Was there a "review opportunity" under the lease within s 13(5)? (Grounds 4-6)
64 MTAA submits that, upon finding that 2.86 per cent of the consideration paid pursuant to the Lease over the relevant period (representing approximately $2.74 million) was not reviewable, the Tribunal should have found that there was no "general review" of the consideration payable under the Lease, so as to be a "review opportunity" within s 13(5)(b) of the GST Transition Act.
65 It contends that the Tribunal erred in finding that in DB Rreef and Westley Nominees the Full Court confirmed that a review of "nearly all" of the consideration could be regarded as a general review of the whole of the consideration. As MTAA puts it, the ratio of the Full Courts can be found in the following extract from the judgment in Westley Nominees at [57]:
The concept of a "general review" for the purpose of para (b) of s 13(5) of the GST Transition Act requires a complete or almost universal consideration of the same subject: DB Rreef at [98] per Sackville J. The words "the consideration" refer to the whole of the consideration for the supply, not to a mere part of that consideration. (emphasis added)
and that those parts of the judgments in DB Rreef and Westley Nominees referring to a general review being "the whole or nearly all" and "nearly all" of the consideration were obiter statements.
66 MTAA submits that if those obiter statements reflect the law, the Tribunal erred in finding that if a "material" part of the consideration cannot be reviewed, there is no review opportunity. The proper approach, it says, is to apply a de minimis rule, to determine whether the amount is "so trifling in value or in amount as to be negligible", and had it done so the Tribunal should have found that the non-reviewable part of the consideration was not a de minimis amount. This, it submits, is consistent with the approach of the Full Court in Westley Nominees where the focus of the Court's discussion was on contributions to a promotion fund which represented some 0.53 per cent of the total amount paid. It is also, MTAA contends, consistent with the enquiry into fairness referred to by the Tribunal as a guide to what would constitute "nearly all".
67 MTAA submits that in undertaking this enquiry into fairness, the Tribunal erred in relying on the proportion of the GST liability on the non-reviewable component as compared to the total consideration paid, which improperly reduced the percentage to 0.26 per cent of the total consideration period. It observes that no such approach was undertaken or considered by the Full Court in DB Rreef or Westley Nominees, and that further, the Tribunal failed to have regard to the evidence that MTAA was exposed to an ongoing detriment through its liability to pay GST on all of the consideration while being entitled to recover only a smaller part from DFAT.
68 We do not accept these submissions.
69 The Tribunal, for the reasons it gave, concluded that "nearly all" of the consideration under the Lease was reviewable and, on that basis, a "review opportunity" arose under s 13(5). The Full Court in DB Rreef adopted the construction of the words "general review" articulated at first instance by Sackville J: "a complete or almost universal" consideration of the same subject. At [82] the Full Court employed a synonymous phrase "the whole or nearly all of the consideration for the supply". The Full Court in Westley Nominees again described "general review" in the terms employed by Sackville J. His Honour in DB Rreef at first instance at [98] arrived at that construction by attributing the ordinary dictionary meaning for the words "general review".
70 The Tribunal found that the amortisation amounts and statutory outgoings were not reviewable and that these non-reviewable components represented 2.86 per cent of the total consideration paid for supplies made during the relevant period. It seems that the correct percentage is 3.1 per cent but nothing turns on this difference nor was it contended otherwise. It also found that the GST liability in respect of the non-reviewable Lease consideration represented 0.26 per cent of the total consideration paid. Section 13(5)(b) of the GST Transition Act does not, for the following reasons, compel a different conclusion.
71 A "review opportunity" under s 13(5)(b) of the GST Transition Act, requires that the supplier have the opportunity to conduct a "general review" of the whole consideration. Here, the issue is whether the review opportunity afforded by the rent review process under the Lease was a "general" review. The word "general" qualifies the nature of the review and allows but does not require that the review be "universal". It is enough, as was held by Sackville J in DB Rreef, that it is "almost universal". It does not exclude only trivial or de minimis amounts of consideration. Such expressions are unjustifiable glosses on the meaning of "general" qualifying the word "review". They are also at odds with the meaning adopted by the Full Court in each of DB Rreef and Westley Nominees.
