Industry Standards and Practices
81Mr Cavanagh appeared to suggest that the expert evidence was to the effect that the construction of the hop-up complied with the applicable industry standards. If that was what Mr Cavanagh intended to convey, the evidence does not establish that proposition.
82Two experts gave evidence. Mr Cowling, a civil and construction engineer, was called by Mr Abrahim and prepared several reports. Mr Costin was called by Erect Safe. Curiously enough, Mr Costin's qualifications are not recorded in the Appeal Books as his report was not tendered and he was not asked about his qualifications when he gave oral evidence. However, it appears to have been common ground that Mr Costin had relevant expertise.
83The two experts prepared a joint report and gave concurrent evidence. Both expressed the view that the hop-up as constructed and with tie-wire and planks in place was not unsafe and was capable of bearing the loads to which it was likely to be subjected. But they expressed different opinions as to whether the hop-up, as constructed, complied with applicable standards.
84The experts identified the relevant standards, but we were not taken to the standards themselves and they do not appear to have been admitted into evidence. In any event, the experts agreed that the standards were "not prescriptive". Mr Cowling said that the standards required scaffolding to be fit for its purpose and, in his opinion, the scaffolding (by which he meant the hop-up as constructed) was not "fit for purpose". Mr Costin contented himself with the observation that:
there was nothing definitive within the Standards to say that the scaffolding did not comply.
85Nor does the evidence support the proposition that the hop-ups were assembled in conformity with a uniform industry practice. The experts were asked whether the method of construction of the hop-up was consistent with industry practice as at 2 April 2007. The answer was that neither could say what industry practice was at the time. Mr Costin expanded upon this answer in his oral evidence, indicating that in his experience the usual method of securing hop-ups was to use a tie-bar (a metal bar running alongside a plank, between the bracket and the transom). He had rarely seen a hop-up secured just by tie-wire.
86When giving oral evidence, Mr Costin conceded that it would be sensible, when assembling a three-board hop-up, to tie not only Plank 3, but also Plank 2:
DOOLEY: Do you not think that it would have been appropriate to put two ties around the second plank at either end, the transom end, and the hop-up end, as well as for instance two ties around the third plank at both the hop-up end and the transom end?
WITNESS COSTIN: At what point in time?
DOOLEY: At the beginning when it is first set in place?
WINESS COSTIN: I believe that the one tie at the end of each of the third plank, held the three planks adequately and this was confirmed to me when we did the set up at Erect Safe's building.
HIS HONOUR: It would hold it adequately, if it were there?
WITNESS COSTIN: That's correct.
HIS HONOUR: But you have heard that tradesmen - and I don't suppose it is a surprise to you - tradesmen do remove brackets when it's convenient to do so?
WITNESS COSTIN: Mmm.
HIS HONOUR: And they've done it a number of times, is that right?
WITNESS COSTIN: Yes.
HIS HONOUR: And also I think it's fair to assume that indeed on this particular case it was a tradesman who removed this, one would think, rather than a scaffolder?
WITNESS COSTIN: Yes.
HIS HONOUR: And so that when it is removed of course it's not safe. I think that's a given?
WITNESS COSTIN: Yes.
HIS HONOUR: We're agreed. And therefore, would it not be common sense to say this: Tradesmen remove these boards from time to time. It is unpredictable. We can't be there all the time. We don't have a camera on the board. Hopefully we would see it when we go and do our inspections, but of course it might be done just after we inspect and then we wouldn't notice it until we next inspect it. That kind of reasoning, do you agree, is common sense?
WITNESS COSTIN: I agree, yes.
HIS HONOUR: Therefore you would ask yourself: Well, if the hop-up - because a hop-up has two issues: One, it is on the hop-up that the board is most likely to be removed, because it's the hop-up which is against the building where all this other work is taking place, agree?
WITINESS COSTIN: I agree.
