CIRCUMSTANCES
5 On 23 December 2002, the Luna Park Reserve Trust (LPRT) entered into a Deed of Agreement for Lease and Sub-lease of the Luna Park Reserve to Luna Park Sydney Pty. Limited (LPS) and Metro, providing to the effect that Metro would develop Luna Park and that LPRT would then grant a lease of the site for forty years to LPS.
6 Included in the proposed development was the construction of a bar and brasserie, to be known as the Waterfront Brasserie.
7 In September 2003, Metro accepted an offer from Roche to purchase a forty-year lease of the Waterfront Brasserie for $18.5 million plus GST, under a transaction including the following elements:
1. Roche to enter a Development Contract with Metro for certain building works for the Waterside Brasserie in accordance with agreed plans (prepared to satisfy Roche's requirements).
2. Roche to provide the fit-out of the Waterside Brasserie at its cost.
3. Roche to pay $2 million on entry into the Development Contract, $11 million on Practical Completion of the building work, $4 million on Practical Completion of the fit-out, and the balance of $1.5 million on the granting of certain licences.
4. Roche to receive a sub-lease of the Waterside Brasserie from LPS for forty years (less one day) at a peppercorn rent.
5. Guarantees by the Guarantors.
8 On 26 September 2003, two agreements were entered into to give effect to this transaction:
(1) The Development Contract, involving Metro, Roche, the Guarantors and Multiplex, annexure A of which was a copy of an Agreement for Sub-lease between LPS, Roche, Metro and the Guarantors, signed by the parties other than LPS.
(2) The Fitout Deed, involving Roche, Metro and the Guarantors.
9 Broadly, the Development Contract provided for the design, construction and financing of building works for the Waterside Brasserie for the benefit of Roche, for a price of $13 million, with a deposit of $2 million to be paid on the date of the contract and the balance of $11 million to be paid on the "Settlement Date". "Settlement Date" is defined as 11am Sydney time ten business days after "Practical Completion", which is itself an expression given a definition in the Development Contract. Under the Development Contract, Practical Completion was required to take place before the "Sunset Date", defined in the Development Contract to be 31 December 2004, failing which Roche could by written notice to Metro terminate the Development Contract.
10 The Fitout Deed provided for the fitout of the Waterside Brasserie by Roche at its expense, and for Metro to provide various services to Roche in respect of liquor and other licenses for the premises for fees totalling $5.5 million. Roche was required to apply for all necessary consents as soon as practicable after the date of the Deed, and to cause the fitout to be carried out promptly after containing these consents; and subject to Metro providing access to the site, Roche was required to use its best endeavours to complete the fitout no later than 30 July 2004, as extended by a period no less than the number of days after 28 February 2004 until Practical Completion under the Development Contract occurred. That had the general effect of giving Roche about five months after Practical Completion to complete the fitout.
11 The Agreement for Sub-lease provided for the grant of a sub-lease from LPS to Roche on the "Commencing Date", defined as 5pm on the date ten business days after Practical Completion under the Development Contract, for a period of 40 years from the Commencing Date at a rent of $1 for the term.
12 The obligations of Roche under each of these agreements was guaranteed by the Guarantors.
13 Roche paid Metro $2 million on or about 26 September 2003, and from about late 2003 Metro proceeded to carry out work under the Development Contract.
14 Clause 2A of the Development Contract made the obligations of the parties under the Development Contract conditional on the satisfaction of certain conditions precedent, and provided that the Development Contract would "be deemed to be automatically rescinded and of no force and effect" if the conditions precedent were not satisfied by 31 December 2003 or such later date as Metro might notify Roche in writing up to the Sunset Date.
15 On 18 December 2003, Metro gave written notice to Roche that the date of 31 December 2003 in cl.2A of the Development Contract was extended to 31 March 2004; but it did not give any further such written notice until after 31 March 2004.
16 As at 31 March 2004, some of the conditions precedent referred to in cl.2A had not been satisfied; but between 31 March 2004 and 21 May 2004, building work continued in accordance with plans approved by Roche, and the solicitors for the parties continued to work towards satisfaction of the conditions precedent.
17 However, on 21 May 2004, Roche wrote to Metro stating that, because the conditions precedent provided in cl.2A of the Development Contract were not fulfilled by 31 March 2004, the Development Contract was rescinded at the expiration of the deadline of 31 March 2004 and that the Fitout Deed was also rescinded. Metro responded denying this.
18 The respondents then commenced proceedings in the Supreme Court seeking a declaration that the Development Contract and the Fitout Deed were of no force and effect, and seeking a refund of the deposit of $2 million. Metro and Multiplex cross-claimed for contrary declarations and for an order specifically enforcing the Development Contract.
19 On 30 August 2004, Einstein J made a declaration that the Development Contract was valid and subsisting, and made an order that the appellants specifically perform the Development Contract.
20 The respondents appealed from that decision, but the appeal was not heard until 17 December 2004; and in the meantime, Metro proceeded to seek to achieve Practical Completion under the Development Contract. The Court of Appeal reserved its decision after the hearing on 17 December 2004.
21 On 4 January 2005, Roche gave notice terminating the Development Contract, claiming that Practical Completion had not been reached by the Sunset Date.
22 On 3 March 2005, the Court of Appeal upheld the respondents' appeal from Einstein J's orders of 30 August 2004. The Court of Appeal decided that:
1. Clause 2A did have the effect that, if the conditions precedent were not satisfied by the date specified in clause 2A or such later date as Metro had notified in writing, the Development Contract was automatically rescinded without the requirement of notice.
2. Nothing occurred prior to 31 March 2004 to extend the relevant date, so (subject to questions of estoppel and election) the Development Contract came to an end immediately after 31 March 2004.
3. The conduct of the parties could have given rise to a conventional estoppel operating against automatic rescission, and Roche's conduct could have amounted to a binding election to affirm the contract.
23 Accordingly, the Court of Appeal set aside Einstein J's orders, and remitted the matter to the Equity Division to determine the issues concerning conventional estoppel and election, and also the liability of the Guarantors and the issue of specific performance.
24 On 2 September 2005, an application by the appellants for special leave to appeal from that Court of Appeal decision to the High Court of Australia was heard. The High Court indicated a firm view that the Supreme Court should proceed as required by the orders of the Court of Appeal, and dismissed the application, making costs of the application costs in the cause in the Equity Division.