NSWNSWDC
David Kenneth Costin trading as DC Build Construct v Catherine Maree Parer in her capacity as administrator of the deceased estate of Christopher Charles Musgrave No.1
[2021] NSWDC 564
District Court of NSW|2021-09-13
View original sourceAt a glance
Source factsCourt
District Court of NSW
Decision date
2021-09-13
Source
Original judgment source is linked above.
Judgment (9 paragraphs)
[1]
Introduction
- The plaintiff in this matter is a builder ("the builder"). By a contract in writing dated 24 September 2018 ("the contract") he agreed to build a new three bedroom two story dwelling on land at Angourie, New South Wales for the owner of that land Mr Chris Musgrave ("the owner"). The statement of claim seeks payment of the sum of $301,578.92 as a debt due under the contract and makes alternative claims for damages for breach of the contract or alternatively by way of a quantum meruit and quantum valebat. The defendant denies the claim and in her defence asserts that the final progress payment which is what is in dispute and which is progress claim 8 is determined by the contract to be the sum of $21,199.43. The defence alleges numerous breaches of the contract by the builder and asserts that by reason of the alleged breaches of contract the contract including any variations is unenforceable by reason of section 10(1) of the Home Building Act. Section 10 provides that a person who contracts to do residential building work in contravention of section 4 (unlicensed contracting) or under a contract which does not comply with section 7 (in short that it be in writing) or in contravention of any other provision of the Act or the regulations prescribed for the purposes of section 10 (and there are are no such provisions specified in the regulations or elsewhere in the Act so far as the Court was informed) is unenforceable. Putting aside the issue as to variations, none of the matters asserted in the defence as being breaches appear to fall within section 10. There is no claim, again putting aside the issue of variations for the present, for anything to be set off against the builder's claim.
- The issues raised by the pleadings and also by the parties outlines of submissions provided before the case began will be referred to below. Although it is not immediately obvious from the defence the issue in this case fundamentally is whether a proper interpretation of the contract is that it is a fixed price contract or a cost plus contract. That in itself is an odd position given that the defendant pleads that it is a cost plus contract. Ultimately that point, whilst still pressed, was seen by the defendant to be overshadowed by a quantum meruit claim which the owner conceded would succeed, with the difference in the parties positions being the amount. The owner argues that claim should be assessed at some $190,000.