Chronology
27 This folly of the State, according to NAC, is best demonstrated by the following chronology of the relevant events:
(1) 24 April 2012 - The State issues Notices of Intention to Take (NOITTs) under the Land Administration Act 1997 (WA) (the LAA).
(2) April 2012 - The State serves on NAC a notice under s 24MD(6B) of the NTA.
(3) 2 July 2012 - NAC objects to the notices and NOITTs issued under the NTA and the LAA.
(4) 24 September 2012 - The State issues replacement NOITTs under the LAA.
(5) 9 November 2012 - NAC objects to the second set of NOITTs.
(6) 12 December 2012 - Letter from the State, via the State Solicitor's Office (the SSO), to the NAC, that attempts to create an assumption of a request for the referral of the objection by NAC to the IP.
(7) 25 January 2013 - Letter from NAC to the SSO. In para [2] the letter affirms NAC does not withdraw its objection, nor request that it be referred to the IP for hearing. NAC reiterates that as stated in 2011, the State (presently and of its own volition) has no right to refer the objection to the IP.
(8) 4 February 2013 - Letter from the SSO to NAC's lawyers, Land Equity Legal (LEL) - The State notes that NAC does not withdraw its objection nor request referral. The State expresses that its position is that it may now proceed to issue taking orders. However, "as a matter of good practice it will ensure the objections are heard by an independent person in accordance with s 24MD(6B)(f) of the NTA". The letter says that although NAC is invited to participate in the hearing before the IP, even if it does not, the State will ask the IP to consider the objection and make a decision.
(9) 4 February 2013 - Letter from the SSO to the IP - asserts that the objection is referred under s 24MD(6B)(f) of the NTA and says that it is the State's view that it may proceed to do the future act, but that as a matter of "good practice", it would ensure the objection was heard by the IP in accordance with s 24MD(6B)(f) of the NTA.
(10) 7 February 2013 - Letter from LEL to the SSO - Refutes jurisdiction to refer to the IP.
(11) 22 February 2013 - "Directions hearing" before the IP. Counsel for the State in the independent person proceedings submits it is a referral under s 24MD(6B) of the NTA. Counsel for NAC submits there is no jurisdiction on the basis of a lack of request for a referral by NAC, but notes that from prior decisions the IP will not consider objections to jurisdiction. The IP is informed that NAC's counsel is to consider whether Federal Court proceedings should be commenced including advising on a "lurking constitutional issue", and a possible interlocutory injunction application. The State's counsel says an injunction may be opposed. The IP makes directions in terms of a minute from the State, as amended by the IP at the hearing, to program the objection for hearing and determination.
(12) 1 April 2013 - LEL write to the IP to seek extension of time limits provided for in the "directions", but reaffirms that NAC's position is that there is no jurisdiction to hear the objection.
(13) 3 April 2013 - The SSO write to the IP opposing the request of LEL.
(14) 12 April 2013 - Second "directions hearing" before the IP. Counsel for NAC maintains the objection to jurisdiction and requests extension of time limits set to comply with the procedural "directions" made by the IP. This is on the basis that NAC has instructed its solicitors to take proceedings in the Federal Court. Counsel for the State opposes this. The IP varies directions but not to the extent requested NAC.
(15) 17 April 2013 - Originating application filed in the Federal Court. It seeks relief that the IP be restrained from hearing and determining the objection and interlocutory relief. At the request of NAC the Court lists the interlocutory injunction application and first directions hearings for 19 April 2013.
(16) 17 April 2013 - The application is supported by affidavits from Mr Holmes and Mr Stenson, the CEO of NAC. Mr Stenson at [6] explains that NAC wants the IP to be restrained from hearing and determining the objections as the "Applicant wishes to continue to consult and negotiate with the [State] to try and reach a mutually agreeable outcome about the proposed acquisition of the native title rights and interests that are held by the Applicant". At 7 Mr Stenson also explains that participation in the objection proceedings would be a costly exercise for NAC.
(17) 18 April 2013 - In the afternoon, counsel for the State confers with counsel for NAC. He suggests a way to obviate the need for a hearing of the injunction application, including the IP agreeing not to proceed with the hearing of the objection until the resolution of the Court proceedings and programming for an early hearing of the substantive application (the deferral proposal).
(18) 19 April 2013 - Attempts are made to carry the deferral proposal into effect, but there are difficulties from the IP being difficult to contact.
