RPR Maintenance Pty Ltd v Marmax Investments Pty Ltd
[2014] FCA 514
At a glance
Source factsCourt
Federal Court of Australia
Decision date
2014-05-22
Before
Griffiths J
Catchwords
- RELIEF - whether damages should be grossed up for tax - assessing quantum of damages
Source
Original judgment source is linked above.
Catchwords
Judgment (13 paragraphs)
REASONS FOR JUDGMENT 1 Judgment in the substantive proceedings was delivered on 29 April 2014 (see RPR Maintenance Pty Ltd v Marmax Investments Pty Ltd [2014] FCA 409). The parties were provided with an opportunity to seek to agree final orders which gave effect to the reasons for judgment. They have been unable to reach full agreement and each has filed and served a brief outline of submissions in support of their respective proposed final orders. The parties do not oppose the matter being disposed of on the papers and without a further oral hearing. 2 I will deal with each of the matters which are in dispute and express my view on them, before indicating the proposed final orders. I will use the same abbreviations as in the primary judgment.
(a) Quantum of damages and interest payable by Marmax for breach of contract 3 Marmax disputes that it should be ordered to pay $9,423 (as at 13 May 2014) to which a further $1.08 per day should be added until the date of the final orders. It contends that the correct figure should be calculated by reference to five jobs only and not include an additional job which RPR says should be included (namely the Bultitude job, as to which see [267] and [270] of the primary judgment). Marmax says that while the lead sheet for the job is dated 29 August 2008 (and therefore within the term of the sub-franchise agreement), the job was not actually done until 12 October 2008, when the sub-franchise agreement had terminated. 4 It is clear from [270] of the primary judgment that there was a finding that the Bultitude job involved a breach of RPR's exclusivity. Accordingly, it should be included in the calculation of the quantum of damages payable by Marmax. In my view, the source of the contractual relationship between the parties relating to that job is not the lead sheet but is a document entitled "variation to contract", which is also dated 29 August 2008. The contract was entered into before the termination of the sub-franchise agreement and, in my view, it is not to the point that the job itself was not carried out until October 2008.