The Craftsmen Restoration & Renovations v Thomas Boland, Thomas Boland v The Craftsmen Restoration & Renovations
[2008] NSWSC 660
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2008-07-01
Before
Howie J
Source
Original judgment source is linked above.
Judgment (129 paragraphs)
Introduction 1 HIS HONOUR: On 5 September 2001 the parties entered into a building contract for alterations to domestic premises in Riverview. The plaintiff was the builder and the first and second defendants were the owners of the premises. Problems arose between the parties in June 2002 and on 5 August 2003 the owners purported to terminate the contract on the basis of default by the builder in the manner in which the work was carried out. On 6 August 2003 the owners commenced proceedings in the District Court. On 12 August 2003 the builder commenced proceedings before the Consumer, Trader and Tenancy Tribunal ("the Tribunal"), the third defendant. 2 Eventually the two matters came on for hearing before Senior Member Paull. The parties were represented by counsel, Senior Counsel in the case of the owners. There was a conclave of expert witnesses, eight hearing days from 22 August 2005 through to March 2006 and submissions ran over four days from May to June 2006. The Tribunal delivered its decision on 28 August 2006. The judgment of the Senior Member runs for 93 pages. The judgment was substantially in favour of the owners. 3 Almost immediately the builder commenced proceedings by summons in this Court seeking declaratory relief as to the rights of the parties and orders in effect overturning the Tribunal's findings and replacing them with those in favour of the builder. The owners in effect cross-claimed by a summons seeking to quash some of the orders made by the Tribunal on the basis of errors of law. 4 Consistent with the manner in which the dispute has so far proceeded, there has been voluminous material placed before this Court. The matter was listed for hearing with a two-day estimate although I had only one day then available. However, during the hearing it became obvious that the matter could not be completed largely because of the tender by the builder of a 46-page document setting out the alleged errors made by the Tribunal, relevant sections of the transcript, and submissions by the builder. It was referred to as an "aide memoir". The owners' legal representatives had not previously seen the document and they wished to have time to consider it. It should be noted that in April 2008 the owners responded to this document with a critical analysis of it extending over 48 pages. 5 The matter was stood over to the last two days of the 2007 term and further submissions were filed. At the completion of the hearing the parties sought to make further submissions in writing. Written submissions on behalf of the owners were not filed until April 2008. The builder raised certain objections to these submissions and there has been further correspondence between the solicitors for the parties and the Court. The incessant bickering between the parties and their legal representatives has continued even after this Court reserved its decision. 6 It is appropriate here to note that the matter was not conducted in a way that was appropriate for the resolution of a dispute before the Tribunal. One of the objects of the Consumer, Trader and Tenancy Tribunal Act 2001 (the Act) in establishing the Tribunal is: