Can the builder claim an amount greater than the disputed amount?
- As noted above the cost of the works is an unknown amount but made up of the amounts set out in clause 15.2 and schedule 2. The obligation on the owner is to pay the price of the building works under the contract in the manner and at the times stated in the contract; see clause 3.1. The manner of the payment is governed by clause 15. That clause requires the builder to give the owner a written claim for a progress payment at each stage described in schedule three. That occurred in respect of progress claim eight.
- Where the parties are in dispute as to a payment claim they can either choose to keep the contract on foot and engage in whatever form of dispute resolution including litigation as they may determine. The contract has a dispute resolution clause but no party makes any reference to this in these proceedings. That clause, clause 31 makes no provision for what is to occur if the parties do not resolve their dispute. My view is that the parties are then at liberty to bring such proceedings as they consider appropriate. The matter in dispute in those proceedings is the quantum of the disputed claim.
- There does not appear to me to be any principled reason why the ultimate figure found to be payable under the progress claim can be no more than what was stated in the progress claim provided that the higher amount is made known to the owner and the owner is given every opportunity to challenge that amount. There is no express term of the contract excluding this approach. The argument of the builder to the effect that clause 15 provides a trigger mechanism for the liability to pay for the next stage seems logical. Ordinarily in a non contentious contract that claim would inform the owner of what the obligation is as at that stage under the cost plus contract. Work would then continue on and a further claim made in due course. Or if it was the final claim then an amended claim could be made certainly prior to payment. If payment was made other issues may arise such as accord and satisfaction but that is not the case here.
- This approach allows the entitlements of both parties to be arrived at without artificial restraint and I prefer it to the defendant's approach. This conclusion is consistent with the view of McDougal J in Creative Building Services v Jolene Investments Pty Ltd [2013] NSWSC 391 at [31]. Notably what was considered there, as here, was a final claim.
- The argument is however somewhat moot, for even if the above conclusion is incorrect there is no dispute that all of the same work is open to be claimed by way of quantum meruit. I might add in that regard the fact that the builder makes the concession that more than $21,000 can be claimed by way of a quantum meruit, and noting also the reference by both parties to Mann v Paterson Constructions Pty Ltd [2019] HCA 32, shows that it is in the contemplation of the parties that the contract is for a cost amount such that more than $21,000 can be claimed by progress claimant 8. This is because the point of Mann, which was a case of a fixed price contract, was to limit the restitutionary claim to be within the bounds of the expectations of the contract. The concession that the quantum meruit can be more than $21,000 is a concession that the contemplation of the contract or the effect of its terms was that more than the approximate $600,000 in total could be the cost of the building works.