72 We are of the opinion that the Tribunal correctly approached the question of whether the rent review clause in issue gave rise to a "general" review by examining the proportion of the total consideration that is excluded from the review. It made the comparison by considering the 2.86 per cent figure. That it also considered the proportions by considering the 0.26 per cent figure did not detract from its first comparison. Had it considered only the 0.26 per cent figure, the position may have been different.
73 Contrary to MTAA's submissions, this approach of proportionality finds support in the Full Court decisions in DB Rreef and Westley Nominees.
74 In DB Rreef, the lessee was obliged to pay or reimburse the "operating costs". These constituted approximately 17 per cent of the consideration, and the Full Court at [82] found that "the fact that such a contribution could not be reviewed is fatal to the Commissioner's case because there is no review opportunity in relation to the whole or nearly all of the consideration for the supply …".
75 Likewise, in Westley Nominees, only the "base annual rent" was reviewable and amounts payable by the lessee for the "annual percentage rental", operating expenses, after hours charges and contributions to a promotion fund were not reviewable. In Westley Nominees, the base annual rent was 70.94 per cent of the overall rent, but only 51.94 per cent of the total consideration. The Full Court observed at [66] that:
[I]f all the elements of the consideration could be reviewed other than Coles' contribution to the promotion fund, then it would be open to conclude that the review was, nevertheless, a general review being a review of nearly all of the consideration. … However, where more than 48 per cent of the (whole of the) consideration is not open to review, it cannot be said that there has been an opportunity for a general review of the consideration for the supply.
76 The ratio in each of DB Rreef (2006) 152 FCR 437 and Westley Nominees is not constituted only by the passage in Westley Nominees at [57] relied upon by MTAA. Where it referred to the "whole of the consideration" in that passage the context was a rejection by the Full Court of the trial judge's reasons, which did not characterise all amounts to be paid as "the consideration" but implicitly found that there were two supplies such that the question of whether there was a "general review" did not require account to be taken of the lessee's contribution to outgoings as part of the consideration for the supply, namely, the lease. So much is apparent from [58] of the Full Court's judgment which immediately follows the passage relied on by MTAA as well as what is to be found at [66] to which we referred above.
77 In any event it is the whole of the consideration which is to be the subject of the review but, importantly, that review has only to be a general review. The consideration is the whole of the amounts payable under the Lease. It is not a requirement of s 13 that the question of whether or not a review is general is to be considered by an examination of the several components to each of which part of the consideration is attributed. Rather, it is the total amount of money payable which is the product of the consideration referable to those several components which must be generally reviewable.
78 The whole consideration under the Lease rounded up to the nearest dollar was $88,597,745. That part of the consideration, for amortisation and statutory outgoings, which was not reviewable, also rounded up to the nearest dollar amounted to $2,740,150. It is the product of the second of these figures expressed as a percentage of the whole consideration which is 3.1 per cent.
79 Doubtless minds could differ as to whether a review of approximately 97 per cent of the whole consideration supported a conclusion that "nearly all" of the consideration was reviewable. Nonetheless, the Tribunal, acknowledging as it did that approximately 3 per cent of the consideration was not reviewable, found, as a fact, that "nearly all" of the consideration under the Lease was reviewable and that this constituted the necessary "general" review amounting to a "review opportunity" for the purposes of s 13(5). This is a finding of fact that cannot be challenged in this Court. This raises the qualification to the fifth general proposition set out by the Full Court in Pozzolanic at 287-8. If the proper legal test has been identified giving the relevant statutory language its ordinary meaning, as is the case here, the question whether the facts as found fall within those words or not and where it is reasonably open to hold that they do, is a question of fact. Accordingly, no error of law is manifest because it might be said that on the material before the Tribunal different conclusions were open as to whether the identified test was satisfied or not. The contrary proposition on which MTAA's submissions implicitly relied, that it was not reasonably open to the Tribunal to conclude that an opportunity to review approximately 97 per cent of the whole consideration involved "a general review" of the consideration within the meaning of s 13(5), should not be accepted.
80 Grounds 4 to 6 fail.