Attempting to follow the pattern of movements in the successive statement of claim
40 It is convenient to interpolate at this point some overview matters which required to be taken into consideration before examining in detail the attack on the ruling concerning the second bracket of claim and amendments.
41 It is certainly extremely difficult to follow the pattern of movements in the several propounded statements of claim and one finds in this exercise some real changes, often quite unexpected as far as I was concerned, as I travelled through the disparate documents. The point may be briefly made in the following non-exhaustive observations:
· The original statement of claim did not include any attempt to rely upon the related party sections of the Corporations Law. The 12 May 2003 version did include such an attempt.
· The original statement of claim did not seek to allege any representations made to the plaintiff and to the Chocolate Factory companies that the contract would include particular terms or that by the prospectuses, the second and third defendants represented certain matters to the plaintiff and to these companies which had issued the prospectuses. Nor did it allege that such representations were false or misleading, or were relied upon or that the Investor Vehicles, by reason of those representations and that conduct, had suffered loss and damage for which they were entitled to claim against the plaintiff, by reason whereof the plaintiff had suffered loss and damage. The 12 May 2003 version did include an attempt to so allege.
· The original statement of claim did not seek to allege that Westpoint, Mr Carey and Mr Beck had led the independent directors of the plaintiff to believe, or had knowingly permitted them to believe, that the 2000 contract, proposed to be executed [and in fact executed at the end of August 2000], was in the terms and to the effect of matters referred to in paragraphs 13 and 15 and in terms not less favourable to the plaintiff and the 1999 contract, so as to induce them to raise no objection to the Plaintiffs execution of the 2000 contract in late August. Nor did the original statement of claim seek to plead that Westpoint, Mr Carey and Mr Beck knew and the fact was that it was essential to the commercial viability of the Project that it include particular inclusions and finishes and be designed in particular fashion. The original statement of claim did not seek to plead that Westpoint, Mr Carey and Mr Beck procured the plaintiff to enter the 2000 contract on 31 August 2000 which they well knew did not reflect or provide for such matters, and well knew that the independent directors of the plaintiff did not know such matters. The 12 May version did seek to plead these matters as well as to plead the related party's provisions earlier referred to.
· Whereas the original statement of claim, as has already been indicated, sought to plead the Contract in bifurcated fashion giving particulars also to the Prospectuses, and the version sought to be propounded on 12 May 2003 included a paragraph in almost identical terms, by the time the 23 May 2003 version was drafted, the plaintiff was no longer pursuing any bifurcated version of the alleged Contract but was merely pleading the 31 August 2000 written contract. As already stated that approach has continued into the current version of the statement of claim.
42 Returning to the amendment sought by the second bracket, as will appear from the above general description of the anterior allegations, aside from the problematic and defectively pleaded paragraphs 30 (a) (b) and (c), the 23 May amendments included for the first-time, as I understand it, an allegation grounded upon the proposition that there had been legal wrongdoing concerning how it came about that the plaintiff had been caused to enter into the 31 August 2000 Contract. The 23 May version of the statement of claim squarely sought to allege inter alia:
"45 CA Management breached its obligations under the Management Agreement by:
(a) causing [the plaintiff] to enter into the Contract dated 31 August 2000…" [emphasis added]
43 Paragraph 45 CA then proceeded to include a number of sub paragraph is: (b)-(p). Apparently sub-paragraphs (g)-(o) were allowed, sub-paragraph (p) was not pressed. During argument yesterday counsel were not able to agree as to whether (b)-(f) were disallowed or withdrawn, it appearing from transcript 369 on the plaintiff's submissions before me that (b) and (c) were disallowed. The defendants before me asserted that (b)-(f) were withdrawn. During argument today transcript references and an explanation as to reformulated pleadings satisfied me that subparagraph (b) - (f) were in fact disallowed [see transcript 342.3, 342.34, 343.23, 363.34, 366.1, 366.42 - 369, 369.3, 369.12].
44 Notwithstanding this general muddle on the application before me it is clear enough that the central focus of the parties before me was on paragraph 45 CA sub paragraph (a).
45 The transcript of the argument of 23 May makes clear that the plaintiff's counsel before the referee, in being requested to identify how the plaintiff sought to put its case that the third defendant had breached its obligations under the Management Agreement by causing the plaintiff to enter into the later contract, furnished a long answer at transcript 255.41 - 256.40 in the following terms:
"Mr Gray: And the consequences of it. The last question I think was how was it caused. My answer, I think, was that it was signed by Mr Beck who had roles as directors of both Management and the plaintiff and by Mr Coleman who was a Management employee fulfilling the responsibilities of management under the management agreement in relation to the plaintiff's affairs.
The way in which the causation occurred can be explained by reference to documents in the folders, and, in a nutshell, the case will be put that the Westpoint interests were intending to seek changes to the 1999 contract from very early on in 2000.
On the plaintiff's side in August at least, Mr Church, as a director of the plaintiff, at a directors meeting expressed the view that there should be an independent review of the contractual documents between the plaintiff and Westpoint, particularly the construction contract. What then happened was that apparently a number - perhaps even three - of draft new contracts were prepared by Westpoint interests. They were given to Blake Dawson Waldron, a firm called MM Consulting, and Coudert Brothers for the purpose of obtaining advice and in particular some expression of view about the effect on, vis-à-vis, the plaintiff.
Reports were received from all of them. The Blake Dawson Waldron advice and the MM Consultant's advice were never disclosed to the plaintiff. Coudert Brothers gave a one-page advice, the terms of which were apparently unsatisfactory to Westpoint. They asked Coudert Brothers to change the terms of the advice. That was done and subsequently a copy of that one-page Coudert Brothers advice was given to the directors of the plaintiff. That happened after the second contract had been signed. The directors of the plaintiff never saw the second contract and never had any detailed explanation of what it did and how the plaintiff's interests were affected.
So that the background circumstances underlying the allegations in paragraph 34CA is that the second contract was entered into by the plaintiff through the actions of Management personnel, namely Mr Beck and Mr Coleman, in circumstances where its terms and effect have never been disclosed to, let alone approved by, the directors of the plaintiff."
46 The transcript then covers the referee putting to the plaintiff's counsel that his explanation "boils down… to an allegation of fraud on the part of at least Messrs Beck and Coleman." [Transcript 256.44]
47 The plaintiff's counsel responded by making the point that the word "fraud" had not been used in the proposed amendment of the statement of claim and submitting that it was not necessary for the plaintiff to plead fraud, adding: