ii. that no written notice of extension of time beyond 31 March 2004 had been given.
66 The balance of probabilities is in favour of a rejection of the evidence given by Mr Michael Roche that the matter of the issue of satisfaction of the conditions precedent had completely slipped his mind between 18 December 2003 and March 2004.
67 Hence the finding is that Roche was aware of circumstances giving rise to the right to rescind prior to 21 May 2004.
Whether Roche engaged in conduct, after becoming aware of circumstances giving rise to the right to rescind, between 31 March and 21 May 2004, justifiable only upon the footing that an election had been made to affirm the contract.
68 It is true that there is some difficulty in identifying the precise dates upon which particular site meetings were held and that one requires to be very cautious to travel through the evidence of a number of witnesses in order to actually tie down what was the date when a particular site meeting was held. The footnotes to Roche's submissions generally appear to establish the precise dates and to identify what is incorrect and what is in fact correct in the evidence of particular witnesses in that regard.
69 That having been said it remains the fact that particular Roche brothers did attend a number of site meetings and an examination of the evidence in relation to what occurred at those meetings does establish, as one would expect, that the discussions took place with regard to the continuing works.
70 As observed in the initial first instance judgment, there is absolutely no doubt but that both parties continued between 31 March 2004 and 21 May 2004 to conduct themselves as if the contract was still on foot.
71 The following evidence demonstrates that Roche continued to exercise rights under the Development Contract between 31 March 2004 and 21 May 2004:
i. on 1 April 2004 Raymond Yeo and Pino Accardo (Metro Edgley's consultant) attended a site meeting with Michael and Christopher Roche and Graham Jago of Nordon Jago (Roche's architect) and discussed the fitout tender, the Liquor Licence and the Roche financing for the Waterfront Brasserie [notes of the meeting appear at blue 3/872-873] ;
ii. on 7 April 2004 Christopher and William Roche attended at a meeting with Mr Accordo and Mr Mark Diblen, site manager for Metro at the Luna Park site. they were accompanied by the management team of the Unicorn Hotel in order to review the progress of the works and to give the management team and understanding of the location and premises for the Luna Park Bar.
iii. on 22 April 2004 Michael and Christopher Roche and Graham Jago attended a site meeting at the basement of the Waterfront Brasserie with Pino Accardo regarding the panels under the boardwalk. Mr Hindes was also in attendance. The meeting had been arranged by Mr Accordo so that Roche could review the high level awning windows of the Waterfront Brasserie and the existing timber boardwalk and in particular, a panel which had been inserted under the boardwalk. At that stage it was not determined on whether to insert a panels under the boardwalk has Roche wanted to maximise the view from the basement of the Waterfront Brasserie and the panels would obscure that view. At the meeting Michael Roche said to not put in the rest of the panels. ;
iv. in late April Pino Accardo had a discussion with Richard Stone of Nordon Jago regarding the tender drawings;
v. on 20 April 2004 Michael Roche had a conversation with Raymond Yeo concerning the Liquor Licence;
vi. on 23 April 2006 Michael Roche had a telephone discussion with Raymond Yeo regarding the development application for the fitout and the Place of Public Entertainment Licence ("POPE Licence");
vii. on 29 April 2004 Michael and Christopher Roche and Graham Jago attended a meeting at Multiplex's offices with Raymond Yeo, Mark Cogo of McKenzie Consulting and Ian Cady from JBA Urban Planning Consultants regarding the fitout development application;
viii. directly after that meeting and on the same day Michael and Christopher Roche and Graham Jago attended a meeting with Raymond Yeo, Mark Cogo, Ian Cady and Stephane Kerr and Nick Fterniatis from the Sydney Harbour Foreshore Authority regarding the fitout development application. The POPE calculations were discussed it being agreed that the council was in error and the statement being made that consent for the Development application could be finalised within a week. ;
ix. Directly after that meeting and on the same day Michael and Christopher Roche and Graham Jago attended a lunch with Raymond Yeo, Mark Cogo and Ian Cady at which the fitout tender and the Roche financing for the Waterfront Brasserie were progressed. Various matters were discussed including the Roche fitout Development Application, the status of the fitout tender, the fitout drawings and marketing for Roche;
x. Following that meeting Michael and Christopher Roche had a discussion with Mr Yeo during the course of which Mr Yeo asked the Roches to push Mr Jago on the tender and asked how funding with the Commonwealth Bank was position. Mr A Roche indicated that the Roche's were working on the feasibility report and asked for a further update of the status of Luna Park
xi. on 28 April 2004 Kalinda Cobby had two telephone discussions with Deborah Bailey (Metro Edgley's solicitor) relating to variations to the documents required under the Development Contract during which Ms Cobby requested on behalf of Roche that the second defendant pay the costs of the variations and provide a copy of the building model;
xii. on 30 April 2004 Metro Edgley's solicitors received an email from Kalinda Cobby regarding variations to documents required under the Development Contract;
xiii. on 4 May 2004 Michael Roche had a telephone discussion with Raymond Yeo regarding maximum seating capacities of the Waterfront Brasserie;
xiv. on 7 May 2004 Michael Roche had a telephone discussion with Raymond Yeo concerning the handover of the Waterfront Brasserie, site access, status of the Liquor Licence, proposed fitout presentation and status of fitout tendering and finance;
xv. in early May 2004 Michael and Christopher Roche attended a site meeting at the Waterfront Brasserie with Pino Accardo;
xvi. on 17 May 2004 Pino Accardo had a telephone discussion with Richard Stone concerning the tenderers for the fitout;
xvii. on 20 May 2004 Pino Accardo received a facsimile concerning the Waterfront Brasserie from Nordon Jago;
xviii. on 20 May 2004 Pino Accardo attended a site meeting at the Waterfront Brasserie with Richard Stone of Nordon Jago for a fitout tenderer inspection;
xix. on 21 May 2004 Deborah Bailey had a telephone discussion with Kalinda Cobby regarding payment of the costs for variations to the documents required under the Development Contract;
xx. Michael Roche gave evidence that he did not inform Nordon Jago of his view that the Development Contract was at an end and permitted Nordon Jago to continue to perform work as if the Development Contract was on foot;
xxi. Michael Roche gave evidence that between 31 March 2004 and 21 May 2004 he did not withdraw instructions from Kalinda Cobby and permitted her to continue implementing the Development Contract.
72 The conduct was unequivocal in terms of being justifiable only if an election had been made to affirm the contract.
The issues concerning the guarantors
The Court of Appeal
73 Each of Michael, Chris and William Roche [the Roche brothers], together with their parents Kevin and Gabrielle [the Roche parents], signed guarantees for Roche's obligations under the Development Contract, the Agreement for Sublease and the Fitout Deed.
74 The Court of Appeal observed that "there would be a real question as to whether the Guarantors remain bound" if Metro succeeds on the combination of conventional estoppel and election. The Court posed 2 issues for determination on the remitter:
i. are the relevant guarantors themselves bound by the relevant conventional estoppel; and
ii. are any other provisions of the guarantees sufficient to maintain liability of the guarantors notwithstanding that, but for a conventional estoppel as between Roche and Metro, the contract would have been automatically discharged.
75 On the pleadings before the Court for the first trial, the question of the guarantors' liability arose only by adjunct to Roche's claim for declarations that the Development Contract and Fitout Deed had been automatically rescinded on 31 March 2004.
76 On the pleadings now before the Court, the question of the guarantors' liability continues to arise in that fashion, but also by adjunct to Roche's claims for declarations that the Development Contract, Fitout Deed and Agreement for Sublease had been automatically rescinded on 31 December 2004 [and alternatively, in the case of the Agreement for Sublease, on 31 December 2003] or validly terminated on 4 January 2005. In addition, it arises by reason of the claim for damages against them as the Second Cross Defendants.
The present position
77 Metro has not succeeded in its case put in terms of conventional estoppel. Hence Metro has not succeeded on the combination of conventional estoppel and election.
78 The material contracts were automatically rescinded on 31 March 2004
79 There is not even a suggestion by Metro that the Roche parents had an involvement in Roche's conduct between 31 March and 21 May 2004 or could have played any part in the adoption of the material assumption by Metro.
The guarantee terms
80 The guarantees in each of the 3 agreements were, mutatis mutandis, in identical terms. Outside of the reliance placed upon sub clause (b), the only provisions in the guarantees which Metro suggests might maintain liability of the guarantors notwithstanding the automatic rescission are sub-clauses (d) and (i). Sub-clauses (d) and (i) , together with the introductory words of the guarantee provide: