Other delay costs of at least $70,278
34 As the label suggests, the third component is for other costs allegedly caused by Ultradrilling's delays in the Project.
35 This component was rejected by the Deputy Registrar on the grounds that there "[was] simply no evidence (credible or otherwise) before the [C]ourt to explain how this offsetting claim [was] said to arise". As a result, on review West filed additional affidavit material (as it was entitled to do) from Mr West seeking to rectify that problem. That evidence was described as disclosing "the actual costs associated with the delay caused by [Ultradrilling] and not otherwise covered by the claims permitted by the Deputy District Registrar". Those actual costs, which at $101,458.70 exceeded the previous, estimated figure of $70,278, were itemised as follows:
Calculation of Actual Costs
Incurred and associated with the 27 days lost
5.4 weeks
Payroll
Engineer 1 7,470.00
Engineer 2 5,659.00
Engineer 3 6,800.00
allowance paid to engineers 1,620.00
Accommodation 4,750.00
Transport 2,350.00
Compressor 4,000.00
Lost mark up
on engineer's costs at 30% 9,794.00
Lost profit on 29 pumps usually
rented at $110 per day and left
idle for 37 days allowing for
costs estimated at 50% 59,015.00
TOTAL 101,458.70
36 The additional affidavit from Mr West went on to describe these claims in the following terms:
In that period [of 27 days] [West] was required to retain 3 engineers, with accommodation and transport and pay them a per day sustenance allowance. The period also required the retention of a compressor. In that period the engineers and the pumps could have been employed on other projects. If so employed [West] would have recovered approximately a further 30% on the costs as a profit. During the delay some 29 pumps were idle. If the pumps were used elsewhere they would usually be rented out at $110 per day (each day not just working days). If rented out, [West] would incur costs of about 50% of the rent recovered.
37 Ultradrilling submitted that the fact that West now puts forward these details of the offsetting claim to overcome the difficulties identified by the Deputy Registrar should tell strongly against the genuineness of the claim, both on the issue of whether the delays are recoverable by West against Ultradrilling and the amount of any such claim. In any event, Ultradrilling contends that the evidence now provided does not rise above mere assertion and should be rejected on that basis alone: see Elm Financial Services Pty Ltd v MacDougal [2004] NSWSC 560 at [18]-[19] and TR Administration 66 ACSR at 79-80. Ultradrilling focused, in particular, on the charges for "lost mark up" and the "lost profit" on the pumps (see [35] above). Ultradrilling contended that if, as was required, a line was drawn to distinguish between evidence that was merely spurious, bluster or assertion and evidence which provided sufficient factual particularity to exclude the merely fanciful or futile, the offsetting claim would be dismissed: TR Administration at 79-80.
38 I reject this submission. What this application has demonstrated is that the terms on which West engaged Ultradrilling to drill bore holes and the manner in which Ultradrilling completed that work is the subject of dispute. Those issues cannot be resolved and should not be resolved in the present application. Moreover, it must be recalled that West is not required to establish the precise dollars and cents or provide a fully evidenced claim: Elm Financial Services at [19].
39 Secondly, the bases on which Ultradrilling contends that charges for "lost mark up" and the "lost profit" on the pumps are spurious cannot be accepted. "Lost mark up" was criticised by Ultradrilling on the grounds that "[t]he sense in which this amount was 'lost' [was] unexplained." However, that loss was explained. In Mr West's additional affidavit and accompanying spreadsheet (see [35]-[36] above), it was described as the margin which West would have received on the engineer's labour - that is, the difference between the rate charged to the client and the rate actually paid to the engineer. Whether such loss is recoverable from Ultradrilling and if so, whether 30% is the correct rate to apply in calculating the loss, are issues to be determined in other forums. The other loss, the "lost profit" component, was challenged by Ultradrilling on the basis that because the pumps were said to be custom-built for the Project, there could be no "usual practice" for renting the pumps and it was not plausible to assume that each of the pumps, if not required on the Project, would have been immediately rented out for the whole period to a third party at $110 per day. Again, those are issues that will need to be resolved in another forum.
40 In the present case, it cannot be said that the evidence was merely spurious, bluster or assertion. The evidence ultimately provided by West provided sufficient factual particularity to exclude the merely fanciful or futile. Whether West will succeed at any trial of the issue is irrelevant.