Multiplex Constructions Pty Limited v HSH Hotels
[2003] NSWSC 1069
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2003-09-24
Before
Bergin J, McClellan J
Source
Original judgment source is linked above.
Judgment (41 paragraphs)
Background 7 The building Works were to be completed in stages. Originally there were two Stages, defined in the Contract Particulars as: Stage 1: The Works excluding "Levels 9 to 25" but including all plant and equipment, plant areas, lifts and essential services (as described in the building approval) which are necessary for the commencement or completion of furnishing, fittings and equipment fitout works of Stamford Plaza Sydney. Stage 2: The balance of the Works not included in Stage 1. 8 In the Deed the definition of "Stages of Work" was amended to the following: Stage 1A: That part of the Works described as Stage 1A on the plan which is Part O to the Contract but also including all other areas, lifts and services (as described in the building approval) which are necessary for the commencement and/or the completion (as the case may be) of furnishings, fittings and equipment fitout works of that part of Stamford Plaza Sydney within Stage 1A however, in the case of particular areas of Stage 1A on a shared access basis, as more particularly described in the plan which is Part O to the contract. Stage 1B: That part of the Works described as Stage 1B on the plan which is Part O to the Contract but also including all other areas, lifts and services (as described in the building approval) which are necessary for the commencement and completion of furnishings, fittings and equipment fitout works of that part of Stamford Plaza Sydney within Stage 1B however, in the case of particular areas of Stage 1B on a shared access basis, as more particularly described in the plan which is Part O to the Contract. Stage 2: The balance of the Works not included in Stage 1A or 1B. 9 Part O to the Contract consisted of 11 drawings. Drawings 102 to 108 related to Basement Levels 5 to 1 inclusive, Ground Level and Level 1 respectively and were dated 16 March 1999. Drawings 109 to 112 related to Level 2; Levels 3 and 4; Level 5; and Levels 6, 7 and 8 respectively and were dated 21 December 1998. 10 Drawing 102 contained a legend of the colours on the drawings with a date next to each Stage. Stage 1A was coloured blue and dated 2 October 1999. Shared 1A was hatched blue and dated 2 October 1999. Stage 1B was coloured yellow and dated 16 October 1999. Shared 1B was hatched yellow and dated 16 October 1999. Stage 2 was blank, or white, and dated 30 October 1999. There was a problem with the colouring in of the various drawings in relation to the lifts numbered 1, 2 and 3. Although the lifts from the Ground to Level 8 should have been coloured blue for Stage 1A, they were coloured blue from Levels 1 to 8 but not on the Ground Level. 11 The Contract as amended provided for Completion as follows: For Stages 1A, 1B and 2: (a) the Builder has removed all rubbish associated with the Stage; (b) the Builder has removed all temporary accommodation and plant, equipment and work from the Stage. For Stages 1A and 1B: (a) the Builder can provide sufficient and continuous access to Stage 1A and 1B as the case may require of the Works to enable the Principal or Other Contractors engaged by the Principal to complete furniture, fixture and equipment fitout works including access to: (i) the offices of Stamford Plaza, Sydney located on the ground floor and basement car parking levels; (ii) ground floor including foyer/lobby/function rooms/restaurant/kitchens of Stamford Plaza, Sydney; and (iii) ground floor building manager's office of Stamford on Kent. (b) the Builder can provide sufficient and continuous access to Stamford Hotels and Resorts personnel for sales and marketing activities to existing and prospective clients of Stamford Hotels and Resorts. Sufficient access includes access to all levels of Stamford Plaza, Sydney and the ground floor foyer, ground floor restaurants, board room and function rooms, the health club and swimming pool on Level 1, the rooms located on Levels 1 to 8 (inclusive). If the builder complies with the access arrangements shown in the plan in Part O it will be deemed to have provided "sufficient and continuous access" under this paragraph (a) and (b). For Stage 2: (a) the Builder has procured the registration with the Land Titles Office of the Strata Documentation referred to in clauses 17.2 (a) and (c) and provided the Contract Administrator with three (3) copies of the Strata Documentation as registered; (b) the Builder has provided to the Contract Administrator a "handover package" for each strata unit in the Stage containing all instruction manuals, warranties and guarantees related to the items installed in the unit, all plugs for the sinks, baths and basins and 2 sets of keys for the entry doors, doors to balconies and the garages, security systems, letter boxes, unit doors, any house service doors and any loose items that should be handed over to the purchaser of any unit; (c) the Builder has provided the Contract Administrator with copies of all Approvals including those necessary to occupy and use the completed Works; (d) the Works have been satisfactorily commissioned and tested and all services and installations perform as required by the Contract; (e) the Builder has provided the Contract Administrator with all warranties relevant for the Works as required by clause 8.4; (f) the Builder has done everything necessary to procure the registration with the Land Titles Office of the Strata Documentation referred to in clause 17.2(b) (including procuring all the Approvals as referred to in clause 17.3(b) and, if required by the Principal, any pre-investigation by the Land Titles Office), except for lodging the Strata Documentation with the Land Titles Office and has provided the Strata Documentation to the Contract Administrator in registrable form; and (g) the Builder has provided the Contract Administrator with a Certificate of Classification pursuant to the Local Government (Approvals) Regulation 1993, Division 6 in respect of the Works; and (h) without limiting any obligation under clause 18.1, the items of finishes specified in the Schedule of Finishes (as defined in the Standard Contract for sale) have been installed as required by clause 42.1 of the Standard Contract for Sale for all apartments. 12 The dates for Completion under the Contract as amended were: for Stage 1A, 2 October 1999; for Stage 1B, 30 October 1999, and for Stage 2, 30 October 1999. 13 It was proposed that the Hotel would be operated by Stamford and that it would be equivalent to a hotel with a five-star rating. The Hotel had what has been referred to as its "hard opening" (accommodating guests), on 2 May 2000. The apartments were to be sold either off the plan or after Completion. Residents commenced occupying the apartments in March 2000. 14 By letter dated 14 April 2000 from Minter Ellison, solicitors for Multiplex, to Clayton Utz, the then solicitors for HSH and Stamford, and a response from Clayton Utz of 19 April 2000, the parties reached an agreement which can be conveniently summarized as follows: 1. Completion of the Works was deemed to have occurred on 28 March 2000; 2. Rectification of defects referred to in the agreed program for rectification was to occur by 30 April 2000 to allow a "hard opening" of the Hotel on 1 May 2000, with flexibility of implementation of the detail to be negotiated between Multiplex and Stamford; 3. Multiplex was to provide a program for rectification of the remaining listed defects in the apartments in Stage 2, subject to the program being provided by no later than 28 April 2000 and Multiplex agreeing that all of the defects which were to be included in the program were rectified by the end of May 2000; 4. Multiplex was to provide a program for rectification of the remaining listed defects in Stage 1A and 2 in the apartments by 28 April 2000 and to rectify those defects by the end of May 2000; 5. HSH would make no claim for liquidated damages beyond 28 March 2000; 6. If HSH incurred any general damages as a result of any failure by Multiplex to rectify defects in accordance with the Contract it would be entitled to recover those damages; and 7. Although Stamford would not then issue a Notice of Completion, the parties would proceed as if it had. 15 It was also noted between the parties that notwithstanding the deemed Completion arrangement, HSH would not be regarded as accepting that Completion could or should have occurred or did occur on a date earlier than 28 March 2000. It was also agreed that Multiplex was entitled to claim that Completion of each Stage and the Works as a whole occurred on dates prior to 28 March 2000. 16 At the hearing before the Referee, Multiplex claimed that Completion of Stage 1A had occurred as at 26 November 1999 and Completion of Stage 2 had occurred on 24 February 2000. HSH and Stamford claimed that neither Stage was completed prior to the deemed completion date of 28 March 2000. 17 The parties have accepted before me that the arguments put before the Referee in respect of the competing claims as to Completion can be summarized as follows. Multiplex argued: 1. The whole of the Works comprising Stage 1A and Stage 2 were complete; 2. Any defects which existed were minor and did not prevent the reasonable use of the Works or Stage and the correction of which did not prejudice the convenient use of the Works or Stage; 3. Lifts 1, 2 and 3 were not required to be completed for Stage 1A and that Lift 4 was capable of being used to access Stage 1A; 4. It was not required to provide the relevant Certificates for Stage 1A and that it had provided all relevant Certificates and warranties required for completion of Stage 2; 5. That it had satisfied all of the Completion Requirements. 18 HSH and Stamford argued: 1. Aspects of Works comprising Stage 1A and Stage 2 were incomplete; 2. There were defects which were not minor defects that prevented the Works or Stage from being reasonably capable of being used for the intended purpose of the Works or Stage and the correction of which prejudiced the convenient use of the works or Stage; 3. Lifts 1, 2 and 3 formed part of Stage 1A and were not completed in November 1999. They were not operational until 22 January 2000; 4. Multiplex had not provided all of the necessary Certificates pursuant to clause 13.1 of the Contract and had not provided all the necessary warranties pursuant to clause 8.4 of the Contract; and 5. Multiplex had not satisfied all of the Completion Requirements in the Part B Contract Particulars. 19 The Report is 418 pages in length and contains a most detailed record of the issues between the parties and the evidence given at the hearing before the Referee. The Referee concluded that Completion of Stage 1A occurred on 26 November 1999 and Completion of Stage 2 occurred on 24 February 2000. In both instances, those dates were said to be inclusive of all extensions of time to which Multiplex was entitled. 