HIS HONOUR: And therefore, thinking about that problem, there are two ways: First of all, you issue horrific warnings that you know, "You'll get various parts of your anatomy cut off if we catch you removing bits of planking", that's one way in which you do it. You warn the workers "You are just not to do it". That appears to be part of the solution in this case. You don't have to worry about that, but I'm letting you know, you probably heard the evidence, workers were warned not to tamper. However, as one expects, tampering nevertheless occurred. The next thing that you might do is, if they tamper, they are most likely only to tamper [with] the board that is next to the building because they're getting rid of it in order to do their work. And therefore, if we fix the second plank, we at least know that the whole thing is not going to come apart?
WITNESS COSTIN: I agree.
HIS HONOUR: That strikes me as easy to do and a sensible response to the problem?
WITNESS COSTIN: I agree. (Emphasis added.)
Mr Cowling agreed with Mr Costin's responses.
87Mr Costin's evidence does not support the proposition that three-board hop-ups which use tie-wire as the safety mechanism are invariably assembled or re-assembled with only Plank 3 secured to the bracket and transom.
88Mr Hassian's evidence also does not support that proposition. Mr Hassian said that he was aware that renderers sometimes needed to remove one (not two) of the planks on a three-board hop-up, in order to gain access to the wall adjacent to Plank 3. When that occurred, it was Plank 3 that was removed. Mr Hassian agreed that if the wire attached to Plank 3 was removed, the other two planks became dangerous because "that one [which] is tied [is] keeping it all together, secure". He then explained the practice he adopted when he was asked, as he was from time to time, to remove Plank 3 to facilitate the work of renderers or painters:
Q. But where you've got a situation where, for example, the renderer needs to have one board removed to do the particular wall - A. Yes.
Q. - and of course when the renderer's finished, the painter's going to come and do the painting?A. Yes.
Q. So the board will need to be replaced?A. Yes.
Q. So you take the board off for the renderer?A. Yes.
Q. And if you were going to take that board off safely, wouldn't it mean you would have to tie - A. You have to tie -
Q. - the second board down?A. Yes.
Q. Because otherwise it would be unsafe to work on for the renderer?A. Yes.
Q. And when you put the board back when the renderer was finished his job, which you would normally do, yes - A. Yes.
Q. - would you untie where you had previously tied the second board and then retie the first, or would you retie the replacement board - or would you simply retie the replacement board?A. Well, if you're going to take one board off just for the renderer--
Q. Yes.A. - you've tied the second board.
Q. Of course.A. Yes, and removed -
Q. Now, when you put the board back though, because the painter's got to come?A. Yes.
Q. Wouldn't you put the board back?A. You put the board back and you still tie it.
Q. Yes, you would then tie that board?A. The last one, yes. You retie the last one, but you won't undo the second board.
Q. You would leave it as it was?A. Yeah.
Q. Is that right?A. Yeah, no need to undo it or anything like that.
89It is clear from this evidence that whenever Erect Safe removed Plank 3 from a hop-up to facilitate access by renderers or other tradespeople to the adjacent wall, and subsequently replaced Plank 3, the hop-up was secured by tie-wires attached to both Planks 2 and 3. Thus, although Mr Hassian indicated that Erect Safe always initially assembled its hop-ups with only Plank 3 secured by tie-wires, in practice some of Erect Safe's hop-ups had both Planks 2 and 3 secured by tie-wires.
90The evidence falls well short of establishing that Erect Safe's method of securing hop-ups on site conformed with a uniform industry practice. Many, if not most hop-ups are not secured by tie-wire, but by tie-bars. Erect Safe's own practice was to have two tie-wires in place (for Planks 2 and 3) when it was required to remove and replace Plank 3. Conformity with industry practice is a guide, not the determinant of whether a defendant has acted with reasonable care: Mercer v Commissioner for Road Transport (1937) 56 CLR 580, at 589, per Latham CJ; 593, per Rich, Evatt and McTiernan JJ; Dovuro Pty Ltd v Wilkins [2003] HCA 51; 215 CLR 317, at [34], per McHugh J; Cregan Hotel Management Pty Ltd v Hadaway [2011] NSWCA 338, at [70], per Giles JA (with whom Allsop P agreed) (a case under the CL Act). But no such conformity has been demonstrated in this case.