and Steve Akerman agreed that the mud plant would remain at the Helensburgh Depot because of the danger of floods.
63 I accept that, relative to Mr Akerman, the culpability of Mr Walker and Mr Herbert is less. They were obviously content to allow Mr Akerman to do all the running on the project, acknowledging that the quid pro quo for them was, as directors of Apache Earthworks, they stood to gain if the joint venture project, under Mr Akerman's direction, was a success. Having said that, Mr Herbert and Mr Walker cannot avoid their responsibilities and ultimate culpability, which their plea of guilty acknowledges, simply because of their more arms length role vis-a-vis Mr Akerman.
64 I discern no distinction in the relative culpability as between Mr Herbert and Mr Walker.
65 The decision of the Full Bench in Capral clearly indicates that general and specific deterrence are factors that should be given weight in all but exceptional circumstances. The Full Bench said at 643-644 that:
We consider that the extract from the judgment of Hungerford J in Fisher v Samaras Industries Pty Limited accurately states the approach that members of this Court should take in relation to the question of deterrence, both general and personal or specific, when sentencing an offender in relation to a serious breach of the legislation. It follows that those aspects of deterrence are matters which should normally be given weight of some substance in the sentencing process.
66 In respect of specific deterrence, the Full Bench held in Capral at 644-645:
In sentencing, a court may disregard the element of specific deterrence if satisfied that the risk of re-offending is low or non-existent. The court may form such a view as a result of the rehabilitation of the offender: R v Corner (unreported, Court of Criminal Appeal, 19 December 1997) or because the offender will not have the opportunity to commit a similar offence in the future: R v Macdonell (unreported, Court of Criminal Appeal, 8 December 1995). However, we think it unlikely that the weight to be attached to specific deterrence could be reduced to zero in cases of offences under the Act.
67 I consider general deterrence to be relevant to all three defendants. Specific deterrence brings with it somewhat different considerations. The joint venture company is no longer operating. According to both Mr Walker and Mr Herbert, Mr Akerman advised, in or about mid 2005, that he no longer wished to operate in Australia. The fact that Mr Akerman has made no appearance in his own proceedings and is currently residing in America would support that assertion. Counsel for the prosecutor contended that specific deterrence was a relevant consideration in relation to the corporate defendant in that, while currently dormant, it was still registered and could commence to operate again in the construction industry.
68 I accept I cannot be confident the corporate defendant will never operate again but I consider, in all the circumstances, it is most unlikely. In my view, specific deterrence is of minimal weight in my considerations in relation to Akerman Apache.
69 The situation in relation to Mr Herbert and Mr Walker is somewhat different. Both remain as directors of Apache Earthworks and Apache Assets Pty Limited (Apache Assets). Both companies, as became apparent in the course of these proceedings, continue to be engaged in diverse projects in the construction industry - an industry that is replete with risks to safety. Admittedly, those companies are not a defendant in these proceedings. Nevertheless, both Mr Walker and Mr Herbert in particular continue to have a hands on role in the business activities of their companies in construction industry projects. By all accounts, Apache Earthworks in particular has a sound and proactive approach to workplace safety largely through the observance of safe workplace standards overseen by Mr Herbert who remains actively involved in the projects undertaken by Apache. I consider specific deterrence to be a relevant factor in relation to Mr Walker and Mr Herbert tempered by the above considerations.
70 As well, I have noted the steps taken by Mr Herbert immediately following the accident involving Mr Boyer to put processes in place designed to ensure the corporate defendant addressed the safety concerns that the accident on 3 November 2003 highlighted. As he deposed:
[71] When I returned to Sydney after the funeral, I gathered all the safety documents which had been stored in the back of the container at the site. These documents included the following:
(a) Attached and marked with the letters JDH1 are copies of job safety analysis sheets which were completed by Akerman and his men prior to the incident; and
(b) Attached and marked JDH2 are copies of equipment check lists. These were completed by Paul Jasper and Boyer.
[72] Following my return to Sydney I implemented the following:
(a) In or around December 2003, I arranged for new hazard risk assessment forms to be completed. These had already been submitted by Akerman but Sydney Water wanted them to be reviewed and changed. I do not have copies of the hazard risk assessments because they were provided to Sydney Water.
(b) In or around late November I hired an engineer to assist me in implementing and redesigning the safety system. Attached and marked with the letters JDH3 are copies of the original Safety Management Plan, together with the revised plan.
71 It was contended that the corporate defendant's asset base and ongoing financial viability is nominal and demonstrates an incapacity to pay any significant penalty. On that issue, s 6 of the Fines Act 1996 provides as follows:
In the exercise by a court of a discretion to fix the amount of any fine, the court is required to consider:
(a) such information regarding the means of the accused as is reasonably and practicably available to the Court for consideration, and