emmett J:
1 This appeal is concerned with a breach of an agreement made on 17 December 1999 (the Fishing Agreement). The primary judge found a breach of the Fishing Agreement but concluded that no loss was caused by the breach. His Honour also rejected claims of misleading and deceptive conduct concerning the conduct of one of the parties.
2 The parties to the Fishing Agreement were the first respondent, Cossack Pearls Pty Limited (Cossack), Pearl Coast Divers Pty Limited (the Contractor) and Colin and Leanne Sharp. Mr Sharp is the appellant both in his own right and as trustee of the Sharp Family Trust.
3 The proceeding at first instance was commenced by the Contractor and Liquid Investments (WA) Pty Limited (Liquid) against Cossack, Dampier Pearling Company Limited (Dampier), Mr Lindsay Brady and Mr Paul Thomas. The Contractor made claims of breach of the Fishing Agreement and Liquid made claims of misleading and deceptive conduct. The Contractor also made claims of misleading and deceptive conduct.
4 Both the Contractor and Liquid are in liquidation. On 19 June 2008, orders were made by a judge of the Court that Mr Sharp be substituted as an applicant in place of the Contractor and that Mr Sharp as trustee of the Sharp Family Trust be substituted as an applicant in place of Liquid.
5 The other respondents to the appeal are Dampier and Messrs Brady and Thomas. All were found to have no liability to Mr Sharp, either in relation to the causes of action prosecuted on behalf of the Contractor or in relation to the causes of action prosecuted on behalf of Liquid.
6 Under clause 2.1 of the Fishing Agreement, Cossack promised, by 31 December in each year of the Term, to complete and lodge with the WA Fisheries Department:
an annual notice of intent to transfer the Quota to the Contractor;
Notice of Pearling or Hatchery Activity Form; and
any other forms, applications or documents reasonably required by the Fisheries Department or any other authority;
to transfer the Tags for the Quota to the Contractor.
7 Under clause 2.2, Cossack promised to use its reasonable endeavours to obtain any approvals required pursuant to clause 2.1.
8 Clause 3 of the Fishing Agreement provided that, during the Term, the Contractor must:
catch the Quota during the Shell Season; and
catch not less than 5,000 shell in each month during the Term.
9 The Term is the period of 5 years commencing on 1 January 2000. The Shell Season is the period from 1 January to 31 July in each year of the Term. Tags are tags for Shell issued by the WA Fisheries Department. Shell means live pearl oyster shells. Quota means the quota of 25,000 Shell allocated to Cossack under its pearling licence, and the quota of 7,500 Shell which Cossack is entitled to catch pursuant to an agreement to catch Shell under a pearling licence granted to Dampier.
10 Clause 4.1 provided that if in any month during the Shell Season the Contractor fails to catch and deliver at least 5,000 shell, Cossack may itself, or may employ another contractor to, fish and catch that part of the Quota for the relevant month. Under clause 4.2, if the Contractor fails to catch and deliver to Cossack at least 80 per cent of the Quota by 30 June in any year of the Term then Cossack may terminate the agreement.
11 By clause 20, the Contractor irrevocably appointed Cossack to be the attorney of the Contractor on expiration or earlier termination of the Fishing Agreement to complete and lodge with the WA Fisheries Department:
a Notice of Intent to transfer the Quota back to Cossack;
Notice of Pearling or Hatchery Activity Form to transfer the Tags for the Quota to Cossack; and
any other consents or documents to enable Cossack to exercise its rights under clause 20.
12 Under clause 35, each party agreed to execute and do all acts and things necessary or desirable to implement and give full effect to the provisions and purpose of the Fishing Agreement.
13 The Contractor fished under the Fishing Agreement during the 2000 season and harvested all of the Quota during that season. Towards the end of 2000, Mr Sharp and Mr Brady met to discuss operations during the 2001 season. Mr Brady provided Mr Sharp with 1,250 Tags, being sufficient Tags to cover 10,000 Shell, which was the minimum catch for 2 months.
14 The Contractor commenced fishing operations in January 2001, but those operations were impeded by a series of cyclones. As a result, the Contractor had not harvested 10,000 Shell by the end of March 2001 and the Contractor had not satisfied the requirement of clause 3(b) that he catch not less than 5,000 Shell in each month. By the end of March 2001, there was a cumulative shortfall of 6,783 Shell. During April, the Contractor harvested 4,996 Shell, four below the minimum, giving a cumulative shortfall of 6,787.
15 In the meantime, however, Cossack had reallocated the balance of the Tags for the 2001 season to another contractor. As at the end of May, the Contractor had received 2,812 Tags, covering 22,496 Shell. The remaining 1,250 Tags had been given to the other contractor.
16 On 18 June 2001, the Contractor ran out of Tags to cover that part of the Quota that had been allocated to him under the Fishing Agreement. He then arranged to obtain Tags from another allocation that enabled him to catch a further 7,500 Shell.
17 Mr Sharp accepted that at no point up until the end of May did the lack of Tags have anything to do with his not making up his Quota. He accepted that there was a shortfall on what he had caught of 7,295. Mr Sharp also accepted that, when he had 7,500 Tags on his boat from another source for the period from 18 June 2001 through to 30 June 2001, he in fact only caught 1,763 Shell.
18 Cossack contends that, even thought there may have been a breach of contract by reason of the failure to supply further Tags, that failure had no causal connection with the failure to achieve the 80 per cent of the Quota by 30 June 2001. That is to say, the Contractor caught all of the Shell that it could catch, and lack of Tags was not an impediment. Even with the additional 7,500, the Contractor still did not achieve 80 per cent of the Quota by 30 June 2001. Hence, while there was a breach of contract, there were no damages suffered by reason of the breach. Further, there was no causal connection between that breach and the failure to achieve 80 per cent of the Quota.
19 However, in the statement of claim, Mr Sharp asserts that, by reason of the breach of the Fishing Agreement occasioned by Cossack's refusal to provide the Contractor with the balance of the Tags on 5 June 2001, the Contractor lost the profit on the income that would have been generated from catching the balance of the Quota during 2001. The Shell Season finished on 31 July 2001. Mr Sharp asserts that, had he been provided with Tags in accordance with the Fishing Agreement, he would have been able to catch sufficient Shell between 5 June 2001 and 31 July 2001 to make up the quota.
20 While the failure to deliver Tags did not prevent the Contractor from achieving 80 per cent of the quota by 30 June 2001, there is a further question as to whether, had the Contractor received the Tags to which it was entitled, it might have caught Shell from 30 June to 31 July 2001. The Contractor caught 1,763 Shell in the period 18 June 2001 to 30 June 2001, after obtaining Tags for 7500 Shell. In those circumstances, it seems highly doubtful that, even after receiving further Tags, he would have caught more than he actually caught. That is to say, whether with Tags provided by Cossack or Tags obtained from another source, he did not lose the opportunity of deriving profit from whatever Shell he was able to catch before the end of the 2001 Shell Season. Because he had obtained Tags form an alternative source, he effectively suffered no loss.
21 I have read in draft form the joint reasons of Bennett and McKerracher JJ for concluding that the appeal should be dismissed with costs. I agree that the appeal should be dismissed for the reasons proposed by Bennett and McKerracher JJ.
I certify that the preceding twenty-one (21) numbered paragraphs are a true copy of the Reasons for Judgment herein of the Honourable Justice Emmett.