(19) 19 April 2013 - NAC files its submissions in support of the interlocutory injunction.
(20) 19 April 2013 - Consent orders are fashioned between the SSO and LEL, which are put to Gilmour J. The IP also is contacted and agrees in writing to the deferral proposal.
(21) 19 April 2013 - Consent orders made including that costs of the interlocutory injunction application are reserved.
(22) 8 May 2013 - NAC's outline of submissions are filed. The argument on the "constructional ground" is articulated at [128]-[132]. There is an absence of any suggestion that an objector had an effective veto under s 24MD(6B) of the NTA. There is also the submission that the State must comply with both the NTA and the LAA to lawfully take the land and all native title rights and interests.
(23) 16 May 2013 - The State's submissions are filed and served.
(24) 21 May 2013 - NAC's final submissions and submission in reply are filed (reply submission). The submissions make it clear that the State has misunderstood what NAC's position was and for this reason further explained what it was.
(25) 22 May 2013 - In the afternoon counsel for the State discusses the hearing with counsel for NAC. Amongst other things counsel for the State advises that the State will now be withdrawing the referral from the IP and thus there will be no objection before him for hearing and determination, and thus no matter for determination by the Court the following day.
(26) 23 May 2013 - The State, via the SSO, writes and emails the SSO letter to the IP.
(27) 23 May 2013 - The parties appear before the Court and the substantive hearing does not take place.
28 NAC submits that the SSO letter is the final act of the State's folly because, having referred the hearing of the objection on the basis of "good practice" it has now changed its mind on what it thinks constitutes "good practice". Further, NAC submits that it is also manifest that the State must have changed its mind on the law - to an acceptance of the argument made all along by NAC.
29 The contentions of NAC, in summary, are that the State took it on a frolic to the IP on the basis of what it then asserted was "good practice". It then conducted itself before the IP in such as way as to make it necessary for NAC to commence these proceedings to restrain the IP. The State vigorously opposed the Court application up to the day before hearing. Then the State decided to withdraw the referral from the IP. This, implicitly at least, must have involved acceptance that NAC's argument about the construction of the section was correct. That is, the withdrawal implicitly involved recognition that it could not lawfully refer the objection for hearing unless requested by an objector. Further, the State had by then taken a 180-degree turnaround on what it thought was "good practice". The State's conduct in taking NAC on this frolic was sheer folly - and its conduct was such that the State should be ordered to pay the costs of NAC on an indemnity basis.
30 I do not accept NAC's submissions that the State engaged in a folly.
31 At the previous hearing, senior counsel for the State explained the reason why the State withdrew the referral of this matter to the IP. It did so after it received and reviewed NAC's submissions in reply. These were received by the State late in the afternoon on 21 May 2013.
32 I was informed that the State's decision was made and communicated to the applicants (via their counsel) on the afternoon of 22 May 2013.
33 The State's submissions dated 15 May 2013 outlined what it understood to be the issues before the Court relating to the construction of s 24MD(6B) of the NTA. They involved three alternative construction arguments.
34 First, the State set out what it understood to be NAC's central contention; that s 24MD(6B)(f) requires that an objector request referral, and that if this does not occur a necessary precondition to the IP hearing and determining the objection has not occurred (the first construction).
35 Second, the State put a different construction of s 24MD to the effect that ss 24MD(6B)(d), (f) and (g) only require that there be an objection and an appointment of an independent person to hear and determine it (the second construction).
36 Third, the State put an alternative construction; if no request is made by an objector to the State to appoint an independent person to hear the objection, the State simply grants the title, or compulsorily acquires. If the objector does not request the State to appoint an independent person after consultation, the State simply proceeds to do the future act (the third construction).
37 Prior to receipt of NAC's submissions in reply, the State's understanding was that NAC advanced the first construction, opposed the second construction and did not advance the third construction.
38 When NAC's submissions in reply were reviewed, it emerged according to the understanding of the State, for the first time, that NAC did not advance the first construction, opposed the second construction and accepted the third construction.
39 When the State realised that there was common ground as to the third construction, and that NAC was not advancing the (inconsistent) first construction, there was no point in proceeding with the reference to the IP. Accordingly, the decision was made to withdraw the reference
40 The State contends that both parties are, in part, responsible for the misunderstanding by the State of NAC's position as to construction.