20 The Referee concluded that 75% of the securities retained by HSH should have been released no later than 2 May 2000 and the balance no later than 27 March 2001. The Referee also concluded that there were delays of 31 days in respect of Stage 1A and 66 days in respect of Stage 2. He found liquidated damages of $381,300 and $1,056,000 respectively, totalling $1,437,300 and recommended judgment be entered for Multiplex in the amount of $1,195,546, calculated as the balance owing under the Contract of $2,632,846 less liquidated damages of $1,437,300, plus interest on $1,195,546. 21 In his Report of 13 June 2003 the Referee recommended interest be awarded to Multiplex with entry of judgment for it in the amount of $1,860,486.70, inclusive of interest up to and including 28 May 2003. The Referee also recommended interest be awarded on the amount of $1,523,833.60 from 29 May 2003 to the date of entry of judgment. Applicable Legal Principles 22 These applications are made pursuant to Part 72, rule 13 of the Rules which provides: 13 (1) Where a report is made, the Court may, of its own motion, after notice to the parties, or on application by any party, on a matter of fact or law or both - (a) adopt, vary or reject the report in whole or in part; (b) require an explanation by way of report from the referee; (c) on any ground, remit for further consideration by the referee the whole or any part of the matter referred for a further report; (d) decide any matter on the evidence taken before the referee, with or without additional evidence, and shall give such judgment or make such order as the Court thinks fit. (2) Evidence additional to the evidence taken before the referee may not be adduced before the Court except with leave of the Court. 23 Whilst the discretion of the Court is wide it must be remembered that this is not an appeal. As Gleeson CJ said in Super Pty Limited v SJP Formwork (Aust) Pty Limited (1992) 29 NSWLR 549 at 563-564: It would be inconsistent with the object and purpose of the rules, and potentially productive of delay, expense and hardship, that the practical effect of appointing a referee should be simply to add an extra level to the hierarchy of decision-makers in a given case. … What is involved in an application under Pt 72, r 13 is not an appeal, whether by way of a hearing de novo or a more limited re-hearing. This is consistent with the right of the referee to conduct the reference as the referee thinks fit and unconstrained by the rules of evidence. Rather, the judge, in reviewing the report and deciding whether to adopt, vary or reject it, has a judicial discretion to exercise in a manner that is consistent both with the object and purpose of the rules and with the wider setting in which they take their place. That wider setting is a system for the administration of justice according to law. In so far as the subject matter of dissatisfaction with a referee's report is a question of law, or the application of legal standards to established facts, then a proper exercise of discretion would require a judge to consider and determine that matter afresh. That was decided by this Court in Homebush Abattoir Corporation v Bermria Pty Ltd (1991) 22 NSWLR 605: see also, Cape v Maidment (1991) 98 ACTR 1 at 4. That conclusion is entirely consistent with the history of the rule and the reasoning of the High Court in Buckley which, although the case related to different provisions is also instructive as to the present provisions. Subject to what has just been said, it is undesirable to attempt closely to confine the manner in which the discretion is to be exercised: cf Nicholls v Stamer [1980] VR 479 at 495 per Brooking J. The nature of the complaints made about the report, the type of litigation involved, and the length and complexity of proceedings before the referee, may all be relevant considerations. The purpose of Pt 72 is to provide, where the interests of justice so dictate, a form of partial resolution of disputes alternative to orthodox litigation, and it would frustrate that purpose to allow the reference to be treated as some kind of warm-up for the real contest. On the other hand, if the referee's report reveals some error of principle, some absence or excess of jurisdiction, or some patent misapprehension of the evidence, that would ordinarily be a reason for rejecting it: cf Jordan v McKenzie (1987) 26 CPC (2d) 193. So also would perversity or manifest unreasonableness in fact-finding. 24 As to the matter of manifest unreasonableness in fact finding Gleeson CJ agreed with the views of the trial judge, Giles J. In this regard Gleeson CJ said at 555 that Giles J: … rejected the submission that he was obliged to reconsider, and determine for himself, every issue of fact or law in respect of which the builder was dissatisfied with the decision of the referee. He considered that such an approach would render virtually futile the whole procedure of sending matters out to a referee, and was not required by the rules. On the contrary, his Honour approached the matter on the basis that he had a discretionary decision to make as to whether he adopted the referee's report in whole, or in part, and that, in making that decision, he, being satisfied that the referee had applied his mind to the task of fact finding required of him, carefully and in a manner consistent with legal principle, would not do more than ensure that the referee had addressed the appropriate questions, and that there was evidence capable of being accepted, which, if accepted, supported the findings of fact made. Grounds Relied Upon for Rejection of Reports 25 The following grounds were relied upon by HSH in support of its Motion for rejection of the Referee's Reports: